Aditya Villa

NATWARLAL SHETH

Anjar saher R.s.no. 5/3, vidi road, Anjar, Anjar (kutch) 370110

Approved

12th Dec 2018

Completed

31st Mar 2019

Registration No.

PR/GJ/KUTCH/ANJAR/Others/PAA04337/121218

Acknowledgement No.

PR/KUTCH/ANJAR/BHUJ TPO/181008/006060

Project Type

Plotted Development

Approving Authority

Anjar Area Development Authority

District

Kutch

Taluka

Anjar

State

Gujarat

Project Details

Project NameAditya Villa
RERA NumberPR/GJ/KUTCH/ANJAR/Others/PAA04337/121218
Acknowledgement NumberPR/KUTCH/ANJAR/BHUJ TPO/181008/006060
Project DescriptionProjected plotted development
Project TypePlotted Development
Project StatusAPPROVED
DistrictKutch
TalukaAnjar
AddressAnjar saher R.s.no. 5/3, vidi road, Anjar, Anjar (kutch) 370110
Pincode370110
StateGujarat
Approving AuthorityAnjar Area Development Authority
Approved On2018-12-12
Start Date2017-04-19
End Date2019-03-31
Submission Date2018-10-08
Months Delayed0

Area & Cost Details

Total Land Area12139.8
Total Covered Area8930.5
Total Open Area3209.3
Open Parking Area219.1
Covered Parking Area0.0
Covered Parking Count0
Parking for Sale Count2
Cost of Land24953
Estimated Project Cost3200000
Total Project Cost4024953

Land Details

MojeAnjar
City Survey No.3522/B-3
Plot No.Anjar
Sub Plot No.-

Promoter Details

Promoter NameNATWARLAL SHETH
Promoter TypeIndividual/Propritorship
Emailgasheth@gmail.com
Mobile9265535489
PANAMRPS9474M
Experience (Years)0
Area Constructed (sqm)0
Projects Completed0
Ongoing Projects1

