Shraddha Infrastructure
Near Ganesh Citadel, Raysan, PDPU Road
Approved
11th Mar 2020
Pending
30th Jun 2026
Registration No.
PR/GJ/GANDHINAGAR/GANDHINAGAR/Others/RAA06874/A1R/060323
Acknowledgement No.
PR/GANDHINAGAR/GANDHINAGAR/GANDHINAGAR TPO/200204/008789
Project Type
Residential/Group Housing
Approving Authority
Others
District
Gandhinagar
Taluka
Gandhinagar
State
Gujarat
| Project Name | Madhav Crest Villa |
| RERA Number | PR/GJ/GANDHINAGAR/GANDHINAGAR/Others/RAA06874/A1R/060323 |
| Acknowledgement Number | PR/GANDHINAGAR/GANDHINAGAR/GANDHINAGAR TPO/200204/008789 |
| Project Description | 'HOME' built not just with bricks and mortar, but with love, affection and care. Enjoy being part of bigger family where you will be cared for. |
| Project Type | Residential/Group Housing |
| Project Status | APPROVED |
| District | Gandhinagar |
| Taluka | Gandhinagar |
| Address | Near Ganesh Citadel, Raysan, PDPU Road |
| State | Gujarat |
| Approving Authority | Others |
| Approved On | 2020-03-11 |
| Start Date | 2019-12-13 |
| End Date | 2026-06-30 |
| Submission Date | 2020-01-23 |
| Months Delayed | 0 |
| Total Land Area | 9799.0 |
| Total Land Area (Registered) | 9799.0 |
| Total Covered Area | 3938.61 |
| Total Open Area | 5860.39 |
| Total Carpet Area | 8096.94 |
| Open Parking Area | 0 |
| Covered Parking Area | 1058.4 |
| Covered Parking Count | 36 |
| Parking for Sale Count | 0 |
| Cost of Land | 441000000 |
| Estimated Project Cost | 200000000 |
| Total Project Cost | 244100000 |
| Promoter Name | Shraddha Infrastructure |
| Promoter Type | PARTNERSHIP FIRM |
| shraddha.infra.rera99@gmail.com | |
| Mobile | 9099928772 |
| Company Registration No. | GUJGND01113 |
| PAN | ADXFS6311G |
| Date of Incorporation | 2019-04-26 |
| Experience (Years) | 1 |
| Area Constructed (sqm) | 9881 |
| Projects Completed | 0 |
| Ongoing Projects | 1 |
| Partner 1 | MUKESHKUMAR MADHABHAI PATEL |
| PAN | ACKPP7502N |
| Address | 311/2 Mangalmurtipark Society,, Sector: 8 |
| Partner 2 | RENUKABEN MUKESHKUMAR PATEL |
| PAN | AUZPP7465P |
| Address | 311/2 Mangalmurtipark Society,, Sector: 8 |
| Partner 3 | RAMILABEN RAJENDRAKUMAR PATEL |
| PAN | APIPP4877R |
| Address | Patel Vas,, Raysan |
| Partner 4 | VIRAJ RAJENDRAKUMAR PATEL |
| PAN | DCIPP6266A |
| Address | 201 Suramya Appt Panchvati 2nd Line, Gulbaitekra Road Ahmedabad City, |
| Partner 5 | DHARMIK MUKESHKUMAR PATEL |
| PAN | CDMPP1841D |
| Address | 311/2 Mangalmurtipark Society, Sector: 8 |
| 1 - Start Date | 2019-12-13 |
| 1 - End Date | 2026-06-30 |
| 1 - Progress | 0.0% |
| 1 - Booked Units | 0 |
| 1 - Unbooked Units | 1 |
| 2 - Start Date | 2019-12-13 |
| 2 - End Date | 2026-06-30 |
| 2 - Progress | 0.0% |
| 2 - Booked Units | 0 |
| 2 - Unbooked Units | 1 |
| 3 - Start Date | 2019-12-13 |
| 3 - End Date | 2026-06-30 |
