BANDHAN ARCADE

BANDHAN DEVELOPERS

BANDHAN ARCADE,MEGHRAJ ROAD, MODASA

Approved

15th Nov 2018

Completed

15th Apr 2021

Registration No.

PR/GJ/ARAVALLI/MODASA/Others/CAA04031/151118

Acknowledgement No.

PR/ARAVALLI/MODASA/ARAVALLI TPO/171009/003666

Project Type

Commercial

Approving Authority

Modasa Municipality

District

Aravalli

Taluka

Modasa

State

Gujarat

Project Details

Project NameBANDHAN ARCADE
RERA NumberPR/GJ/ARAVALLI/MODASA/Others/CAA04031/151118
Acknowledgement NumberPR/ARAVALLI/MODASA/ARAVALLI TPO/171009/003666
Project DescriptionCOMMERCIAL PROJECT
Project TypeCommercial
Project StatusAPPROVED
DistrictAravalli
TalukaModasa
AddressBANDHAN ARCADE,MEGHRAJ ROAD, MODASA
Pincode383315
StateGujarat
Approving AuthorityModasa Municipality
Approved On2018-11-15
Start Date2017-10-15
End Date2021-04-15
Submission Date2017-10-09
Months Delayed0

Area & Cost Details

Total Land Area3136.05
Total Covered Area1249.4
Total Open Area1886.65
Open Parking Area591.41
Covered Parking Area1207.25
Covered Parking Count1
Parking for Sale Count4
Cost of Land22000000
Estimated Project Cost56978290
Total Project Cost78978290

Land Details

MojeModasa

Promoter Details

Promoter NameBANDHAN DEVELOPERS
Promoter TypePARTNERSHIP FIRM
Emailbandhanarcademodasa@gmail.com
Mobile9099696133
Company Registration No.NOT APPLICABLE
PANAARFB7436N
Experience (Years)6
Area Constructed (sqm)3136
Projects Completed2
Ongoing Projects1

Promoter Partners

Partner 1KETULKUMAR DHANVANTARIKUMAR JAYSWAL
Address58,Gitanjali Soc.,Malpur Road, MODASA
Partner 2PATEL PIYUSHBHAI JYANTIBHAI
Address61,Patelfadi,Pahadpur, MODASA

