Sankalp Residency
Shree Laxminarayan Buildcon
Sankalp Residency, Next to Subh Residency,, Piplag Chokdi, N H No. 8,
Approved
28th Aug 2020
Completed
31st Mar 2024
Registration No.
PR/GJ/KHEDA/NADIAD/Others/RAA07394/280820
Acknowledgement No.
PR/KHEDA/NADIAD/NADIAD TPO/200728/009386
Project Type
Residential/Group Housing
Approving Authority
Nadiad Municipality
District
Kheda
Taluka
Nadiad
State
Gujarat
Project Details
| Project Name | Sankalp Residency |
| RERA Number | PR/GJ/KHEDA/NADIAD/Others/RAA07394/280820 |
| Acknowledgement Number | PR/KHEDA/NADIAD/NADIAD TPO/200728/009386 |
| Project Description | 3 BHK Luxurious Living |
| Project Type | Residential/Group Housing |
| Project Status | Completed |
| District | Kheda |
| Taluka | Nadiad |
| Address | Sankalp Residency, Next to Subh Residency,, Piplag Chokdi, N H No. 8, |
| State | Gujarat |
| Approving Authority | Nadiad Municipality |
| Approved On | 2020-08-28 |
| Start Date | 2020-06-09 |
| End Date | 2024-03-31 |
| Submission Date | 2020-07-22 |
| Months Delayed | 0 |
Area & Cost Details
| Total Land Area | 13456.0 |
| Total Land Area (Registered) | 13456.0 |
| Total Covered Area | 5488.84 |
| Total Open Area | 7967.16 |
| Total Carpet Area | 7189.09 |
| Open Parking Area | 0 |
| Covered Parking Area | 0.0 |
| Covered Parking Count | 0 |
| Parking for Sale Count | 0 |
| Cost of Land | 40053655 |
| Estimated Project Cost | 137625000 |
| Total Project Cost | 177678655 |
Land Details
| Moje | Nadiad |
| Sub Plot No. | - |
Promoter Details
| Promoter Name | Shree Laxminarayan Buildcon |
| Promoter Type | PARTNERSHIP FIRM |
| shr**********************@gmail.com | |
| Mobile | 98******** |
| Company Registration No. | NA |
| PAN | ADY******* |
| Experience (Years) | 5 |
| Area Constructed (sqm) | 8721 |
| Projects Completed | 0 |
| Ongoing Projects | 1 |
Promoter Partners
| Partner 1 | Rajesh Kantilal Patel |
| Address | Sutariya Pole,, Kanthariya Chakla, Nadiad |
| Partner 2 | Apurva P Patel |
| Address | B/11, Shaktidhara Society,, India Colony Road, Bapunagar |
| Partner 3 | Bhupendrabhai Vastabhai Prajapati |
| Address | 7, Nilkanth Society, Juna Dumral Road,, Patel Society Area, Nadiad |
| Partner 4 | Ishaan Rajemdrakumar Patel |
| Address | 5, Karmvir Villa Society,, Santram Dairy Road, Nadiad |
| Partner 5 | Purshotam Hansraj Shakhala |
| Address | 3, Karmveer Vila, Dairy Road,, Nadiad |
| Partner 6 | Jayendrabhai G Turakheya |
| Address | Lakhsdip Society,, Near Shardamandir School, Nadiad |
| Partner 7 | Bharatbhai Laljibhai Prajapati |
| Address | 8, Nilkanth Society, Juna Damral Road,, Vaishali Road, Nadiad |
| Partner 8 | Girishkumar N Prajapati |
| Address | 4 Suryanagar Society,, Behind Vaishali Cinema, Nadiad |
Building Blocks
| A - Start Date | 2020-06-09 |
| A - End Date | 2024-03-31 |
| A - Progress | 100.0% |
| A - Booked Units | 16 |
| A - Unbooked Units | 0 |
| B - Start Date | 2020-06-09 |
| B - End Date | 2024-03-31 |
| B - Progress | 100.0% |
| B - Booked Units | 4 |
| B - Unbooked Units | 0 |
| C - Start Date | 2020-06-09 |
| C - End Date | 2024-03-31 |
| C - Progress | 100.0% |
| C - Booked Units | 17 |
| C - Unbooked Units | 0 |
| D - Start Date | 2020-06-09 |
| D - End Date | 2024-03-31 |
| D - Progress | 100.0% |
| D - Booked Units | 33 |
| D - Unbooked Units | 0 |
| E - Start Date | 2020-06-09 |
| E - End Date | 2024-03-31 |
| E - Progress | 100.0% |
| E - Booked Units | 6 |
| E - Unbooked Units | 0 |
| F - Start Date | 2020-06-09 |
| F - End Date | 2024-03-31 |
| F - Progress | 100.0% |
| F - Booked Units | 5 |
| F - Unbooked Units | 0 |
| G - Start Date | 2020-06-09 |
| G - End Date | 2024-03-31 |
| G - Progress | 100.0% |
| G - Booked Units | 1 |
| G - Unbooked Units | 0 |
| H - Start Date | 2020-06-09 |
| H - End Date | 2024-03-31 |
| H - Progress | 100.0% |
| H - Booked Units | 1 |
| H - Unbooked Units | 0 |
| I - Start Date | 2020-06-09 |
| I - End Date | 2024-03-31 |
| I - Progress | 100.0% |
| I - Booked Units | 1 |
| I - Unbooked Units | 0 |
| J - Start Date | 2020-06-09 |
| J - End Date | 2024-03-31 |
| J - Progress | 100.0% |
| J - Booked Units | 4 |
| J - Unbooked Units | 0 |
| K - Start Date | 2020-06-09 |
| K - End Date | 2024-03-31 |
| K - Progress | 100.0% |
| K - Booked Units | 3 |
| K - Unbooked Units | 0 |
| L - Start Date | 2020-06-09 |
| L - End Date | 2024-03-31 |
| L - Progress | 50.0% |
| L - Booked Units | 1 |
| L - Unbooked Units | 1 |
| M - Start Date | 2020-06-09 |
| M - End Date | 2024-03-31 |
| M - Progress | 100.0% |
| M - Booked Units | 2 |
| M - Unbooked Units | 0 |
Inventory Units
| 3 BHK BUNGLOWS - Total Units | 95 |
| 3 BHK BUNGLOWS - Carpet Area | 7189.09 |
| 3 BHK BUNGLOWS - Exclusive Area | 325.18 |
| 3 BHK BUNGLOWS - Open Terrace Area | 0.0 |
Quarterly Progress
| January 2021 | 19.41% |
| April 2021 | 34.93% |
| July 2021 | 58.83% |
| October 2021 | 70.48% |
| January 2022 | 73.04% |
| April 2022 | 92.64% |
| July 2022 | 93.05% |
| October 2022 | 100.0% |
| April 2024 | 100.0% |
Professionals
| Architect | Savan Panchal |
| Licence No. | CA/2018/100507 |
| Engineer | Brijesh Gandhi |
| Licence No. | LIC NO 234 |
The information provided on this page is collated from publicly available resources. PropTech Pulse does not guarantee the accuracy, completeness, or authority of this data and shall not be held liable for any discrepancies. For queries or further assistance, please contact us at pulse@aurumproptech.in