SHIVANAND INFRACON PRIVATE LIMITED
plot no 11, c/o sukhsanti residency,fulsar, bhavnagar
Approved
9th Feb 2018
Completed
30th Mar 2021
Registration No.
PR/GJ/BHAVNAGAR/BHAVNAGAR/Others/MAA01588/EX1/221019
Acknowledgement No.
PR/BHAVNAGAR/BHAVNAGAR/BHAVNAGAR TPO/170731/000963
Project Type
Mixed Development
Approving Authority
Bhavnagar Municipal Corporation
District
Bhavnagar
Taluka
Bhavnagar
State
Gujarat
| Project Name | upavandarshan 4 |
| RERA Number | PR/GJ/BHAVNAGAR/BHAVNAGAR/Others/MAA01588/EX1/221019 |
| Acknowledgement Number | PR/BHAVNAGAR/BHAVNAGAR/BHAVNAGAR TPO/170731/000963 |
| Project Description | resident cum commercial |
| Project Type | Mixed Development |
| Project Status | APPROVED |
| District | Bhavnagar |
| Taluka | Bhavnagar |
| Address | plot no 11, c/o sukhsanti residency,fulsar, bhavnagar |
| Pincode | 364004 |
| State | Gujarat |
| Approving Authority | Bhavnagar Municipal Corporation |
| Approved On | 2018-02-09 |
| Start Date | 2016-10-05 |
| End Date | 2021-03-30 |
| Submission Date | 2017-07-31 |
| Months Delayed | 0 |
| Total Land Area | 459.39 |
| Total Covered Area | 206.14 |
| Total Open Area | 253.25 |
| Open Parking Area | 262.65 |
| Covered Parking Area | 133.44 |
| Covered Parking Count | 1 |
| Parking for Sale Count | 1 |
| Cost of Land | 1450000 |
| Estimated Project Cost | 12000000 |
| Total Project Cost | 13450000 |
| Moje | Fulsar |
| Sub Plot No. | A - 11 |
| Promoter Name | SHIVANAND INFRACON PRIVATE LIMITED |
| Promoter Type | COMPANY |
| shivanandinfracon@yahoo.in | |
| Mobile | 9898007677 |
| Company Registration No. | U45203GJ2013PTC075371 |
| PAN | AATGS2287D |
| Experience (Years) | 15 |
| Area Constructed (sqm) | 73000 |
| Projects Completed | 1 |
| Ongoing Projects | 3 |
| Partner 1 | Kunjan Trivedi |
| Address | 111, Earth aalay, nr. ghogha circle, bhavnagar |
| 101 - Start Date | 2016-10-05 |
| 101 - End Date | 2021-03-30 |
| 101 - Progress | 100.0% |
| 101 - Booked Units | 1 |
| 101 - Unbooked Units | 0 |
| 102 - Start Date | 2016-10-05 |
| 102 - End Date | 2021-03-30 |
| 102 - Progress | 100.0% |
| 102 - Booked Units | 1 |
| 102 - Unbooked Units | 0 |
| 103 - Start Date | 2016-10-05 |
| 103 - End Date | 2021-03-30 |
| 103 - Progress | 100.0% |
| 103 - Booked Units | 1 |
| 103 - Unbooked Units | 0 |
| 104 - Start Date | 2016-10-05 |
| 104 - End Date | 2021-03-30 |
| 104 - Progress | 0.0% |
| 104 - Booked Units | 0 |
| 104 - Unbooked Units | 1 |
| 105 - Start Date | 2016-10-05 |
| 105 - End Date | 2021-03-30 |
| 105 - Progress | 0.0% |
| 105 - Booked Units | 0 |
| 105 - Unbooked Units | 1 |
| 201 - Start Date | 2016-10-05 |
| 201 - End Date | 2021-03-30 |
| 201 - Progress | 100.0% |
| 201 - Booked Units | 1 |
| 201 - Unbooked Units | 0 |
| 202 - Start Date | 2016-10-05 |
| 202 - End Date | 2021-03-30 |
| 202 - Progress | 100.0% |
| 202 - Booked Units | 1 |
| 202 - Unbooked Units | 0 |
| 203 - Start Date | 2016-10-05 |
| 203 - End Date | 2021-03-30 |
| 203 - Progress | 0.0% |
| 203 - Booked Units | 0 |