| 3 - Progress | 100.0% |
| 3 - Booked Units | 1 |
| 3 - Unbooked Units | 0 |
| 4 - Start Date | 2019-12-13 |
| 4 - End Date | 2026-06-30 |
| 4 - Progress | 100.0% |
| 4 - Booked Units | 1 |
| 4 - Unbooked Units | 0 |
| 5 - Start Date | 2019-12-13 |
| 5 - End Date | 2026-06-30 |
| 5 - Progress | 100.0% |
| 5 - Booked Units | 1 |
| 5 - Unbooked Units | 0 |
| 6 - Start Date | 2019-12-13 |
| 6 - End Date | 2026-06-30 |
| 6 - Progress | 100.0% |
| 6 - Booked Units | 1 |
| 6 - Unbooked Units | 0 |
| 7 - Start Date | 2019-12-13 |
| 7 - End Date | 2026-06-30 |
| 7 - Progress | 0.0% |
| 7 - Booked Units | 0 |
| 7 - Unbooked Units | 1 |
| 8 - Start Date | 2019-12-13 |
| 8 - End Date | 2026-06-30 |
| 8 - Progress | 100.0% |
| 8 - Booked Units | 1 |
| 8 - Unbooked Units | 0 |
| 9 - Start Date | 2019-12-13 |
| 9 - End Date | 2026-06-30 |
| 9 - Progress | 0.0% |
| 9 - Booked Units | 0 |
| 9 - Unbooked Units | 1 |
| 10 - Start Date | 2019-12-13 |
| 10 - End Date | 2026-06-30 |
| 10 - Progress | 100.0% |
| 10 - Booked Units | 1 |
| 10 - Unbooked Units | 0 |
| 11 - Start Date | 2019-12-13 |
| 11 - End Date | 2026-06-30 |
| 11 - Progress | 100.0% |
| 11 - Booked Units | 1 |
| 11 - Unbooked Units | 0 |
| 12 - Start Date | 2019-12-13 |
| 12 - End Date | 2026-06-30 |
| 12 - Progress | 100.0% |
| 12 - Booked Units | 1 |
| 12 - Unbooked Units | 0 |
| 12/A - Start Date | 2019-12-13 |
| 12/A - End Date | 2026-06-30 |
| 12/A - Progress | 0.0% |
| 12/A - Booked Units | 0 |
| 12/A - Unbooked Units | 1 |
| 14 - Start Date | 2019-12-13 |
| 14 - End Date | 2026-06-30 |
| 14 - Progress | 0.0% |
| 14 - Booked Units | 0 |
| 14 - Unbooked Units | 1 |
| 15 - Start Date | 2019-12-13 |
| 15 - End Date | 2026-06-30 |
| 15 - Progress | 100.0% |
| 15 - Booked Units | 1 |
| 15 - Unbooked Units | 0 |
| 16 - Start Date | 2019-12-13 |
| 16 - End Date | 2026-06-30 |
| 16 - Progress | 100.0% |
| 16 - Booked Units | 1 |
| 16 - Unbooked Units | 0 |
| 17 - Start Date | 2019-12-13 |
| 17 - End Date | 2026-06-30 |
| 17 - Progress | 100.0% |
| 17 - Booked Units | 1 |
| 17 - Unbooked Units | 0 |
| 18 - Start Date | 2019-12-13 |
| 18 - End Date | 2026-06-30 |
| 18 - Progress | 0.0% |
| 18 - Booked Units | 0 |
| 18 - Unbooked Units | 1 |
| 19 - Start Date | 2019-12-13 |
| 19 - End Date | 2026-06-30 |
| 19 - Progress | 100.0% |
| 19 - Booked Units | 1 |
| 19 - Unbooked Units | 0 |
| 20 - Start Date | 2019-12-13 |
| 20 - End Date | 2026-06-30 |
| 20 - Progress | 100.0% |
| 20 - Booked Units | 1 |
| 20 - Unbooked Units | 0 |
| 21 - Start Date | 2019-12-13 |
| 21 - End Date | 2026-06-30 |
| 21 - Progress | 100.0% |
| 21 - Booked Units | 1 |
| 21 - Unbooked Units | 0 |
| 22 - Start Date | 2019-12-13 |
| 22 - End Date | 2026-06-30 |
| 22 - Progress | 0.0% |
| 22 - Booked Units | 0 |
| 22 - Unbooked Units | 1 |
| 23 - Start Date | 2019-12-13 |
