MADHUVAN BY SHREENILAY
SHREE NILAY BUILDCON
MANSA BALIYADEV MANDIR ROAD, AT - MANSA, TA - MANSA
Approved
25th Feb 2022
Completed
31st Dec 2025
Registration No.
PR/GJ/GANDHINAGAR/MANSA/Others/RAA09854/250222
Acknowledgement No.
PR/GANDHINAGAR/MANSA/GUJRERA/220201/012321
Project Type
Residential/Group Housing
Approving Authority
Others
District
Gandhinagar
Taluka
Mansa
State
Gujarat
Project Details
| Project Name | MADHUVAN BY SHREENILAY |
| RERA Number | PR/GJ/GANDHINAGAR/MANSA/Others/RAA09854/250222 |
| Acknowledgement Number | PR/GANDHINAGAR/MANSA/GUJRERA/220201/012321 |
| Project Description | RESIDENTIAL BUNGLOWS |
| Project Type | Residential/Group Housing |
| Project Status | Completed |
| District | Gandhinagar |
| Taluka | Mansa |
| Address | MANSA BALIYADEV MANDIR ROAD, AT - MANSA, TA - MANSA |
| State | Gujarat |
| Approving Authority | Others |
| Approved On | 2022-02-25 |
| Start Date | 2021-12-13 |
| End Date | 2025-12-31 |
| Submission Date | 2022-01-26 |
| Months Delayed | 0 |
Area & Cost Details
| Total Land Area | 4756.0 |
| Total Land Area (Registered) | 4756.0 |
| Total Covered Area | 1627.85 |
| Total Open Area | 3128.15 |
| Total Carpet Area | 2445.85 |
| Open Parking Area | 13.75 |
| Covered Parking Area | 0.0 |
| Covered Parking Count | 0 |
| Parking for Sale Count | 1 |
| Cost of Land | 14608140 |
| Estimated Project Cost | 39700000 |
| Total Project Cost | 54308140 |
Promoter Details
| Promoter Name | SHREE NILAY BUILDCON |
| Promoter Type | PARTNERSHIP FIRM |
| shr***************@gmail.com | |
| Mobile | 88******** |
| Company Registration No. | GUJGND01431 |
| PAN | AEI******* |
| Date of Incorporation | 2020-12-13 |
| Experience (Years) | 3 |
| Area Constructed (sqm) | 1650 |
| Projects Completed | 0 |
| Ongoing Projects | 1 |
Promoter Partners
| Partner 1 | SANIKUMAR MANUBHAI PATEL |
| PAN | EAO******* |
| Address | GOKULNAGAR, AT - ITADARA, TA - MANSA |
| Partner 2 | JAYESHKUMAR HASMUKHBHAI PATEL |
| PAN | ATH******* |
| Address | B 46, HIRAVADI SOCIETY, MANSA GANDHINAGAR ROAD, AT - MANSA, TA - MANSA |
| Partner 3 | DINESHBHAI GOBARBHAI PATEL |
| PAN | AKF******* |
| Address | 205, NILKANTH RESIDENCY, BEHIND JAN SEVA KENDRA, NEW NARODA |
| Partner 4 | VIRENDRABHAI VARVABHAI PATEL |
| PAN | AIZ******* |
| Address | 6 BANSARI BUNGLOWS, PETHAPUR |
| Partner 5 | MINISHKUMAR PATEL |
| PAN | ANR******* |
| Address | M 504 SHUKAN RIVER VIEW, NR DARSHAN FLATS, HANSOL, SARDARNAGAR |
| Partner 6 | JIGNESHKUMAR SENDHABHAI PATEL |
| PAN | ATB******* |
| Address | OUTSIDE VAV DARWAJA, CHAMPAPURI VAS, AT - MASNA, TA - MANSA |
| Partner 7 | DAHYABHAI SOMABHAI PATEL |
| PAN | ACI******* |
| Address | 8/B, SURYANARAYAN SOCIETY,, NR SAURABH SCHOOL, NAVA VADAJ |
| Partner 8 | SENDHABHAI GOBARDAS PATEL |
| PAN | ALV******* |
| Address | OUTSIDE VAV DARWAJA, CHAMPAPURI VAS, AT - MANSA, TA - MASNA |
Building Blocks
| A - Start Date | 2021-12-13 |
| A - End Date | 2025-12-31 |
| A - Progress | 100.0% |
| A - Booked Units | 1 |
| A - Unbooked Units | 0 |
| B - Start Date | 2021-12-13 |
| B - End Date | 2025-12-31 |
| B - Progress | 100.0% |
| B - Booked Units | 9 |
| B - Unbooked Units | 0 |
| C - Start Date | 2021-12-13 |
| C - End Date | 2025-12-31 |
| C - Progress | 100.0% |
| C - Booked Units | 9 |
| C - Unbooked Units | 0 |
| D - Start Date | 2021-12-13 |
| D - End Date | 2025-12-31 |
| D - Progress | 100.0% |
| D - Booked Units | 2 |
| D - Unbooked Units | 0 |
| E - Start Date | 2021-12-13 |
| E - End Date | 2025-12-31 |
| E - Progress | 100.0% |
| E - Booked Units | 2 |
| E - Unbooked Units | 0 |
| F - Start Date | 2021-12-13 |
| F - End Date | 2025-12-31 |
| F - Progress | 100.0% |
| F - Booked Units | 1 |
| F - Unbooked Units | 0 |
| G - Start Date | 2021-12-13 |
| G - End Date | 2025-12-31 |
| G - Progress | 100.0% |
| G - Booked Units | 1 |
| G - Unbooked Units | 0 |
Inventory Units
| RESIDENTIAL BUNGLOWS - Total Units | 25 |
| RESIDENTIAL BUNGLOWS - Carpet Area | 2445.85 |
| RESIDENTIAL BUNGLOWS - Exclusive Area | 74.64 |
| RESIDENTIAL BUNGLOWS - Open Terrace Area | 0.0 |
Quarterly Progress
| July 2022 | 21.25% |
| October 2023 | 48.07% |
| January 2024 | 49.34% |
| April 2024 | 60.16% |
| July 2024 | 69.33% |
| October 2024 | 72.06% |
| January 2026 | 100.0% |
Professionals
| Architect | MAULIK CHAVDA |
| Licence No. | CA201359853 |
| Engineer | AMRUTBHAI H PATEL |
| Licence No. | AUDAENGG113 |
| Contractor | VIJAYBHAI KALIDAS PATEL |
The information provided on this page is collated from publicly available resources. PropTech Pulse does not guarantee the accuracy, completeness, or authority of this data and shall not be held liable for any discrepancies. For queries or further assistance, please contact us at pulse@aurumproptech.in