| 203 - Unbooked Units | 1 |
| 204 - Start Date | 2016-10-05 |
| 204 - End Date | 2021-03-30 |
| 204 - Progress | 100.0% |
| 204 - Booked Units | 1 |
| 204 - Unbooked Units | 0 |
| 205 - Start Date | 2016-10-05 |
| 205 - End Date | 2021-03-30 |
| 205 - Progress | 0.0% |
| 205 - Booked Units | 0 |
| 205 - Unbooked Units | 1 |
| 301 - Start Date | 2016-10-05 |
| 301 - End Date | 2021-03-30 |
| 301 - Progress | 100.0% |
| 301 - Booked Units | 1 |
| 301 - Unbooked Units | 0 |
| 302 - Start Date | 2016-10-05 |
| 302 - End Date | 2021-03-30 |
| 302 - Progress | 100.0% |
| 302 - Booked Units | 1 |
| 302 - Unbooked Units | 0 |
| 303 - Start Date | 2016-10-05 |
| 303 - End Date | 2021-03-30 |
| 303 - Progress | 0.0% |
| 303 - Booked Units | 0 |
| 303 - Unbooked Units | 1 |
| 304 - Start Date | 2016-10-05 |
| 304 - End Date | 2021-03-30 |
| 304 - Progress | 100.0% |
| 304 - Booked Units | 1 |
| 304 - Unbooked Units | 0 |
| 305 - Start Date | 2016-10-05 |
| 305 - End Date | 2021-03-30 |
| 305 - Progress | 100.0% |
| 305 - Booked Units | 1 |
| 305 - Unbooked Units | 0 |
| 401 - Start Date | 2016-10-05 |
| 401 - End Date | 2021-03-30 |
| 401 - Progress | 100.0% |
| 401 - Booked Units | 1 |
| 401 - Unbooked Units | 0 |
| 402 - Start Date | 2016-10-05 |
| 402 - End Date | 2021-03-30 |
| 402 - Progress | 0.0% |
| 402 - Booked Units | 0 |
| 402 - Unbooked Units | 1 |
| 403 - Start Date | 2016-10-05 |
| 403 - End Date | 2021-03-30 |
| 403 - Progress | 0.0% |
| 403 - Booked Units | 0 |
| 403 - Unbooked Units | 1 |
| 404 - Start Date | 2016-10-05 |
| 404 - End Date | 2021-03-30 |
| 404 - Progress | 100.0% |
| 404 - Booked Units | 1 |
| 404 - Unbooked Units | 0 |
| 405 - Start Date | 2016-10-05 |
| 405 - End Date | 2021-03-30 |
| 405 - Progress | 100.0% |
| 405 - Booked Units | 1 |
| 405 - Unbooked Units | 0 |
| 501 - Start Date | 2016-10-05 |
| 501 - End Date | 2021-03-30 |
| 501 - Progress | 100.0% |
| 501 - Booked Units | 1 |
| 501 - Unbooked Units | 0 |
| 505 - Start Date | 2016-10-05 |
| 505 - End Date | 2021-03-30 |
| 505 - Progress | 100.0% |
| 505 - Booked Units | 1 |
| 505 - Unbooked Units | 0 |
| 1 - Start Date | 2016-10-05 |
| 1 - End Date | 2021-03-30 |
| 2 - Start Date | 2016-10-05 |
| 2 - End Date | 2021-03-30 |
| 3 - Start Date | 2016-10-05 |
| 3 - End Date | 2021-03-30 |
| 4 - Start Date | 2016-10-05 |
| 4 - End Date | 2021-03-30 |
| 5 - Start Date | 2016-10-05 |
| 5 - End Date | 2021-03-30 |
| 6 - Start Date | 2016-10-05 |
| 6 - End Date | 2021-03-30 |
| 28 - Total Units | 10 |
| 28 - Carpet Area | 731.62 |
| 28 - Exclusive Area | 44.86 |
| 28 - Open Terrace Area | 205.93 |
| April 2019 | 74.97% |
| July 2019 | 99.25% |
| October 2019 | 100.0% |
| January 2020 | 100.0% |
| April 2020 | 100.0% |
| October 2020 | 100.0% |
| January 2021 | 100.0% |
| April 2021 | 100.0% |
| April 2021 | 100.0% |
| Architect | SANKET RATHOD |
| Licence No. | ER 68 |
| Engineer | sanket rathod |
| Licence No. | ER 68 |
| Engineer | SUNIL VASA |
| Licence No. | STR 03 |