AKSHAR ICONS
AKSHAR INFRA
RS NO 347 VILLAGE ANDADA NEAR SAMRAJYA SCHOOL, ANKLESHWAR BHARUCH OLD NH 8, ANKLESHWAR
Approved
26th Feb 2018
Completed
30th Sept 2020
Registration No.
PR/GJ/BHARUCH/ANKLESVAR/Others/MAA01757/260218
Acknowledgement No.
PR/BHARUCH/ANKLESVAR/BHARUCH TPO/170929/003103
Project Type
Mixed Development
Approving Authority
Bharuch- Ankleshwar Urban Development Authority
District
Bharuch
Taluka
Anklesvar
State
Gujarat
Project Details
| Project Name | AKSHAR ICONS |
| RERA Number | PR/GJ/BHARUCH/ANKLESVAR/Others/MAA01757/260218 |
| Acknowledgement Number | PR/BHARUCH/ANKLESVAR/BHARUCH TPO/170929/003103 |
| Project Description | RESIDENTIAL CUM COMMERCIAL PROJECT WITH 92 SHOPS 112 FLATS 50 BUNGLOWS ON NON AGRI LAND RS NO 347 VILLAGE ANDADA ANKLESHWAR |
| Project Type | Mixed Development |
| Project Status | Completed |
| District | Bharuch |
| Taluka | Anklesvar |
| Address | RS NO 347 VILLAGE ANDADA NEAR SAMRAJYA SCHOOL, ANKLESHWAR BHARUCH OLD NH 8, ANKLESHWAR |
| Pincode | 393010 |
| State | Gujarat |
| Approving Authority | Bharuch- Ankleshwar Urban Development Authority |
| Approved On | 2018-02-26 |
| Start Date | 2014-09-25 |
| End Date | 2020-09-30 |
| Submission Date | 2017-09-29 |
| Months Delayed | 0 |
Area & Cost Details
| Total Land Area | 16000.0 |
| Total Covered Area | 4895.0 |
| Total Open Area | 11105.0 |
| Open Parking Area | 2298 |
| Covered Parking Area | 836.0 |
| Covered Parking Count | 56 |
| Parking for Sale Count | 160 |
| Cost of Land | 16430032 |
| Estimated Project Cost | 255189000 |
| Total Project Cost | 271619032 |
Land Details
| Moje | Andada |
Promoter Details
| Promoter Name | AKSHAR INFRA |
| Promoter Type | PARTNERSHIP FIRM |
| aks***********@gmail.com | |
| Mobile | 98******** |
| Company Registration No. | GUJ VDD 23275 |
| PAN | ABB******* |
| Experience (Years) | 15 |
| Area Constructed (sqm) | 14608 |
| Projects Completed | 3 |
| Ongoing Projects | 1 |
Promoter Partners
| Partner 1 | Arjanbhai Nanjibhai Vaghasia |
| Address | 23-24, Ved Gurukul Road,, Narayan Muni Nagar |
Building Blocks
| F1+F2 - Start Date | 2014-09-25 |
| F1+F2 - End Date | 2020-09-30 |
| F1+F2 - Progress | 10.0% |
| F1+F2 - Booked Units | 6 |
| F1+F2 - Unbooked Units | 54 |
| F3+F4 - Start Date | 2014-09-25 |
| F3+F4 - End Date | 2020-09-30 |
| F3+F4 - Progress | 73.33% |
| F3+F4 - Booked Units | 44 |
| F3+F4 - Unbooked Units | 16 |
| F5+F6 - Start Date | 2014-09-25 |
| F5+F6 - End Date | 2020-09-30 |
| F5+F6 - Progress | 70.0% |
| F5+F6 - Booked Units | 42 |
| F5+F6 - Unbooked Units | 18 |
| F7 - Start Date | 2014-09-25 |
| F7 - End Date | 2020-09-30 |
| F7 - Progress | 83.33% |
| F7 - Booked Units | 20 |
| F7 - Unbooked Units | 4 |
