SHREE HARI ENTERPRISE
OPP SHAYONA TILAK, VANDEMATRAM ROAD, GOTA
Approved
17th Nov 2017
Completed
31st Mar 2019
Registration No.
PR/GJ/AHMEDABAD/AHMEDABAD CITY/AUDA/MAA00751/EX1/060219
Acknowledgement No.
PR/AHMEDABAD/AHMADABAD CITY/AHMEDABAD TPO/170916/002056
Project Type
Mixed Development
Approving Authority
Ahmedabad Municipal Corporation
District
Ahmedabad
Taluka
Ahmedabad City
State
Gujarat
| Project Name | SHAYONA AAGMAN PHASE - I BLOCK D TO O |
| RERA Number | PR/GJ/AHMEDABAD/AHMEDABAD CITY/AUDA/MAA00751/EX1/060219 |
| Acknowledgement Number | PR/AHMEDABAD/AHMADABAD CITY/AHMEDABAD TPO/170916/002056 |
| Project Description | 2 & 3 BHK RESIDENTIAL APPARTMENT & SHOPS |
| Project Type | Mixed Development |
| Project Status | APPROVED |
| District | Ahmedabad |
| Taluka | Ahmedabad City |
| Address | OPP SHAYONA TILAK, VANDEMATRAM ROAD, GOTA |
| Pincode | 382481 |
| State | Gujarat |
| Approving Authority | Ahmedabad Municipal Corporation |
| Approved On | 2017-11-17 |
| Start Date | 2016-11-16 |
| End Date | 2019-03-31 |
| Submission Date | 2017-09-16 |
| Months Delayed | 0 |
| Total Land Area | 10548.0 |
| Total Covered Area | 3825.85 |
| Total Open Area | 4984.15 |
| Open Parking Area | 0 |
| Covered Parking Area | 3516.87 |
| Covered Parking Count | 306 |
| Parking for Sale Count | 0 |
| Cost of Land | 184386466 |
| Estimated Project Cost | 271557661 |
| Total Project Cost | 455944127 |
| Moje | Gota |
| TP No. | 33 |
| TP Name | Gota |
| Promoter Name | SHREE HARI ENTERPRISE |
| Promoter Type | PARTNERSHIP FIRM |
| shayona.aagman@gmail.com | |
| Mobile | 9825032729 |
| Company Registration No. | NOT APPLICABLE |
| PAN | ACYFS6302B |
| Experience (Years) | 25 |
| Area Constructed (sqm) | 36898 |
| Projects Completed | 0 |
| Ongoing Projects | 2 |
| Partner 1 | HARSHADBHAI B PATEL |
| Address | 7, ANMOL RESIDENCY III, NR SOLA BHAGWAT |
| Partner 2 | Bhavesh Patel |
| Address | 10 Shayona Kutir Bunglows, Nr. Bhagwat Vidhyapith, Sola |
| D - Start Date | 2016-11-16 |
| D - End Date | 2019-03-31 |
| D - Progress | 80.77% |
| D - Booked Units | 21 |
| D - Unbooked Units | 5 |
| E+F - Start Date | 2016-11-16 |
| E+F - End Date | 2019-03-31 |
| E+F - Progress | 50.0% |
| E+F - Booked Units | 20 |
| E+F - Unbooked Units | 20 |
| G+H - Start Date | 2016-11-16 |
| G+H - End Date | 2019-03-31 |
| G+H - Progress | 52.5% |
| G+H - Booked Units | 21 |
| G+H - Unbooked Units | 19 |
| I - Start Date | 2016-11-16 |
| I - End Date | 2019-03-31 |
| I - Progress | 40.0% |
| I - Booked Units | 8 |
| I - Unbooked Units | 12 |
| J - Start Date | 2016-11-16 |
| J - End Date | 2019-03-31 |
| J - Progress | 75.0% |
| J - Booked Units | 15 |
| J - Unbooked Units | 5 |
| K - Start Date | 2016-11-16 |
| K - End Date | 2019-03-31 |
| K - Progress | 55.0% |
| K - Booked Units | 11 |
| K - Unbooked Units | 9 |
| L+M - Start Date | 2016-11-16 |
| L+M - End Date | 2019-03-31 |
| L+M - Progress | 57.5% |
| L+M - Booked Units | 23 |
| L+M - Unbooked Units | 17 |
| N+O - Start Date | 2016-11-16 |
| N+O - End Date | 2019-03-31 |
| N+O - Progress | 82.5% |
| N+O - Booked Units | 33 |
| N+O - Unbooked Units | 7 |
| RESIDENTIAL AND COMMERCIAL UNITS - Total Units | 246 |
| RESIDENTIAL AND COMMERCIAL UNITS - Carpet Area | 14013.14 |
| RESIDENTIAL AND COMMERCIAL UNITS - Exclusive Area | 1221.22 |
| RESIDENTIAL AND COMMERCIAL UNITS - Open Terrace Area | 0.0 |
| April 2018 | 95.5% |
| April 2019 | 95.5% |
| April 2019 | 95.5% |
| Architect | TN OZA |
| Licence No. | CA/2016/75092 |
| Engineer | KETAVBHAI JOSHI |
| Licence No. | SD0042220721R3 |
| Contractor | Mohiyuddin Nathukhan Maniyar |