MUNICIPAL CORPORATION OF BHAVNAGAR
TP 03 RUVA FP 109, BHAVNAGAR
Approved
29th Nov 2019
Completed
15th Dec 2023
Registration No.
PR/GJ/BHAVNAGAR/BHAVNAGAR/Others/MAA06407/EX1/300123
Acknowledgement No.
PR/BHAVNAGAR/BHAVNAGAR/BHAVNAGAR TPO/190821/007938
Project Type
Mixed Development
Approving Authority
Bhavnagar Municipal Corporation
District
Bhavnagar
Taluka
Bhavnagar
State
Gujarat
| Project Name | 2489 EWS 1 PMAY FP 109 |
| RERA Number | PR/GJ/BHAVNAGAR/BHAVNAGAR/Others/MAA06407/EX1/300123 |
| Acknowledgement Number | PR/BHAVNAGAR/BHAVNAGAR/BHAVNAGAR TPO/190821/007938 |
| Project Description | TP 3 RUVA FP 109 CONSTRUCTION OF 728 UNIT AND 27 SHOP |
| Project Type | Mixed Development |
| Project Status | APPROVED |
| District | Bhavnagar |
| Taluka | Bhavnagar |
| Address | TP 03 RUVA FP 109, BHAVNAGAR |
| Pincode | 364002 |
| State | Gujarat |
| Approving Authority | Bhavnagar Municipal Corporation |
| Approved On | 2019-11-29 |
| Start Date | 2019-02-15 |
| End Date | 2023-12-15 |
| Submission Date | 2019-08-13 |
| Months Delayed | 0 |
| Total Land Area | 11282.0 |
| Total Land Area (Registered) | 11282.0 |
| Total Covered Area | 4656.0 |
| Total Open Area | 6626.0 |
| Total Carpet Area | 21910.0 |
| Open Parking Area | 270 |
| Covered Parking Area | 4420.0 |
| Covered Parking Count | 7 |
| Parking for Sale Count | 3 |
| Cost of Land | 0 |
| Estimated Project Cost | 458381906 |
| Total Project Cost | 458381906 |
| Moje | Ruva |
| TP No. | 3 |
| TP Name | Ruva |
| Sub Plot No. | - + - |
| Promoter Name | MUNICIPAL CORPORATION OF BHAVNAGAR |
| Promoter Type | COMPETENT AUTHORITY/ GOVERNMENT |
| bmctownplanningfp16a@gmail.com | |
| Mobile | 9825836369 |
| Company Registration No. | NA |
| PAN | AAALM1064C |
| Date of Incorporation | 1982-02-14 |
| Experience (Years) | 0 |
| Area Constructed (sqm) | 257707 |
| Projects Completed | 6 |
| Ongoing Projects | 17 |
| Partner 1 | NITESHKUMAR BACHUBHAI VADHVANIYA |
| PAN | ACIPV0316J |
| Address | 311/B AADARSH SOCIETY, VIJAYRAJNAGAR BHAVNAGAR |
| A - Start Date | 2019-02-15 |
| A - End Date | 2023-12-15 |
| A - Progress | 86.15% |
| A - Booked Units | 56 |
| A - Unbooked Units | 9 |
| B - Start Date | 2019-02-15 |
| B - End Date | 2023-12-15 |
| B - Progress | 86.15% |
| B - Booked Units | 56 |
| B - Unbooked Units | 9 |
| C - Start Date | 2019-02-15 |
| C - End Date | 2023-12-15 |
| C - Progress | 86.15% |
| C - Booked Units | 56 |
| C - Unbooked Units | 9 |
| D - Start Date | 2019-02-15 |
| D - End Date | 2023-12-15 |
| D - Progress | 100.0% |
| D - Booked Units | 56 |
| D - Unbooked Units | 0 |
| E - Start Date | 2019-02-15 |
| E - End Date | 2023-12-15 |
| E - Progress | 100.0% |
| E - Booked Units | 56 |
| E - Unbooked Units | 0 |
| F - Start Date | 2019-02-15 |
| F - End Date | 2023-12-15 |
| F - Progress | 100.0% |
| F - Booked Units | 56 |
| F - Unbooked Units | 0 |
| G - Start Date | 2019-02-15 |
| G - End Date | 2023-12-15 |
| G - Progress | 100.0% |
| G - Booked Units | 56 |
| G - Unbooked Units | 0 |
| H - Start Date | 2019-02-15 |
| H - End Date | 2023-12-15 |
| H - Progress | 100.0% |
| H - Booked Units | 56 |
| H - Unbooked Units | 0 |
| I - Start Date | 2019-02-15 |
| I - End Date | 2023-12-15 |
| I - Progress | 100.0% |
| I - Booked Units | 56 |
| I - Unbooked Units | 0 |
| J - Start Date | 2019-02-15 |
| J - End Date | 2023-12-15 |
| J - Progress | 100.0% |
| J - Booked Units | 56 |
| J - Unbooked Units | 0 |
| K - Start Date | 2019-02-15 |
| K - End Date | 2023-12-15 |
| K - Progress | 100.0% |
| K - Booked Units | 56 |
| K - Unbooked Units | 0 |
| L - Start Date | 2019-02-15 |
| L - End Date | 2023-12-15 |
| L - Progress | 100.0% |
| L - Booked Units | 56 |
| L - Unbooked Units | 0 |
| M - Start Date | 2019-02-15 |
| M - End Date | 2023-12-15 |
| M - Progress | 100.0% |
| M - Booked Units | 56 |
| M - Unbooked Units | 0 |
| MIXED DEVELOPMENT - Total Units | 755 |
| MIXED DEVELOPMENT - Carpet Area | 21910.0 |
| MIXED DEVELOPMENT - Exclusive Area | 0.0 |
| MIXED DEVELOPMENT - Open Terrace Area | 0.0 |
| April 2020 | 32.79% |
| July 2020 | 38.85% |
| October 2020 | 44.36% |
| January 2021 | 50.93% |
| April 2021 | 57.73% |
| July 2021 | 60.68% |
| October 2021 | 62.81% |
| January 2022 | 63.01% |
| April 2022 | 63.36% |
| July 2022 | 63.55% |
| October 2022 | 64.06% |
| January 2023 | 65.05% |
| April 2023 | 66.62% |
| July 2023 | 70.47% |
| October 2023 | 71.0% |
| Contractor | SHANTI CONSTRUCTION CO |