Building Blocks

R1 - Start Date2017-04-19
R1 - End Date2019-03-31
R1 - FSI0.0
R1 - Built-up Area0.0
R1 - Progress0.0%
R1 - Booked Units0
R1 - Unbooked Units1
R2 - Start Date2017-04-19
R2 - End Date2019-03-31
R2 - FSI0.0
R2 - Built-up Area0.0
R2 - Progress0.0%
R2 - Booked Units0
R2 - Unbooked Units1
R3 - Start Date2017-04-19
R3 - End Date2019-03-31
R3 - FSI0.0
R3 - Built-up Area0.0
R3 - Progress0.0%
R3 - Booked Units0
R3 - Unbooked Units1
R4 - Start Date2017-04-19
R4 - End Date2019-03-31
R4 - FSI0.0
R4 - Built-up Area0.0
R4 - Progress0.0%
R4 - Booked Units0
R4 - Unbooked Units1
R5 - Start Date2017-04-19
R5 - End Date2019-03-31
R5 - FSI0.0
R5 - Built-up Area0.0
R5 - Progress0.0%
R5 - Booked Units0
R5 - Unbooked Units1
R6 - Start Date2017-04-19
R6 - End Date2019-03-31
R6 - FSI0.0
R6 - Built-up Area0.0
R6 - Progress0.0%
R6 - Booked Units0
R6 - Unbooked Units1
R7 - Start Date2017-04-19
R7 - End Date2019-03-31
R7 - FSI0.0
R7 - Built-up Area0.0
R7 - Progress0.0%
R7 - Booked Units0
R7 - Unbooked Units1
R8 - Start Date2017-04-19
R8 - End Date2019-03-31
R8 - FSI0.0
R8 - Built-up Area0.0
R8 - Progress0.0%
R8 - Booked Units0
R8 - Unbooked Units1
R9 - Start Date2017-04-19
R9 - End Date2019-03-31
R9 - FSI0.0
R9 - Built-up Area0.0
R9 - Progress0.0%
R9 - Booked Units0
R9 - Unbooked Units1
R10 - Start Date2017-04-19
R10 - End Date2019-03-31
R10 - FSI0.0
R10 - Built-up Area0.0
R10 - Progress0.0%
R10 - Booked Units0
R10 - Unbooked Units1
R11 - Start Date2017-04-19
R11 - End Date2019-03-31
R11 - FSI0.0
R11 - Built-up Area0.0
R11 - Progress0.0%
R11 - Booked Units0
R11 - Unbooked Units1
R12 - Start Date2017-04-19
R12 - End Date2019-03-31
R12 - FSI0.0
R12 - Built-up Area0.0
R12 - Progress0.0%
R12 - Booked Units0
R12 - Unbooked Units1
R13 - Start Date2017-04-19
R13 - End Date2019-03-31
R13 - FSI0.0
R13 - Built-up Area0.0
R13 - Progress0.0%
R13 - Booked Units0
R13 - Unbooked Units1
R14 - Start Date2017-04-19
R14 - End Date2019-03-31
R14 - FSI0.0
R14 - Built-up Area0.0
R14 - Progress0.0%
R14 - Booked Units0
R14 - Unbooked Units1
R15 - Start Date2017-04-19
R15 - End Date2019-03-31
R15 - FSI0.0
R15 - Built-up Area0.0
R15 - Progress0.0%
R15 - Booked Units0
R15 - Unbooked Units1
R16 - Start Date2017-04-19
R16 - End Date2019-03-31
R16 - FSI0.0
R16 - Built-up Area0.0
R16 - Progress0.0%
R16 - Booked Units0
R16 - Unbooked Units1
R17 - Start Date2017-04-19
R17 - End Date2019-03-31
R17 - FSI0.0
R17 - Built-up Area0.0
R17 - Progress0.0%
R17 - Booked Units0
R17 - Unbooked Units1
R18 - Start Date2017-04-19
R18 - End Date2019-03-31
R18 - FSI0.0
R18 - Built-up Area0.0
R18 - Progress0.0%
R18 - Booked Units0
R18 - Unbooked Units1
R19 - Start Date2017-04-19
R19 - End Date2019-03-31
R19 - FSI0.0
R19 - Built-up Area0.0
R19 - Progress0.0%
R19 - Booked Units0
R19 - Unbooked Units1
R20 - Start Date2017-04-19
R20 - End Date2019-03-31
R20 - FSI0.0
R20 - Built-up Area0.0
R20 - Progress0.0%
R20 - Booked Units0
R20 - Unbooked Units1
R21 - Start Date2017-04-19
R21 - End Date2019-03-31
R21 - FSI0.0
R21 - Built-up Area0.0
R21 - Progress0.0%
R21 - Booked Units0
R21 - Unbooked Units1
R22 - Start Date2017-04-19
R22 - End Date2019-03-31
R22 - FSI0.0
R22 - Built-up Area0.0
R22 - Progress0.0%
R22 - Booked Units0
R22 - Unbooked Units1
R23 - Start Date2017-04-19
R23 - End Date2019-03-31
R23 - FSI0.0
R23 - Built-up Area0.0
R23 - Progress0.0%
R23 - Booked Units0
