MANTHAN GREENS
DHAN INFRASTRUCTURE
MANTHAN GREENS, NR. RADHE ENCLAVE, VATVA - ROPDA ROAD, NEW VATVA
Approved
12th May 2022
Completed
31st Mar 2025
Registration No.
PR/GJ/AHMEDABAD/AHMEDABAD CITY/AUDA/MAA10184/120522
Acknowledgement No.
PR/AHMEDABAD/AHMEDABAD CITY/GUJRERA/220224/012402
Project Type
Mixed Development
Approving Authority
AUDA
District
Ahmedabad
Taluka
Ahmedabad City
State
Gujarat
Project Details
| Project Name | MANTHAN GREENS |
| RERA Number | PR/GJ/AHMEDABAD/AHMEDABAD CITY/AUDA/MAA10184/120522 |
| Acknowledgement Number | PR/AHMEDABAD/AHMEDABAD CITY/GUJRERA/220224/012402 |
| Project Description | RESIDENTIAL AND COMMERCIAL PROJECT |
| Project Type | Mixed Development |
| Project Status | Completed |
| District | Ahmedabad |
| Taluka | Ahmedabad City |
| Address | MANTHAN GREENS, NR. RADHE ENCLAVE, VATVA - ROPDA ROAD, NEW VATVA |
| State | Gujarat |
| Approving Authority | AUDA |
| Approved On | 2022-05-12 |
| Start Date | 2021-09-15 |
| End Date | 2025-03-31 |
| Submission Date | 2022-01-29 |
| Months Delayed | 0 |
Area & Cost Details
| Total Land Area | 5039.0 |
| Total Land Area (Registered) | 5039.0 |
| Total Covered Area | 2079.34 |
| Total Open Area | 2959.66 |
| Total Carpet Area | 4141.0 |
| Open Parking Area | 147.72 |
| Covered Parking Area | 0.0 |
| Covered Parking Count | 0 |
| Parking for Sale Count | 0 |
| Cost of Land | 28276500 |
| Estimated Project Cost | 111500000 |
| Total Project Cost | 158541245 |
Promoter Details
| Promoter Name | DHAN INFRASTRUCTURE |
| Promoter Type | PARTNERSHIP FIRM |
| dha*******@gmail.com | |
| Mobile | 81******** |
| Company Registration No. | GUJAH202743 |
| PAN | AAS******* |
| Date of Incorporation | 2021-04-01 |
Promoter Partners
| Partner 1 | DILIP KANUBHAI PATEL |
| PAN | AJI******* |
| Address | 18, SOLITAIRE BUNGALOWS, NR. MANAV RESIDENCY, SCIENCE CITY ROAD, SOLA |
| Partner 2 | ANKIT GHANSHYAMBHAI VAGHELA |
| PAN | AZJ******* |
| Address | B-2, SOLITAIRE DUPLEX, NR. MANAV RESIDENCY, SCIENCE CITY ROAD, SOLA |
| Partner 3 | HIRAL GAURAV PARIKH |
| PAN | AOO******* |
| Address | BUNGALOW 7, VRUNDAVAN-7, HEBATPUR ROAD,, NR. GULMOHAR PARTY PLOT, THALTEJ |
| Partner 4 | MANTHAN DILIPKUMAR PATEL |
| PAN | BUB******* |
| Address | PATELE VAS, DERIYA PARA,, VATVA, |
| Partner 5 | NIRAV JAYANTIBHAI PATEL |
| PAN | CBB******* |
| Address | 450, REVASADAN, OPP. BODAKDEV BALMANDIR, BODAKDEV GAM, BODAKDEV |
Building Blocks
| A - Start Date | 2021-09-15 |
| A - End Date | 2025-03-31 |
| A - Progress | 100.0% |
| A - Booked Units | 1 |
| A - Unbooked Units | 0 |
| B - Start Date | 2021-09-15 |
| B - End Date | 2025-03-31 |
| B - Progress | 57.14% |
| B - Booked Units | 4 |
| B - Unbooked Units | 3 |
| C - Start Date | 2021-09-15 |
| C - End Date | 2025-03-31 |
| C - Progress | 66.67% |
| C - Booked Units | 4 |
| C - Unbooked Units | 2 |
| D - Start Date | 2021-09-15 |
| D - End Date | 2025-03-31 |
| D - Progress | 100.0% |
| D - Booked Units | 1 |
| D - Unbooked Units | 0 |
| E - Start Date | 2021-09-15 |
| E - End Date | 2025-03-31 |
| E - Progress | 100.0% |
| E - Booked Units | 1 |
| E - Unbooked Units | 0 |
| F - Start Date | 2021-09-15 |
| F - End Date | 2025-03-31 |
| F - Progress | 28.57% |
| F - Booked Units | 2 |
| F - Unbooked Units | 5 |
| G - Start Date | 2021-09-15 |
| G - End Date | 2025-03-31 |
| G - Progress | 100.0% |
| G - Booked Units | 6 |
| G - Unbooked Units | 0 |
| H - Start Date | 2021-09-15 |
| H - End Date | 2025-03-31 |
| H - Progress | 100.0% |
| H - Booked Units | 1 |
| H - Unbooked Units | 0 |
| J - Start Date | 2021-09-15 |
| J - End Date | 2025-03-31 |
| J - Progress | 20.0% |
| J - Booked Units | 1 |
| J - Unbooked Units | 4 |
| K - Start Date | 2021-09-15 |
| K - End Date | 2025-03-31 |
| K - Progress | 40.0% |
| K - Booked Units | 2 |
| K - Unbooked Units | 3 |
Inventory Units
| RESIDENTIAL UNIT - Total Units | 30 |
| RESIDENTIAL UNIT - Carpet Area | 3882.0 |
| RESIDENTIAL UNIT - Exclusive Area | 183.6 |
| RESIDENTIAL UNIT - Open Terrace Area | 0.0 |
| COMMERCIAL SHOP - Total Units | 10 |
| COMMERCIAL SHOP - Carpet Area | 259.0 |
| COMMERCIAL SHOP - Exclusive Area | 0.0 |
| COMMERCIAL SHOP - Open Terrace Area | 0.0 |
Quarterly Progress
| October 2022 | 31.9% |
| January 2023 | 47.41% |
| April 2023 | 52.99% |
| July 2023 | 71.49% |
| October 2023 | 88.28% |
| January 2024 | 84.06% |
| April 2024 | 84.06% |
| July 2024 | 84.06% |
| October 2024 | 84.06% |
| April 2025 | 88.52% |
The information provided on this page is collated from publicly available resources. PropTech Pulse does not guarantee the accuracy, completeness, or authority of this data and shall not be held liable for any discrepancies. For queries or further assistance, please contact us at pulse@aurumproptech.in