Building Blocks

G1 - Start Date2017-10-15
G1 - End Date2021-04-15
G1 - Progress0.0%
G1 - Booked Units0
G1 - Unbooked Units1
G2 - Start Date2017-10-15
G2 - End Date2021-04-15
G2 - Progress0.0%
G2 - Booked Units0
G2 - Unbooked Units1
G3 - Start Date2017-10-15
G3 - End Date2021-04-15
G3 - Progress0.0%
G3 - Booked Units0
G3 - Unbooked Units1
G4 - Start Date2017-10-15
G4 - End Date2021-04-15
G4 - Progress0.0%
G4 - Booked Units0
G4 - Unbooked Units1
G5 - Start Date2017-10-15
G5 - End Date2021-04-15
G5 - Progress100.0%
G5 - Booked Units1
G5 - Unbooked Units0
G6 - Start Date2017-10-15
G6 - End Date2021-04-15
G6 - Progress100.0%
G6 - Booked Units1
G6 - Unbooked Units0
G7 - Start Date2017-10-15
G7 - End Date2021-04-15
G7 - Progress100.0%
G7 - Booked Units1
G7 - Unbooked Units0
G8 - Start Date2017-10-15
G8 - End Date2021-04-15
G8 - Progress100.0%
G8 - Booked Units1
G8 - Unbooked Units0
G9 - Start Date2017-10-15
G9 - End Date2021-04-15
G9 - Progress0.0%
G9 - Booked Units0
G9 - Unbooked Units1
G10 - Start Date2017-10-15
G10 - End Date2021-04-15
G10 - Progress0.0%
G10 - Booked Units0
G10 - Unbooked Units1
G11 - Start Date2017-10-15
G11 - End Date2021-04-15
G11 - Progress0.0%
G11 - Booked Units0
G11 - Unbooked Units1
G12 - Start Date2017-10-15
G12 - End Date2021-04-15
G12 - Progress0.0%
G12 - Booked Units0
G12 - Unbooked Units1
G12A - Start Date2017-10-15
G12A - End Date2021-04-15
G12A - Progress100.0%
G12A - Booked Units1
G12A - Unbooked Units0
G14 - Start Date2017-10-15
G14 - End Date2021-04-15
G14 - Progress0.0%
G14 - Booked Units0
G14 - Unbooked Units1
G15 - Start Date2017-10-15
G15 - End Date2021-04-15
G15 - Progress0.0%
G15 - Booked Units0
G15 - Unbooked Units1
G16 - Start Date2017-10-15
G16 - End Date2021-04-15
G16 - Progress0.0%
G16 - Booked Units0
G16 - Unbooked Units1
G17 - Start Date2017-10-15
G17 - End Date2021-04-15
G17 - Progress0.0%
G17 - Booked Units0
G17 - Unbooked Units1
G18 - Start Date2017-10-15
G18 - End Date2021-04-15
G18 - Progress0.0%
G18 - Booked Units0
G18 - Unbooked Units1
G19 - Start Date2017-10-15
G19 - End Date2021-04-15
G19 - Progress0.0%
G19 - Booked Units0
G19 - Unbooked Units1
G20 - Start Date2017-10-15
G20 - End Date2021-04-15
G20 - Progress0.0%
G20 - Booked Units0
G20 - Unbooked Units1
G21 - Start Date2017-10-15
G21 - End Date2021-04-15
G21 - Progress0.0%
G21 - Booked Units0
G21 - Unbooked Units1
G22 - Start Date2017-10-15
G22 - End Date2021-04-15
G22 - Progress100.0%
G22 - Booked Units1
G22 - Unbooked Units0
G23 - Start Date2017-10-15
G23 - End Date2021-04-15
G23 - Progress0.0%
G23 - Booked Units0
G23 - Unbooked Units1
G24 - Start Date2017-10-15
G24 - End Date2021-04-15
G24 - Progress100.0%
G24 - Booked Units1
G24 - Unbooked Units0
G25 - Start Date2017-10-15
G25 - End Date2021-04-15
G25 - Progress100.0%
G25 - Booked Units1
G25 - Unbooked Units0
G26 - Start Date2017-10-15
G26 - End Date2021-04-15
G26 - Progress100.0%
G26 - Booked Units1
G26 - Unbooked Units0
G27 - Start Date2017-10-15
G27 - End Date2021-04-15
G27 - Progress100.0%
G27 - Booked Units1
G27 - Unbooked Units0
G28 - Start Date2017-10-15
G28 - End Date2021-04-15
G28 - Progress100.0%
G28 - Booked Units1
G28 - Unbooked Units0
G29 - Start Date2017-10-15
G29 - End Date2021-04-15
G29 - Progress100.0%
G29 - Booked Units1
G29 - Unbooked Units0
G30 - Start Date2017-10-15