| 23 - End Date | 2026-06-30 |
| 23 - Progress | 100.0% |
| 23 - Booked Units | 1 |
| 23 - Unbooked Units | 0 |
| 24 - Start Date | 2019-12-13 |
| 24 - End Date | 2026-06-30 |
| 24 - Progress | 100.0% |
| 24 - Booked Units | 1 |
| 24 - Unbooked Units | 0 |
| 25 - Start Date | 2019-12-13 |
| 25 - End Date | 2026-06-30 |
| 25 - Progress | 0.0% |
| 25 - Booked Units | 0 |
| 25 - Unbooked Units | 1 |
| 26 - Start Date | 2019-12-13 |
| 26 - End Date | 2026-06-30 |
| 26 - Progress | 0.0% |
| 26 - Booked Units | 0 |
| 26 - Unbooked Units | 1 |
| 27 - Start Date | 2019-12-13 |
| 27 - End Date | 2026-06-30 |
| 27 - Progress | 100.0% |
| 27 - Booked Units | 1 |
| 27 - Unbooked Units | 0 |
| 28 - Start Date | 2019-12-13 |
| 28 - End Date | 2026-06-30 |
| 28 - Progress | 0.0% |
| 28 - Booked Units | 0 |
| 28 - Unbooked Units | 1 |
| 29 - Start Date | 2019-12-13 |
| 29 - End Date | 2026-06-30 |
| 29 - Progress | 100.0% |
| 29 - Booked Units | 1 |
| 29 - Unbooked Units | 0 |
| 30 - Start Date | 2019-12-13 |
| 30 - End Date | 2026-06-30 |
| 30 - Progress | 100.0% |
| 30 - Booked Units | 1 |
| 30 - Unbooked Units | 0 |
| 31 - Start Date | 2019-12-13 |
| 31 - End Date | 2026-06-30 |
| 31 - Progress | 0.0% |
| 31 - Booked Units | 0 |
| 31 - Unbooked Units | 1 |
| 32 - Start Date | 2019-12-13 |
| 32 - End Date | 2026-06-30 |
| 32 - Progress | 100.0% |
| 32 - Booked Units | 1 |
| 32 - Unbooked Units | 0 |
| 33 - Start Date | 2019-12-13 |
| 33 - End Date | 2026-06-30 |
| 33 - Progress | 100.0% |
| 33 - Booked Units | 1 |
| 33 - Unbooked Units | 0 |
| 34 - Start Date | 2019-12-13 |
| 34 - End Date | 2026-06-30 |
| 34 - Progress | 100.0% |
| 34 - Booked Units | 1 |
| 34 - Unbooked Units | 0 |
| 35 - Start Date | 2019-12-13 |
| 35 - End Date | 2026-06-30 |
| 35 - Progress | 100.0% |
| 35 - Booked Units | 1 |
| 35 - Unbooked Units | 0 |
| 36 - Start Date | 2019-12-13 |
| 36 - End Date | 2026-06-30 |
| 36 - Progress | 0.0% |
| 36 - Booked Units | 0 |
| 36 - Unbooked Units | 1 |
| Residential - Total Units | 36 |
| Residential - Completed Units | 0 |
| Residential - Booked Units | 9 |
| Residential - Carpet Area | 8113.96 |
| Residential - Exclusive Area | 680.87 |
| Residential - Open Terrace Area | 0.0 |
| August 2020 | 5.46% |
| November 2020 | 5.46% |
| February 2021 | 10.42% |
| May 2021 | 14.41% |
| August 2021 | 21.4% |
| November 2021 | 27.42% |
| February 2022 | 29.44% |
| May 2022 | 32.9% |
| August 2022 | 34.35% |
| November 2022 | 37.28% |
| February 2023 | 40.81% |
| May 2023 | 49.94% |
| August 2023 | 52.75% |
| November 2023 | 52.96% |
| January 2024 | 42.6% |
| April 2024 | 68.15% |
| July 2024 | 84.06% |
| July 2026 | 84.06% |
| Architect | Ar. Jharna Nagori |
| Licence No. | CA/2007/39853 |
| Engineer | Mr. Pritesh R Mishra |
| Licence No. | GUD/SDI/111/02/2016 |