| 1 - Start Date | 2014-09-25 |
| 1 - End Date | 2020-09-30 |
| 1 - Progress | 0.0% |
| 1 - Booked Units | 0 |
| 1 - Unbooked Units | 1 |
| 2 - Start Date | 2014-09-25 |
| 2 - End Date | 2020-09-30 |
| 2 - Progress | 100.0% |
| 2 - Booked Units | 1 |
| 2 - Unbooked Units | 0 |
| 3 - Start Date | 2014-09-25 |
| 3 - End Date | 2020-09-30 |
| 3 - Progress | 100.0% |
| 3 - Booked Units | 1 |
| 3 - Unbooked Units | 0 |
| 4 - Start Date | 2014-09-25 |
| 4 - End Date | 2020-09-30 |
| 4 - Progress | 100.0% |
| 4 - Booked Units | 1 |
| 4 - Unbooked Units | 0 |
| 5 - Start Date | 2014-09-25 |
| 5 - End Date | 2020-09-30 |
| 5 - Progress | 100.0% |
| 5 - Booked Units | 1 |
| 5 - Unbooked Units | 0 |
| 6 - Start Date | 2014-09-25 |
| 6 - End Date | 2020-09-30 |
| 6 - Progress | 100.0% |
| 6 - Booked Units | 1 |
| 6 - Unbooked Units | 0 |
| 7 - Start Date | 2014-09-25 |
| 7 - End Date | 2020-09-30 |
| 7 - Progress | 100.0% |
| 7 - Booked Units | 1 |
| 7 - Unbooked Units | 0 |
| 8 - Start Date | 2014-09-25 |
| 8 - End Date | 2020-09-30 |
| 8 - Progress | 100.0% |
| 8 - Booked Units | 1 |
| 8 - Unbooked Units | 0 |
| 9 - Start Date | 2014-09-25 |
| 9 - End Date | 2020-09-30 |
| 9 - Progress | 100.0% |
| 9 - Booked Units | 1 |
| 9 - Unbooked Units | 0 |
| 10 - Start Date | 2014-09-25 |
| 10 - End Date | 2020-09-30 |
| 10 - Progress | 0.0% |
| 10 - Booked Units | 0 |
| 10 - Unbooked Units | 1 |
| 11 - Start Date | 2014-09-25 |
| 11 - End Date | 2020-09-30 |
| 11 - Progress | 100.0% |
| 11 - Booked Units | 1 |
| 11 - Unbooked Units | 0 |
| 12 - Start Date | 2014-09-25 |
| 12 - End Date | 2020-09-30 |
| 12 - Progress | 100.0% |
| 12 - Booked Units | 1 |
| 12 - Unbooked Units | 0 |
| 13 - Start Date | 2014-09-25 |
| 13 - End Date | 2020-09-30 |
| 13 - Progress | 100.0% |
| 13 - Booked Units | 1 |
| 13 - Unbooked Units | 0 |
| 14 - Start Date | 2014-09-25 |
| 14 - End Date | 2020-09-30 |
| 14 - Progress | 100.0% |
| 14 - Booked Units | 1 |
| 14 - Unbooked Units | 0 |
| 15 - Start Date | 2014-09-25 |
| 15 - End Date | 2020-09-30 |
| 15 - Progress | 100.0% |
| 15 - Booked Units | 1 |
| 15 - Unbooked Units | 0 |
| 16 - Start Date | 2014-09-25 |
| 16 - End Date | 2020-09-30 |
| 16 - Progress | 100.0% |
| 16 - Booked Units | 1 |
| 16 - Unbooked Units | 0 |
| 17 - Start Date | 2014-09-25 |
| 17 - End Date | 2020-09-30 |
| 17 - Progress | 100.0% |
| 17 - Booked Units | 1 |
| 17 - Unbooked Units | 0 |
| 18 - Start Date | 2014-09-25 |
| 18 - End Date | 2020-09-30 |
| 18 - Progress | 100.0% |
| 18 - Booked Units | 1 |
| 18 - Unbooked Units | 0 |
| 19 - Start Date | 2014-09-25 |
| 19 - End Date | 2020-09-30 |
| 19 - Progress | 100.0% |
| 19 - Booked Units | 1 |
| 19 - Unbooked Units | 0 |
| 20 - Start Date | 2014-09-25 |