G30 - End Date2021-04-15
G30 - Progress100.0%
G30 - Booked Units1
G30 - Unbooked Units0
G31 - Start Date2017-10-15
G31 - End Date2021-04-15
G31 - Progress0.0%
G31 - Booked Units0
G31 - Unbooked Units1
G32 - Start Date2017-10-15
G32 - End Date2021-04-15
G32 - Progress0.0%
G32 - Booked Units0
G32 - Unbooked Units1
G33 - Start Date2017-10-15
G33 - End Date2021-04-15
G33 - Progress0.0%
G33 - Booked Units0
G33 - Unbooked Units1
G34 - Start Date2017-10-15
G34 - End Date2021-04-15
G34 - Progress0.0%
G34 - Booked Units0
G34 - Unbooked Units1
G35 - Start Date2017-10-15
G35 - End Date2021-04-15
G35 - Progress0.0%
G35 - Booked Units0
G35 - Unbooked Units1
G36 - Start Date2017-10-15
G36 - End Date2021-04-15
G36 - Progress0.0%
G36 - Booked Units0
G36 - Unbooked Units1
G37 - Start Date2017-10-15
G37 - End Date2021-04-15
G37 - Progress100.0%
G37 - Booked Units1
G37 - Unbooked Units0
G38 - Start Date2017-10-15
G38 - End Date2021-04-15
G38 - Progress0.0%
G38 - Booked Units0
G38 - Unbooked Units1
G39 - Start Date2017-10-15
G39 - End Date2021-04-15
G39 - Progress0.0%
G39 - Booked Units0
G39 - Unbooked Units1
G40 - Start Date2017-10-15
G40 - End Date2021-04-15
G40 - Progress0.0%
G40 - Booked Units0
G40 - Unbooked Units1
G41 - Start Date2017-10-15
G41 - End Date2021-04-15
G41 - Progress0.0%
G41 - Booked Units0
G41 - Unbooked Units1
F42 - Start Date2017-10-15
F42 - End Date2021-04-15
F42 - Progress100.0%
F42 - Booked Units1
F42 - Unbooked Units0
F43 - Start Date2017-10-15
F43 - End Date2021-04-15
F43 - Progress100.0%
F43 - Booked Units1
F43 - Unbooked Units0
F44 - Start Date2017-10-15
F44 - End Date2021-04-15
F44 - Progress0.0%
F44 - Booked Units0
F44 - Unbooked Units1
F45 - Start Date2017-10-15
F45 - End Date2021-04-15
F45 - Progress0.0%
F45 - Booked Units0
F45 - Unbooked Units1
F46 - Start Date2017-10-15
F46 - End Date2021-04-15
F46 - Progress100.0%
F46 - Booked Units1
F46 - Unbooked Units0
F47 - Start Date2017-10-15
F47 - End Date2021-04-15
F47 - Progress100.0%
F47 - Booked Units1
F47 - Unbooked Units0
F48 - Start Date2017-10-15
F48 - End Date2021-04-15
F48 - Progress100.0%
F48 - Booked Units1
F48 - Unbooked Units0
F49 - Start Date2017-10-15
F49 - End Date2021-04-15
F49 - Progress100.0%
F49 - Booked Units1
F49 - Unbooked Units0
F50 - Start Date2017-10-15
F50 - End Date2021-04-15
F50 - Progress100.0%
F50 - Booked Units1
F50 - Unbooked Units0
F51 - Start Date2017-10-15
F51 - End Date2021-04-15
F51 - Progress100.0%
F51 - Booked Units1
F51 - Unbooked Units0
F52 - Start Date2017-10-15
F52 - End Date2021-04-15
F52 - Progress0.0%
F52 - Booked Units0
F52 - Unbooked Units1
F53 - Start Date2017-10-15
F53 - End Date2021-04-15
F53 - Progress100.0%
F53 - Booked Units1
F53 - Unbooked Units0
F54 - Start Date2017-10-15
F54 - End Date2021-04-15
F54 - Progress100.0%
F54 - Booked Units1
F54 - Unbooked Units0
F55 - Start Date2017-10-15
F55 - End Date2021-04-15
F55 - Progress100.0%
F55 - Booked Units1
F55 - Unbooked Units0
F56 - Start Date2017-10-15
F56 - End Date2021-04-15
F56 - Progress0.0%
F56 - Booked Units0
F56 - Unbooked Units1
F57 - Start Date2017-10-15
F57 - End Date2021-04-15
F57 - Progress0.0%
F57 - Booked Units0
F57 - Unbooked Units1
F58 - Start Date2017-10-15
F58 - End Date2021-04-15
F58 - Progress0.0%
F58 - Booked Units0
F58 - Unbooked Units1
F59 - Start Date2017-10-15
