AAHNA BUILDSPACE - LLP
SHILP- SHALIGRAM , NEAR AHMEDABAD -1 MALL,, OPP :- SHABARI BUNGLOWS,
Approved
19th Dec 2018
Completed
30th Dec 2022
Registration No.
PR/GJ/AHMEDABAD/AHMEDABAD CITY/AUDA/RAA04413/A2R/261221
Acknowledgement No.
PR/AHMEDABAD/AHMEDABAD CITY/AHMEDABAD TPO/181123/006405
Project Type
Residential/Group Housing
Approving Authority
Ahmedabad Municipal Corporation
District
Ahmedabad
Taluka
Ahmedabad City
State
Gujarat
| Project Name | SHILP- SHALIGRAM |
| RERA Number | PR/GJ/AHMEDABAD/AHMEDABAD CITY/AUDA/RAA04413/A2R/261221 |
| Acknowledgement Number | PR/AHMEDABAD/AHMEDABAD CITY/AHMEDABAD TPO/181123/006405 |
| Project Description | RESIDENCE PROJECTR |
| Project Type | Residential/Group Housing |
| Project Status | APPROVED |
| District | Ahmedabad |
| Taluka | Ahmedabad City |
| Address | SHILP- SHALIGRAM , NEAR AHMEDABAD -1 MALL,, OPP :- SHABARI BUNGLOWS, |
| Pincode | 380052 |
| State | Gujarat |
| Approving Authority | Ahmedabad Municipal Corporation |
| Approved On | 2018-12-19 |
| Start Date | 2018-11-01 |
| End Date | 2022-12-30 |
| Submission Date | 2018-11-23 |
| Months Delayed | 0 |
| Total Land Area | 23257.0 |
| Total Land Area (Registered) | 23257.0 |
| Total Covered Area | 8301.5 |
| Total Open Area | 14955.5 |
| Total Carpet Area | 55365.82 |
| Open Parking Area | 0 |
| Covered Parking Area | 22642.26 |
| Covered Parking Count | 616 |
| Parking for Sale Count | 0 |
| Cost of Land | 2295603800 |
| Estimated Project Cost | 2140000000 |
| Total Project Cost | 4435603800 |
| Moje | Vastrapur |
| TP No. | 1 |
| TP Name | Vastrapur |
| Sub Plot No. | 1 |
| Promoter Name | AAHNA BUILDSPACE - LLP |
| Promoter Type | LIMITED LIABILITY PARTNERSHIP FIRM |
| account@shilp.co.in | |
| Mobile | 9825485927 |
| Company Registration No. | AAK5464 |
| PAN | ABJFA7677F |
| Experience (Years) | 0 |
| Area Constructed (sqm) | 102460 |
| Projects Completed | 0 |
| Ongoing Projects | 1 |
| Partner 1 | YASH G. BRAHMBHATT |
| Address | 05, MRUDUL SITADEL, JUDGES BUNGLOW ROAD,, BODEKDEV, AHMEDABAD |
| BLOCK A - Start Date | 2018-11-01 |
| BLOCK A - End Date | 2022-12-30 |
| BLOCK A - Progress | 100.0% |
| BLOCK A - Booked Units | 38 |
| BLOCK A - Unbooked Units | 0 |
| BLOCK B - Start Date | 2018-11-01 |
| BLOCK B - End Date | 2022-12-30 |
| BLOCK B - Progress | 97.37% |
| BLOCK B - Booked Units | 37 |
| BLOCK B - Unbooked Units | 1 |
| BLOCK C - Start Date | 2018-11-01 |
| BLOCK C - End Date | 2022-12-30 |
| BLOCK C - Progress | 97.37% |
| BLOCK C - Booked Units | 37 |
| BLOCK C - Unbooked Units | 1 |
| BLOCK D - Start Date | 2018-11-01 |
| BLOCK D - End Date | 2022-12-30 |
| BLOCK D - Progress | 97.37% |
| BLOCK D - Booked Units | 37 |
| BLOCK D - Unbooked Units | 1 |
| BLOCK E - Start Date | 2018-11-01 |
| BLOCK E - End Date | 2022-12-30 |
| BLOCK E - Progress | 100.0% |
| BLOCK E - Booked Units | 38 |
| BLOCK E - Unbooked Units | 0 |
| BLOCK F - Start Date | 2018-11-01 |
| BLOCK F - End Date | 2022-12-30 |
| BLOCK F - Progress | 100.0% |
| BLOCK F - Booked Units | 38 |
| BLOCK F - Unbooked Units | 0 |
| BLOCK G - Start Date | 2018-11-01 |
| BLOCK G - End Date | 2022-12-30 |
| BLOCK G - Progress | 92.11% |
| BLOCK G - Booked Units | 35 |
| BLOCK G - Unbooked Units | 3 |
| BLOCK H - Start Date | 2018-11-01 |
| BLOCK H - End Date | 2022-12-30 |
| BLOCK H - Progress | 63.16% |
| BLOCK H - Booked Units | 24 |
| BLOCK H - Unbooked Units | 14 |
| BLOCK I - Start Date | 2018-11-01 |
| BLOCK I - End Date | 2022-12-30 |
| BLOCK I - Progress | 100.0% |
| BLOCK I - Booked Units | 38 |
| BLOCK I - Unbooked Units | 0 |
| BLOCK J - Start Date | 2018-11-01 |
| BLOCK J - End Date | 2022-12-30 |
| BLOCK J - Progress | 100.0% |
| BLOCK J - Booked Units | 38 |
| BLOCK J - Unbooked Units | 0 |
| Residential - Total Units | 380 |
| Residential - Completed Units | 0 |
| Residential - Booked Units | 300 |
| Residential - Carpet Area | 55365.82 |
| Residential - Exclusive Area | 7577.01 |
| Residential - Open Terrace Area | 0.0 |
| May 2019 | 1.59% |
| August 2019 | 17.13% |
| November 2019 | 25.1% |
| February 2020 | 27.38% |
| August 2020 | 35.2% |
| November 2020 | 38.06% |
| February 2021 | 41.5% |
| May 2021 | 46.19% |
| August 2021 | 49.02% |
| November 2021 | 66.8% |
| February 2022 | 68.66% |
| May 2022 | 83.25% |
| August 2022 | 83.25% |
| January 2023 | 100.0% |
| Architect | APURVA R.AMIN |
| Licence No. | CA/2004/33949 |
| Engineer | NARESH K. SHAH |
| Licence No. | AMC-SD0092200821R3 |
| Contractor | TRINE PROJECTS LLP |