| 20 - End Date | 2020-09-30 |
| 20 - Progress | 100.0% |
| 20 - Booked Units | 1 |
| 20 - Unbooked Units | 0 |
| 21 - Start Date | 2014-09-25 |
| 21 - End Date | 2020-09-30 |
| 21 - Progress | 100.0% |
| 21 - Booked Units | 1 |
| 21 - Unbooked Units | 0 |
| 22 - Start Date | 2014-09-25 |
| 22 - End Date | 2020-09-30 |
| 22 - Progress | 100.0% |
| 22 - Booked Units | 1 |
| 22 - Unbooked Units | 0 |
| 23 - Start Date | 2014-09-25 |
| 23 - End Date | 2020-09-30 |
| 23 - Progress | 100.0% |
| 23 - Booked Units | 1 |
| 23 - Unbooked Units | 0 |
| 24 - Start Date | 2014-09-25 |
| 24 - End Date | 2020-09-30 |
| 24 - Progress | 100.0% |
| 24 - Booked Units | 1 |
| 24 - Unbooked Units | 0 |
| 25 - Start Date | 2014-09-25 |
| 25 - End Date | 2020-09-30 |
| 25 - Progress | 100.0% |
| 25 - Booked Units | 1 |
| 25 - Unbooked Units | 0 |
| 26 - Start Date | 2014-09-25 |
| 26 - End Date | 2020-09-30 |
| 26 - Progress | 100.0% |
| 26 - Booked Units | 1 |
| 26 - Unbooked Units | 0 |
| 27 - Start Date | 2014-09-25 |
| 27 - End Date | 2020-09-30 |
| 27 - Progress | 100.0% |
| 27 - Booked Units | 1 |
| 27 - Unbooked Units | 0 |
| 28 - Start Date | 2014-09-25 |
| 28 - End Date | 2020-09-30 |
| 28 - Progress | 100.0% |
| 28 - Booked Units | 1 |
| 28 - Unbooked Units | 0 |
| 29 - Start Date | 2014-09-25 |
| 29 - End Date | 2020-09-30 |
| 29 - Progress | 100.0% |
| 29 - Booked Units | 1 |
| 29 - Unbooked Units | 0 |
| 30 - Start Date | 2014-09-25 |
| 30 - End Date | 2020-09-30 |
| 30 - Progress | 100.0% |
| 30 - Booked Units | 1 |
| 30 - Unbooked Units | 0 |
| 31 - Start Date | 2014-09-25 |
| 31 - End Date | 2020-09-30 |
| 31 - Progress | 100.0% |
| 31 - Booked Units | 1 |
| 31 - Unbooked Units | 0 |
| 32 - Start Date | 2014-09-25 |
| 32 - End Date | 2020-09-30 |
| 32 - Progress | 100.0% |
| 32 - Booked Units | 1 |
| 32 - Unbooked Units | 0 |
| 33 - Start Date | 2014-09-25 |
| 33 - End Date | 2020-09-30 |
| 33 - Progress | 100.0% |
| 33 - Booked Units | 1 |
| 33 - Unbooked Units | 0 |
| 34 - Start Date | 2014-09-25 |
| 34 - End Date | 2020-09-30 |
| 34 - Progress | 100.0% |
| 34 - Booked Units | 1 |
| 34 - Unbooked Units | 0 |
| 35 - Start Date | 2014-09-25 |
| 35 - End Date | 2020-09-30 |
| 35 - Progress | 100.0% |
| 35 - Booked Units | 1 |
| 35 - Unbooked Units | 0 |
| 36 - Start Date | 2014-09-25 |
| 36 - End Date | 2020-09-30 |
| 36 - Progress | 100.0% |
| 36 - Booked Units | 1 |
| 36 - Unbooked Units | 0 |
| 37 - Start Date | 2014-09-25 |
| 37 - End Date | 2020-09-30 |
| 37 - Progress | 100.0% |
| 37 - Booked Units | 1 |
| 37 - Unbooked Units | 0 |
| 38 - Start Date | 2014-09-25 |
| 38 - End Date | 2020-09-30 |
| 38 - Progress | 100.0% |
| 38 - Booked Units | 1 |
| 38 - Unbooked Units | 0 |