F59 - End Date2021-04-15
F59 - Progress0.0%
F59 - Booked Units0
F59 - Unbooked Units1
F60 - Start Date2017-10-15
F60 - End Date2021-04-15
F60 - Progress0.0%
F60 - Booked Units0
F60 - Unbooked Units1
F61 - Start Date2017-10-15
F61 - End Date2021-04-15
F61 - Progress100.0%
F61 - Booked Units1
F61 - Unbooked Units0
F62 - Start Date2017-10-15
F62 - End Date2021-04-15
F62 - Progress100.0%
F62 - Booked Units1
F62 - Unbooked Units0
F63 - Start Date2017-10-15
F63 - End Date2021-04-15
F63 - Progress100.0%
F63 - Booked Units1
F63 - Unbooked Units0
F64 - Start Date2017-10-15
F64 - End Date2021-04-15
F64 - Progress100.0%
F64 - Booked Units1
F64 - Unbooked Units0
F65 - Start Date2017-10-15
F65 - End Date2021-04-15
F65 - Progress100.0%
F65 - Booked Units1
F65 - Unbooked Units0
F66 - Start Date2017-10-15
F66 - End Date2021-04-15
F66 - Progress100.0%
F66 - Booked Units1
F66 - Unbooked Units0
F67 - Start Date2017-10-15
F67 - End Date2021-04-15
F67 - Progress100.0%
F67 - Booked Units1
F67 - Unbooked Units0
F68 - Start Date2017-10-15
F68 - End Date2021-04-15
F68 - Progress100.0%
F68 - Booked Units1
F68 - Unbooked Units0
F69 - Start Date2017-10-15
F69 - End Date2021-04-15
F69 - Progress100.0%
F69 - Booked Units1
F69 - Unbooked Units0
F70 - Start Date2017-10-15
F70 - End Date2021-04-15
F70 - Progress100.0%
F70 - Booked Units1
F70 - Unbooked Units0
F71 - Start Date2017-10-15
F71 - End Date2021-04-15
F71 - Progress100.0%
F71 - Booked Units1
F71 - Unbooked Units0
F72 - Start Date2017-10-15
F72 - End Date2021-04-15
F72 - Progress0.0%
F72 - Booked Units0
F72 - Unbooked Units1
F73 - Start Date2017-10-15
F73 - End Date2021-04-15
F73 - Progress0.0%
F73 - Booked Units0
F73 - Unbooked Units1
F74 - Start Date2017-10-15
F74 - End Date2021-04-15
F74 - Progress0.0%
F74 - Booked Units0
F74 - Unbooked Units1
F75 - Start Date2017-10-15
F75 - End Date2021-04-15
F75 - Progress0.0%
F75 - Booked Units0
F75 - Unbooked Units1
F76 - Start Date2017-10-15
F76 - End Date2021-04-15
F76 - Progress0.0%
F76 - Booked Units0
F76 - Unbooked Units1
F77 - Start Date2017-10-15
F77 - End Date2021-04-15
F77 - Progress0.0%
F77 - Booked Units0
F77 - Unbooked Units1
F78 - Start Date2017-10-15
F78 - End Date2021-04-15
F78 - Progress100.0%
F78 - Booked Units1
F78 - Unbooked Units0
F79 - Start Date2017-10-15
F79 - End Date2021-04-15
F79 - Progress0.0%
F79 - Booked Units0
F79 - Unbooked Units1
F80 - Start Date2017-10-15
F80 - End Date2021-04-15
F80 - Progress0.0%
F80 - Booked Units0
F80 - Unbooked Units1
F81 - Start Date2017-10-15
F81 - End Date2021-04-15
F81 - Progress0.0%
F81 - Booked Units0
F81 - Unbooked Units1
F82 - Start Date2017-10-15
F82 - End Date2021-04-15
F82 - Progress0.0%
F82 - Booked Units0
F82 - Unbooked Units1
S1 - Start Date2017-10-15
S1 - End Date2021-04-15
S1 - Progress0.0%
S1 - Booked Units0
S1 - Unbooked Units1
S2 - Start Date2017-10-15
S2 - End Date2021-04-15
S2 - Progress0.0%
S2 - Booked Units0
S2 - Unbooked Units1
S3 - Start Date2017-10-15
S3 - End Date2021-04-15
S3 - Progress100.0%
S3 - Booked Units1
S3 - Unbooked Units0
S4 - Start Date2017-10-15
S4 - End Date2021-04-15
S4 - Progress100.0%
S4 - Booked Units1
S4 - Unbooked Units0
S5 - Start Date2017-10-15
S5 - End Date2021-04-15
S5 - Progress100.0%
S5 - Booked Units1
S5 - Unbooked Units0
S6 - Start Date2017-10-15
S6 - End Date2021-04-15
