LAXMICHANDBHAI MAGANBHAI HAJIPURA PROPRIETORSHIP OF ADITYA BUILDSHAPE
R. S. No. 1355 (Old R.S. No.-802+803+804+805/1 Paiki 1), Behind Vivah Party Plot, Ahmedabad Highway, Palanpur
Approved
9th Oct 2020
Completed
30th Dec 2024
Registration No.
PR/GJ/BANASKANTHA/PALANPUR/Others/RAA07538/EX1/060724/301224
Acknowledgement No.
PR/BANASKANTHA/PALANPUR/GANDHINAGAR TPO/200919/009628
Project Type
Residential/Group Housing
Approving Authority
Palanpur Area Development Authority
District
Banaskantha
Taluka
Palanpur
State
Gujarat
| Project Name | ADITYA HEIGHTS -PHASE-I |
| RERA Number | PR/GJ/BANASKANTHA/PALANPUR/Others/RAA07538/EX1/060724/301224 |
| Acknowledgement Number | PR/BANASKANTHA/PALANPUR/GANDHINAGAR TPO/200919/009628 |
| Project Description | First time ever a superb combination of Lavish Bungalows and luxurious Flat at one Place at Palanpur City with glorious amenities. |
| Project Type | Residential/Group Housing |
| Project Status | APPROVED |
| District | Banaskantha |
| Taluka | Palanpur |
| Address | R. S. No. 1355 (Old R.S. No.-802+803+804+805/1 Paiki 1), Behind Vivah Party Plot, Ahmedabad Highway, Palanpur |
| State | Gujarat |
| Approving Authority | Palanpur Area Development Authority |
| Approved On | 2020-10-09 |
| Start Date | 2019-12-17 |
| End Date | 2024-12-30 |
| Submission Date | 2020-09-18 |
| Months Delayed | 0 |
| Total Land Area | 6634.0 |
| Total Land Area (Registered) | 5586.06 |
| Total Covered Area | 1608.18 |
| Total Open Area | 5025.82 |
| Total Carpet Area | 5746.52 |
| Open Parking Area | 142.55 |
| Covered Parking Area | 492.7 |
| Covered Parking Count | 1 |
| Parking for Sale Count | 8 |
| Cost of Land | 4146300 |
| Estimated Project Cost | 56000000 |
| Total Project Cost | 66491420 |
| Moje | Palanpur |
| Promoter Name | LAXMICHANDBHAI MAGANBHAI HAJIPURA PROPRIETORSHIP OF ADITYA BUILDSHAPE |
| Promoter Type | Individual/Propritorship |
| adityabuildshape1792@gmail.com | |
| Mobile | 8732912999 |
| PAN | AJBPP8754G |
| Date of Incorporation | 1945-10-29 |
| Experience (Years) | 5 |
| Area Constructed (sqm) | 3809 |
| Projects Completed | 0 |
| Ongoing Projects | 1 |
| A - Start Date | 2019-12-17 |
| A - End Date | 2024-12-29 |
| A - Progress | 100.0% |
| A - Booked Units | 7 |
| A - Unbooked Units | 0 |
| B - Start Date | 2019-12-17 |
| B - End Date | 2024-12-29 |
| B - Progress | 100.0% |
| B - Booked Units | 1 |
| B - Unbooked Units | 0 |
| C - Start Date | 2019-12-17 |
| C - End Date | 2024-12-29 |
| C - Progress | 100.0% |
| C - Booked Units | 3 |
| C - Unbooked Units | 0 |
| D - Start Date | 2019-12-17 |
| D - End Date | 2024-12-29 |
| D - Progress | 100.0% |
| D - Booked Units | 2 |
| D - Unbooked Units | 0 |
| E - Start Date | 2019-12-17 |
| E - End Date | 2024-12-29 |
| E - Progress | 33.33% |
| E - Booked Units | 1 |
| E - Unbooked Units | 2 |
| F - Start Date | 2019-12-17 |
| F - End Date | 2024-12-29 |
| F - Progress | 100.0% |
| F - Booked Units | 4 |
| F - Unbooked Units | 0 |
| G - Start Date | 2019-12-17 |
| G - End Date | 2024-12-29 |
| G - Progress | 100.0% |
| G - Booked Units | 3 |
| G - Unbooked Units | 0 |
| H - Start Date | 2019-12-17 |
| H - End Date | 2024-12-29 |
| H - Progress | 100.0% |
| H - Booked Units | 1 |
| H - Unbooked Units | 0 |
| I - Start Date | 2019-12-17 |
| I - End Date | 2024-12-29 |
| I - Progress | 100.0% |
| I - Booked Units | 1 |
| I - Unbooked Units | 0 |
| J - Start Date | 2019-12-17 |
| J - End Date | 2024-12-29 |
| J - Progress | 0.0% |
| J - Booked Units | 0 |
| J - Unbooked Units | 1 |
| K - Start Date | 2019-12-17 |
| K - End Date | 2024-12-29 |
| K - Progress | 100.0% |
| K - Booked Units | 1 |
| K - Unbooked Units | 0 |
| L - Start Date | 2019-12-17 |
| L - End Date | 2024-12-29 |
| L - Progress | 100.0% |
| L - Booked Units | 1 |
| L - Unbooked Units | 0 |
| M - Start Date | 2019-12-17 |
| M - End Date | 2024-12-29 |
| M - Progress | 100.0% |
| M - Booked Units | 1 |
| M - Unbooked Units | 0 |
| BLOCK-1 - Start Date | 2019-12-17 |
| BLOCK-1 - End Date | 2024-12-29 |
| BLOCK-1 - Progress | 85.71% |
| BLOCK-1 - Booked Units | 36 |
| BLOCK-1 - Unbooked Units | 6 |
| Residential Bungalows - Total Units | 29 |
| Residential Bungalows - Carpet Area | 1532.66 |
| Residential Bungalows - Exclusive Area | 0.0 |
| Residential Bungalows - Open Terrace Area | 0.0 |
| Residential Flats - Total Units | 42 |
| Residential Flats - Carpet Area | 2276.82 |
| Residential Flats - Exclusive Area | 540.33 |
| Residential Flats - Open Terrace Area | 0.0 |
| March 2021 | 19.22% |
| June 2021 | 22.7% |
| September 2021 | 24.78% |
| December 2021 | 28.78% |
| March 2022 | 31.46% |
| July 2022 | 36.53% |
| October 2022 | 40.58% |
| January 2023 | 43.68% |
| April 2023 | 51.51% |
| July 2023 | 57.5% |
| October 2023 | 61.22% |
| October 2024 | 83.34% |
| Architect | PARTH NARENDRASINGH VAGHELA |
| Licence No. | CA/2018/103323 |
| Engineer | PARTH SHAH CONSULTING ENGINEERS |
| Licence No. | SD0661220524 |