HARI AALAYAM
HARI INFRASTRUCTURE
HARI AALAYAM,NEAR SURYA RETREAT BUNGLOW, BESIDE SARTHAK AERA ,SARGASAN, FP-67,TP-9
Approved
29th Sept 2017
Completed
30th Nov 2020
Registration No.
PR/GJ/GANDHINAGAR/GANDHINAGAR/Others/RAA00305/EX1/270120
Acknowledgement No.
PR/GANDHINAGAR/GANDHINAGAR/GANDHINAGAR TPO/170731/000709
Project Type
Residential/Group Housing
Approving Authority
Gandhinagar Urban Development Authority
District
Gandhinagar
Taluka
Gandhinagar
State
Gujarat
Project Details
| Project Name | HARI AALAYAM |
| RERA Number | PR/GJ/GANDHINAGAR/GANDHINAGAR/Others/RAA00305/EX1/270120 |
| Acknowledgement Number | PR/GANDHINAGAR/GANDHINAGAR/GANDHINAGAR TPO/170731/000709 |
| Project Description | 3BHK APPARTMENT |
| Project Type | Residential/Group Housing |
| Project Status | Completed |
| District | Gandhinagar |
| Taluka | Gandhinagar |
| Address | HARI AALAYAM,NEAR SURYA RETREAT BUNGLOW, BESIDE SARTHAK AERA ,SARGASAN, FP-67,TP-9 |
| Pincode | 382422 |
| State | Gujarat |
| Approving Authority | Gandhinagar Urban Development Authority |
| Approved On | 2017-09-29 |
| Start Date | 2017-03-01 |
| End Date | 2020-11-30 |
| Submission Date | 2017-07-31 |
| Months Delayed | 0 |
Area & Cost Details
| Total Land Area | 5985.0 |
| Total Land Area (Registered) | 5985.0 |
| Total Covered Area | 2357.77 |
| Total Open Area | 3627.23 |
| Total Carpet Area | 10327.92 |
| Open Parking Area | 0 |
| Covered Parking Area | 5462.335 |
| Covered Parking Count | 86 |
| Parking for Sale Count | 0 |
| Cost of Land | 62375800 |
| Estimated Project Cost | 178400000 |
| Total Project Cost | 344000000 |
Land Details
| Moje | Uvarsad-Sarghasan-Tarapur |
| TP No. | 9 |
| TP Name | Uvarsad-Sarghasan-Tarapur |
| Sub Plot No. | - |
Promoter Details
| Promoter Name | HARI INFRASTRUCTURE |
| Promoter Type | PARTNERSHIP FIRM |
| har**********@yahoo.com | |
| Mobile | 98******** |
| Company Registration No. | AAJFH6730P |
| PAN | AAJ******* |
| Experience (Years) | 4 |
| Area Constructed (sqm) | 3773 |
| Projects Completed | 0 |
| Ongoing Projects | 0 |
Promoter Partners
| Partner 1 | PATEL NISARG HASMUKHBHAI |
| Address | 689/1,PANCHVATI PARK, SECTOR-23,NEAR IBP PETROL PUMP |
Building Blocks
| Block A - Start Date | 2017-03-01 |
| Block A - End Date | 2020-11-30 |
| Block A - Progress | 100.0% |
| Block A - Booked Units | 14 |
| Block A - Unbooked Units | 0 |
| Block B - Start Date | 2017-03-01 |
| Block B - End Date | 2020-11-30 |
| Block B - Progress | 100.0% |
| Block B - Booked Units | 18 |
| Block B - Unbooked Units | 0 |
| Block C - Start Date | 2017-03-01 |
| Block C - End Date | 2020-11-30 |
| Block C - Progress | 100.0% |
| Block C - Booked Units | 14 |
| Block C - Unbooked Units | 0 |
| Block D - Start Date | 2017-03-01 |
| Block D - End Date | 2020-11-30 |
| Block D - Progress | 100.0% |
| Block D - Booked Units | 20 |
| Block D - Unbooked Units | 0 |
| Block E - Start Date | 2017-03-01 |
| Block E - End Date | 2020-11-30 |
| Block E - Progress | 100.0% |
| Block E - Booked Units | 20 |
| Block E - Unbooked Units | 0 |
Inventory Units
| RESIDENTIAL FLAT - Total Units | 86 |
| RESIDENTIAL FLAT - Carpet Area | 8986.98 |
| RESIDENTIAL FLAT - Exclusive Area | 293.06 |
| RESIDENTIAL FLAT - Open Terrace Area | 337.18 |
Quarterly Progress
| May 2018 | 9.49% |
| August 2018 | 19.24% |
| November 2018 | 40.8% |
| February 2019 | 61.81% |
| May 2019 | 69.06% |
| August 2019 | 74.64% |
| November 2019 | 77.42% |
| August 2020 | 100.0% |
| December 2020 | 100.0% |
Professionals
| Architect | P.S.SUTHAR |
| Licence No. | CA/89/1285 |
| Engineer | AMEE ASSOCIATES |
| Licence No. | SD-1/063/05/2008(GRADE-1) |
| Contractor | RAJESH THAKARSINH PRAJAPATI |
The information provided on this page is collated from publicly available resources. PropTech Pulse does not guarantee the accuracy, completeness, or authority of this data and shall not be held liable for any discrepancies. For queries or further assistance, please contact us at pulse@aurumproptech.in