S6 - Progress100.0%
S6 - Booked Units1
S6 - Unbooked Units0
S7 - Start Date2017-10-15
S7 - End Date2021-04-15
S7 - Progress100.0%
S7 - Booked Units1
S7 - Unbooked Units0
S8 - Start Date2017-10-15
S8 - End Date2021-04-15
S8 - Progress0.0%
S8 - Booked Units0
S8 - Unbooked Units1
S9 - Start Date2017-10-15
S9 - End Date2021-04-15
S9 - Progress0.0%
S9 - Booked Units0
S9 - Unbooked Units1
S10 - Start Date2017-10-15
S10 - End Date2021-04-15
S10 - Progress0.0%
S10 - Booked Units0
S10 - Unbooked Units1
S11 - Start Date2017-10-15
S11 - End Date2021-04-15
S11 - Progress0.0%
S11 - Booked Units0
S11 - Unbooked Units1
S12 - Start Date2017-10-15
S12 - End Date2021-04-15
S12 - Progress0.0%
S12 - Booked Units0
S12 - Unbooked Units1
T1 - Start Date2017-10-15
T1 - End Date2021-04-15
T1 - Progress0.0%
T1 - Booked Units0
T1 - Unbooked Units1
T2 - Start Date2017-10-15
T2 - End Date2021-04-15
T2 - Progress0.0%
T2 - Booked Units0
T2 - Unbooked Units1
T3 - Start Date2017-10-15
T3 - End Date2021-04-15
T3 - Progress0.0%
T3 - Booked Units0
T3 - Unbooked Units1
T4 - Start Date2017-10-15
T4 - End Date2021-04-15
T4 - Progress0.0%
T4 - Booked Units0
T4 - Unbooked Units1
T5 - Start Date2017-10-15
T5 - End Date2021-04-15
T5 - Progress0.0%
T5 - Booked Units0
T5 - Unbooked Units1
T6 - Start Date2017-10-15
T6 - End Date2021-04-15
T6 - Progress0.0%
T6 - Booked Units0
T6 - Unbooked Units1
T7 - Start Date2017-10-15
T7 - End Date2021-04-15
T7 - Progress0.0%
T7 - Booked Units0
T7 - Unbooked Units1
T8 - Start Date2017-10-15
T8 - End Date2021-04-15
T8 - Progress0.0%
T8 - Booked Units0
T8 - Unbooked Units1
B1 - Start Date2017-10-15
B1 - End Date2021-04-15
B1 - Progress0.0%
B1 - Booked Units0
B1 - Unbooked Units1
B2 - Start Date2017-10-15
B2 - End Date2021-04-15
B2 - Progress0.0%
B2 - Booked Units0
B2 - Unbooked Units1
B3 - Start Date2017-10-15
B3 - End Date2021-04-15
B3 - Progress0.0%
B3 - Booked Units0
B3 - Unbooked Units1
B4 - Start Date2017-10-15
B4 - End Date2021-04-15
B4 - Progress0.0%
B4 - Booked Units0
B4 - Unbooked Units1
B5 - Start Date2017-10-15
B5 - End Date2021-04-15
B5 - Progress0.0%
B5 - Booked Units0
B5 - Unbooked Units1
B6 - Start Date2017-10-15
B6 - End Date2021-04-15
B6 - Progress0.0%
B6 - Booked Units0
B6 - Unbooked Units1
B7 - Start Date2017-10-15
B7 - End Date2021-04-15
B7 - Progress100.0%
B7 - Booked Units1
B7 - Unbooked Units0
B8 - Start Date2017-10-15
B8 - End Date2021-04-15
B8 - Progress100.0%
B8 - Booked Units1
B8 - Unbooked Units0

Inventory Units

SHOPS AND HALLS - Total Units102
SHOPS AND HALLS - Carpet Area3701.43
SHOPS AND HALLS - Exclusive Area0.0
SHOPS AND HALLS - Open Terrace Area0.0

Quarterly Progress

April 201950.47%
July 201950.47%
April 202054.57%
July 202055.78%
October 202056.48%
January 202157.18%
May 202161.51%

Professionals

ArchitectRAGHAV ARVINDBHAI PATEL
Licence No.CA/2007/40233
EngineerPATEL DIVYAKANT AMBALAL
Licence No.T.P./1/2/02
ContractorTRILOK CORPORATION

Top Properties in Surat

Pexo Icon

Ask Pulse Ai anything about real estate

Unlock the Latest in Real Estate

News, Infographics, Blogs & More! Delivered to your inbox.

Proptech Pulse Logo

Data that drives action.
Insight that inspires action.
Technology that empowers action.“

Made with Love

Statue

© PropTech Pulse 2026, All rights reserved.

Terms of Use and Privacy Policy