Construction of 492 DUs of Affordable Housing Project at Bavla City under Pradhan Mantri Awas Yojna T.P 3 F.P 168
BAVLA NAGARPALIKA
T.P 3 F.P 168, Rasham Road, Nr. BaliyaDev temple
Approved
4th Jul 2019
Completed
28th May 2021
Registration No.
PR/GJ/AHMEDABAD/BAVLA/Others/RAA05640/EX1/280520
Acknowledgement No.
PR/AHMEDABAD/BAVLA/AHMEDABAD TPO/190515/006799
Project Type
Residential/Group Housing
Approving Authority
Bavla Municipality
District
Ahmedabad
Taluka
Bavla
State
Gujarat
Project Details
| Project Name | Construction of 492 DUs of Affordable Housing Project at Bavla City under Pradhan Mantri Awas Yojna T.P 3 F.P 168 |
| RERA Number | PR/GJ/AHMEDABAD/BAVLA/Others/RAA05640/EX1/280520 |
| Acknowledgement Number | PR/AHMEDABAD/BAVLA/AHMEDABAD TPO/190515/006799 |
| Project Description | Under Pradhan Mantri Awas Yojna 240 DUs are going to be constructed |
| Project Type | Residential/Group Housing |
| Project Status | Completed |
| District | Ahmedabad |
| Taluka | Bavla |
| Address | T.P 3 F.P 168, Rasham Road, Nr. BaliyaDev temple |
| Pincode | 382220 |
| State | Gujarat |
| Approving Authority | Bavla Municipality |
| Approved On | 2019-07-04 |
| Start Date | 2017-04-21 |
| End Date | 2021-05-28 |
| Submission Date | 2019-05-02 |
| Months Delayed | 0 |
Area & Cost Details
| Total Land Area | 14290.0 |
| Total Land Area (Registered) | 14290.0 |
| Total Covered Area | 6261.1 |
| Total Open Area | 8028.9 |
| Total Carpet Area | 8391.84 |
| Open Parking Area | 0 |
| Covered Parking Area | 4034.1 |
| Covered Parking Count | 20 |
| Parking for Sale Count | 0 |
| Cost of Land | 0 |
| Estimated Project Cost | 172512000 |
| Total Project Cost | 172512000 |
Land Details
| Moje | Bavla |
| TP No. | 3 |
| TP Name | Bavla |
Promoter Details
| Promoter Name | BAVLA NAGARPALIKA |
| Promoter Type | COMPETENT AUTHORITY/ GOVERNMENT |
| np_*****@yahoo.co.in | |
| Mobile | 98******** |
| Company Registration No. | NOTAPLICABLE |
| PAN | AAA******* |
| Date of Incorporation | 1994-04-15 |
| Experience (Years) | 5 |
| Area Constructed (sqm) | 29342 |
| Projects Completed | 2 |
| Ongoing Projects | 1 |
Promoter Partners
| Partner 1 | SIDDHARTH RAMBHAI PATEL |
| PAN | ASS******* |
| Address | Patel Vas, Opp. Ramji Mandir,, Maniyari, Patan |
Building Blocks
| A - Start Date | 2017-04-21 |
| A - End Date | 2021-05-28 |
| A - Progress | 100.0% |
| A - Booked Units | 12 |
| A - Unbooked Units | 0 |
| B - Start Date | 2017-04-21 |
| B - End Date | 2021-05-28 |
| B - Progress | 100.0% |
| B - Booked Units | 12 |
| B - Unbooked Units | 0 |
| C - Start Date | 2017-04-21 |
| C - End Date | 2021-05-28 |
| C - Progress | 100.0% |
| C - Booked Units | 12 |
| C - Unbooked Units | 0 |
| D - Start Date | 2017-04-21 |
| D - End Date | 2021-05-28 |
| D - Progress | 100.0% |
| D - Booked Units | 12 |
| D - Unbooked Units | 0 |
| E - Start Date | 2017-04-21 |
| E - End Date | 2021-05-28 |
| E - Progress | 100.0% |
| E - Booked Units | 12 |
| E - Unbooked Units | 0 |
| F - Start Date | 2017-04-21 |