| 39 - Start Date | 2014-09-25 |
| 39 - End Date | 2020-09-30 |
| 39 - Progress | 100.0% |
| 39 - Booked Units | 1 |
| 39 - Unbooked Units | 0 |
| 40 - Start Date | 2014-09-25 |
| 40 - End Date | 2020-09-30 |
| 40 - Progress | 100.0% |
| 40 - Booked Units | 1 |
| 40 - Unbooked Units | 0 |
| 41 - Start Date | 2014-09-25 |
| 41 - End Date | 2020-09-30 |
| 41 - Progress | 0.0% |
| 41 - Booked Units | 0 |
| 41 - Unbooked Units | 1 |
| 42 - Start Date | 2014-09-25 |
| 42 - End Date | 2020-09-30 |
| 42 - Progress | 100.0% |
| 42 - Booked Units | 1 |
| 42 - Unbooked Units | 0 |
| 43 - Start Date | 2014-09-25 |
| 43 - End Date | 2020-09-30 |
| 43 - Progress | 100.0% |
| 43 - Booked Units | 1 |
| 43 - Unbooked Units | 0 |
| 44 - Start Date | 2014-09-25 |
| 44 - End Date | 2020-09-30 |
| 44 - Progress | 100.0% |
| 44 - Booked Units | 1 |
| 44 - Unbooked Units | 0 |
| 45 - Start Date | 2014-09-25 |
| 45 - End Date | 2020-09-30 |
| 45 - Progress | 0.0% |
| 45 - Booked Units | 0 |
| 45 - Unbooked Units | 1 |
| 46 - Start Date | 2014-09-25 |
| 46 - End Date | 2020-09-30 |
| 46 - Progress | 100.0% |
| 46 - Booked Units | 1 |
| 46 - Unbooked Units | 0 |
| 47 - Start Date | 2014-09-25 |
| 47 - End Date | 2020-09-30 |
| 47 - Progress | 100.0% |
| 47 - Booked Units | 1 |
| 47 - Unbooked Units | 0 |
| 48 - Start Date | 2014-09-25 |
| 48 - End Date | 2020-09-30 |
| 48 - Progress | 100.0% |
| 48 - Booked Units | 1 |
| 48 - Unbooked Units | 0 |
| 49 - Start Date | 2014-09-25 |
| 49 - End Date | 2020-09-30 |
| 49 - Progress | 100.0% |
| 49 - Booked Units | 1 |
| 49 - Unbooked Units | 0 |
| 50 - Start Date | 2014-09-25 |
| 50 - End Date | 2020-09-30 |
| 50 - Progress | 100.0% |
| 50 - Booked Units | 1 |
| 50 - Unbooked Units | 0 |
Inventory Units
| INCOMPLETE SHOPS FLATS BUNGLOWS - Total Units | 0 |
| INCOMPLETE SHOPS FLATS BUNGLOWS - Carpet Area | 12137.55 |
| INCOMPLETE SHOPS FLATS BUNGLOWS - Exclusive Area | 594.51 |
| INCOMPLETE SHOPS FLATS BUNGLOWS - Open Terrace Area | 2128.0 |
Quarterly Progress
| July 2018 | 79.51% |
| October 2018 | 85.29% |
| January 2019 | 89.79% |
| April 2019 | 90.8% |
| July 2019 | 92.51% |
| October 2019 | 94.9% |
| January 2020 | 95.59% |
| April 2020 | 100.0% |
| October 2020 | 100.0% |
Professionals
| Architect | AAJ ASSOCIATES |
| Licence No. | BAUDA ARCH 01 |
| Engineer | SVN CONSULTING ENGINEER |
| Licence No. | BAUDA L STR 04 GRADE 1 |
| Contractor | BHUMI BUILDERS |
The information provided on this page is collated from publicly available resources. PropTech Pulse does not guarantee the accuracy, completeness, or authority of this data and shall not be held liable for any discrepancies. For queries or further assistance, please contact us at pulse@aurumproptech.in