MUNICIPAL CORPORATION OF BHAVNAGAR
TP 08 RUVA, FP 33A
Approved
28th Nov 2019
Completed
15th Dec 2023
Registration No.
PR/GJ/BHAVNAGAR/BHAVNAGAR/Others/MAA06398/EX1/120523
Acknowledgement No.
PR/BHAVNAGAR/BHAVNAGAR/BHAVNAGAR TPO/190821/007939
Project Type
Mixed Development
Approving Authority
Bhavnagar Municipal Corporation
District
Bhavnagar
Taluka
Bhavnagar
State
Gujarat
| Project Name | 2489 EWS 1 PMAY FP 33A |
| RERA Number | PR/GJ/BHAVNAGAR/BHAVNAGAR/Others/MAA06398/EX1/120523 |
| Acknowledgement Number | PR/BHAVNAGAR/BHAVNAGAR/BHAVNAGAR TPO/190821/007939 |
| Project Description | TP 8 RUVA FP 33A CONSTRUCTION OF 294 UNITS AND 32 SHOPS |
| Project Type | Mixed Development |
| Project Status | APPROVED |
| District | Bhavnagar |
| Taluka | Bhavnagar |
| Address | TP 08 RUVA, FP 33A |
| Pincode | 364005 |
| State | Gujarat |
| Approving Authority | Bhavnagar Municipal Corporation |
| Approved On | 2019-11-28 |
| Start Date | 2019-02-15 |
| End Date | 2023-12-15 |
| Submission Date | 2019-08-13 |
| Months Delayed | 0 |
| Total Land Area | 5653.0 |
| Total Land Area (Registered) | 5653.0 |
| Total Covered Area | 2060.0 |
| Total Open Area | 3593.0 |
| Total Carpet Area | 9136.0 |
| Open Parking Area | 319 |
| Covered Parking Area | 1512.0 |
| Covered Parking Count | 3 |
| Parking for Sale Count | 3 |
| Cost of Land | 0 |
| Estimated Project Cost | 194842666 |
| Total Project Cost | 194842666 |
| Moje | Ruva |
| TP No. | 8 |
| TP Name | Ruva |
| Sub Plot No. | 33/A |
| Promoter Name | MUNICIPAL CORPORATION OF BHAVNAGAR |
| Promoter Type | COMPETENT AUTHORITY/ GOVERNMENT |
| bmctownplanningfp16a@gmail.com | |
| Mobile | 9825836369 |
| Company Registration No. | NA |
| PAN | AAALM1064C |
| Date of Incorporation | 1982-02-14 |
| Experience (Years) | 0 |
| Area Constructed (sqm) | 257707 |
| Projects Completed | 6 |
| Ongoing Projects | 17 |
| Partner 1 | NITESHKUMAR BACHUBHAI VADHVANIYA |
| PAN | ACIPV0316J |
| Address | 311/B AADARSH SOCIETY, VIJAYRAJNAGAR BHAVNAGAR |
| A - Start Date | 2019-02-15 |
| A - End Date | 2023-12-15 |
| A - Progress | 84.0% |
| A - Booked Units | 42 |
| A - Unbooked Units | 8 |
| B - Start Date | 2019-02-15 |
| B - End Date | 2023-12-15 |
| B - Progress | 87.5% |
| B - Booked Units | 56 |
| B - Unbooked Units | 8 |
| C - Start Date | 2019-02-15 |
| C - End Date | 2023-12-15 |
| C - Progress | 87.5% |
| C - Booked Units | 56 |
| C - Unbooked Units | 8 |
| D - Start Date | 2019-02-15 |
| D - End Date | 2023-12-15 |
| D - Progress | 84.0% |
| D - Booked Units | 42 |
| D - Unbooked Units | 8 |
| G - Start Date | 2019-02-15 |
| G - End Date | 2023-12-15 |
| G - Progress | 100.0% |
| G - Booked Units | 56 |
| G - Unbooked Units | 0 |
| H - Start Date | 2019-02-15 |
| H - End Date | 2023-12-15 |
| H - Progress | 100.0% |
| H - Booked Units | 42 |
| H - Unbooked Units | 0 |
| Residential - Total Units | 294 |
| Residential - Completed Units | 0 |
| Residential - Booked Units | 0 |
| Residential - Carpet Area | 8702.4 |
| Residential - Exclusive Area | 496.86 |
| Residential - Open Terrace Area | 0.0 |
| Shop - Total Units | 32 |
| Shop - Completed Units | 0 |
| Shop - Booked Units | 0 |
| Shop - Carpet Area | 433.96 |
| Shop - Exclusive Area | 0.0 |
| Shop - Open Terrace Area | 0.0 |
| April 2020 | 38.14% |
| July 2020 | 41.01% |
| October 2020 | 45.03% |
| January 2021 | 52.97% |
| April 2021 | 63.08% |
| July 2021 | 65.1% |
| October 2021 | 66.96% |
| January 2022 | 67.4% |
| April 2022 | 68.39% |
| July 2022 | 68.67% |
| October 2022 | 69.15% |
| January 2023 | 70.07% |
| July 2023 | 79.79% |
| October 2023 | 79.79% |
| January 2024 | 100.0% |
| Contractor | SHANTI CONSTRUCTION CO |