| F - End Date | 2021-05-28 |
| F - Progress | 100.0% |
| F - Booked Units | 12 |
| F - Unbooked Units | 0 |
| G - Start Date | 2017-04-21 |
| G - End Date | 2021-05-28 |
| G - Progress | 100.0% |
| G - Booked Units | 12 |
| G - Unbooked Units | 0 |
| H - Start Date | 2017-04-21 |
| H - End Date | 2021-05-28 |
| H - Progress | 100.0% |
| H - Booked Units | 12 |
| H - Unbooked Units | 0 |
| I - Start Date | 2017-04-21 |
| I - End Date | 2021-05-28 |
| I - Progress | 100.0% |
| I - Booked Units | 12 |
| I - Unbooked Units | 0 |
| J - Start Date | 2017-04-21 |
| J - End Date | 2021-05-28 |
| J - Progress | 100.0% |
| J - Booked Units | 12 |
| J - Unbooked Units | 0 |
| K - Start Date | 2017-04-21 |
| K - End Date | 2021-05-28 |
| K - Progress | 100.0% |
| K - Booked Units | 12 |
| K - Unbooked Units | 0 |
| L - Start Date | 2017-04-21 |
| L - End Date | 2021-05-28 |
| L - Progress | 100.0% |
| L - Booked Units | 12 |
| L - Unbooked Units | 0 |
| M - Start Date | 2017-04-21 |
| M - End Date | 2021-05-28 |
| M - Progress | 100.0% |
| M - Booked Units | 12 |
| M - Unbooked Units | 0 |
| N - Start Date | 2017-04-21 |
| N - End Date | 2021-05-28 |
| N - Progress | 100.0% |
| N - Booked Units | 12 |
| N - Unbooked Units | 0 |
| O - Start Date | 2017-04-21 |
| O - End Date | 2021-05-28 |
| O - Progress | 100.0% |
| O - Booked Units | 12 |
| O - Unbooked Units | 0 |
| P - Start Date | 2017-04-21 |
| P - End Date | 2021-05-28 |
| P - Progress | 100.0% |
| P - Booked Units | 12 |
| P - Unbooked Units | 0 |
| Q - Start Date | 2017-04-21 |
| Q - End Date | 2021-05-28 |
| Q - Progress | 100.0% |
| Q - Booked Units | 12 |
| Q - Unbooked Units | 0 |
| R - Start Date | 2017-04-21 |
| R - End Date | 2021-05-28 |
| R - Progress | 100.0% |
| R - Booked Units | 12 |
| R - Unbooked Units | 0 |
| S - Start Date | 2017-04-21 |
| S - End Date | 2021-05-28 |
| S - Progress | 100.0% |
| S - Booked Units | 12 |
| S - Unbooked Units | 0 |
| T - Start Date | 2017-04-21 |
| T - End Date | 2021-05-28 |
| T - Progress | 100.0% |
| T - Booked Units | 12 |
| T - Unbooked Units | 0 |
Inventory Units
| Residential Units - Total Units | 96 |
| Residential Units - Carpet Area | 28.9 |
| Residential Units - Exclusive Area | 0.0 |
| Residential Units - Open Terrace Area | 784.92 |
| Residential Units - Total Units | 144 |
| Residential Units - Carpet Area | 39.01 |
| Residential Units - Exclusive Area | 0.0 |
| Residential Units - Open Terrace Area | 1307.9 |
Quarterly Progress
| September 2020 | 100.0% |
| June 2021 | 100.0% |
Professionals
| Architect | Kalpesh B. Mistry |
| Licence No. | CA/2010/48340 |
| Engineer | Gaurav B. Mistry |
| Licence No. | SD0487051120 |
| Contractor | M/S P. R Patel & co. |
The information provided on this page is collated from publicly available resources. PropTech Pulse does not guarantee the accuracy, completeness, or authority of this data and shall not be held liable for any discrepancies. For queries or further assistance, please contact us at pulse@aurumproptech.in