MAHALAXMI CORPORATION
VILLAGE: KUDASAN, DIST. GANADHINAGAR
Approved
18th Dec 2018
Completed
30th May 2023
Registration No.
PR/GJ/GANDHINAGAR/GANDHINAGAR/Others/RAA04400/181218
Acknowledgement No.
PR/GANDHINAGAR/GANDHINAGAR/GANDHINAGAR TPO/181128/006428
Project Type
Residential/Group Housing
Approving Authority
Gandhinagar Urban Development Authority
District
Gandhinagar
Taluka
Gandhinagar
State
Gujarat
| Project Name | SATVAM GREENS |
| RERA Number | PR/GJ/GANDHINAGAR/GANDHINAGAR/Others/RAA04400/181218 |
| Acknowledgement Number | PR/GANDHINAGAR/GANDHINAGAR/GANDHINAGAR TPO/181128/006428 |
| Project Description | 3 BHK APPARTMENTS |
| Project Type | Residential/Group Housing |
| Project Status | APPROVED |
| District | Gandhinagar |
| Taluka | Gandhinagar |
| Address | VILLAGE: KUDASAN, DIST. GANADHINAGAR |
| Pincode | 382421 |
| State | Gujarat |
| Approving Authority | Gandhinagar Urban Development Authority |
| Approved On | 2018-12-18 |
| Start Date | 2018-11-03 |
| End Date | 2023-05-30 |
| Submission Date | 2018-11-28 |
| Months Delayed | 0 |
| Total Land Area | 4094.0 |
| Total Covered Area | 2782.0 |
| Total Open Area | 1312.0 |
| Open Parking Area | 0 |
| Covered Parking Area | 4181.63 |
| Covered Parking Count | 72 |
| Parking for Sale Count | 0 |
| Cost of Land | 62500000 |
| Estimated Project Cost | 180000000 |
| Total Project Cost | 182500000 |
| Moje | Kudasan |
| TP No. | 6 |
| TP Name | Kudasan-Sargasan-Dholakuva |
| Promoter Name | MAHALAXMI CORPORATION |
| Promoter Type | PARTNERSHIP FIRM |
| rameshspatel31272@gmail.com | |
| Mobile | 9429734854 |
| Company Registration No. | NA |
| PAN | ABIFM4067E |
| Experience (Years) | 8 |
| Area Constructed (sqm) | 4094 |
| Projects Completed | 1 |
| Ongoing Projects | 1 |
| Partner 1 | RAMESHKUMAR PATEL |
| Address | A-128, PRAMUKH ARCADE-2, RELIANCE CHOKDI, KUDASAN, GANDHINAGAR-382421 |
| A - Start Date | 2018-11-03 |
| A - End Date | 2023-05-30 |
| A - Progress | 100.0% |
| A - Booked Units | 24 |
| A - Unbooked Units | 0 |
| B - Start Date | 2018-11-03 |
| B - End Date | 2023-05-30 |
| B - Progress | 100.0% |
| B - Booked Units | 24 |
| B - Unbooked Units | 0 |
| C - Start Date | 2018-11-03 |
| C - End Date | 2023-05-30 |
| C - Progress | 100.0% |
| C - Booked Units | 24 |
| C - Unbooked Units | 0 |
| RESIDENTIAL - Total Units | 72 |
| RESIDENTIAL - Carpet Area | 8187.84 |
| RESIDENTIAL - Exclusive Area | 648.0 |
| RESIDENTIAL - Open Terrace Area | 0.0 |
| May 2019 | 32.56% |
| August 2019 | 43.9% |
| November 2019 | 48.29% |
| February 2020 | 55.92% |
| May 2020 | 64.05% |
| August 2020 | 67.89% |
| November 2020 | 74.55% |
| February 2021 | 88.51% |
| May 2021 | 95.14% |
| August 2021 | 98.3% |
| November 2021 | 100.0% |
| June 2023 | 100.0% |