R23 - Unbooked Units1
R24 - Start Date2017-04-19
R24 - End Date2019-03-31
R24 - FSI0.0
R24 - Built-up Area0.0
R24 - Progress0.0%
R24 - Booked Units0
R24 - Unbooked Units1
R25 - Start Date2017-04-19
R25 - End Date2019-03-31
R25 - FSI0.0
R25 - Built-up Area0.0
R25 - Progress0.0%
R25 - Booked Units0
R25 - Unbooked Units1
R26 - Start Date2017-04-19
R26 - End Date2019-03-31
R26 - FSI0.0
R26 - Built-up Area0.0
R26 - Progress0.0%
R26 - Booked Units0
R26 - Unbooked Units1
R27 - Start Date2017-04-19
R27 - End Date2019-03-31
R27 - FSI0.0
R27 - Built-up Area0.0
R27 - Progress0.0%
R27 - Booked Units0
R27 - Unbooked Units1
R28 - Start Date2017-04-19
R28 - End Date2019-03-31
R28 - FSI0.0
R28 - Built-up Area0.0
R28 - Progress0.0%
R28 - Booked Units0
R28 - Unbooked Units1
R29 - Start Date2017-04-19
R29 - End Date2019-03-31
R29 - FSI0.0
R29 - Built-up Area0.0
R29 - Progress0.0%
R29 - Booked Units0
R29 - Unbooked Units1
R30 - Start Date2017-04-19
R30 - End Date2019-03-31
R30 - FSI0.0
R30 - Built-up Area0.0
R30 - Progress0.0%
R30 - Booked Units0
R30 - Unbooked Units1
R31 - Start Date2017-04-19
R31 - End Date2019-03-31
R31 - FSI0.0
R31 - Built-up Area0.0
R31 - Progress0.0%
R31 - Booked Units0
R31 - Unbooked Units1
R32 - Start Date2017-04-19
R32 - End Date2019-03-31
R32 - FSI0.0
R32 - Built-up Area0.0
R32 - Progress0.0%
R32 - Booked Units0
R32 - Unbooked Units1
R33 - Start Date2017-04-19
R33 - End Date2019-03-31
R33 - FSI0.0
R33 - Built-up Area0.0
R33 - Progress0.0%
R33 - Booked Units0
R33 - Unbooked Units1
R34 - Start Date2017-04-19
R34 - End Date2019-03-31
R34 - FSI0.0
R34 - Built-up Area0.0
R34 - Progress0.0%
R34 - Booked Units0
R34 - Unbooked Units1
R35 - Start Date2017-04-19
R35 - End Date2019-03-31
R35 - FSI0.0
R35 - Built-up Area0.0
R35 - Progress0.0%
R35 - Booked Units0
R35 - Unbooked Units1
R36 - Start Date2017-04-19
R36 - End Date2019-03-31
R36 - FSI0.0
R36 - Built-up Area0.0
R36 - Progress0.0%
R36 - Booked Units0
R36 - Unbooked Units1
R37 - Start Date2017-04-19
R37 - End Date2019-03-31
R37 - FSI0.0
R37 - Built-up Area0.0
R37 - Progress0.0%
R37 - Booked Units0
R37 - Unbooked Units1
R38 - Start Date2017-04-19
R38 - End Date2019-03-31
R38 - FSI0.0
R38 - Built-up Area0.0
R38 - Progress0.0%
R38 - Booked Units0
R38 - Unbooked Units1
R39 - Start Date2017-04-19
R39 - End Date2019-03-31
R39 - FSI0.0
R39 - Built-up Area0.0
R39 - Progress0.0%
R39 - Booked Units0
R39 - Unbooked Units1
R40 - Start Date2017-04-19
R40 - End Date2019-03-31
R40 - FSI0.0
R40 - Built-up Area0.0
R40 - Progress0.0%
R40 - Booked Units0
R40 - Unbooked Units1
R41 - Start Date2017-04-19
R41 - End Date2019-03-31
R41 - FSI0.0
R41 - Built-up Area0.0
R41 - Progress0.0%
R41 - Booked Units0
R41 - Unbooked Units1
R42 - Start Date2017-04-19
R42 - End Date2019-03-31
R42 - FSI0.0
R42 - Built-up Area0.0
R42 - Progress0.0%
R42 - Booked Units0
R42 - Unbooked Units1
R43 - Start Date2017-04-19
R43 - End Date2019-03-31
R43 - FSI0.0
R43 - Built-up Area0.0
R43 - Progress0.0%
R43 - Booked Units0
R43 - Unbooked Units1
R44 - Start Date2017-04-19
R44 - End Date2019-03-31
R44 - FSI0.0
R44 - Built-up Area0.0
R44 - Progress0.0%
R44 - Booked Units0
R44 - Unbooked Units1
R45 - Start Date2017-04-19
R45 - End Date2019-03-31
R45 - FSI0.0
R45 - Built-up Area0.0
R45 - Progress0.0%
R45 - Booked Units0
R45 - Unbooked Units1
R46 - Start Date2017-04-19
R46 - End Date2019-03-31
R46 - FSI0.0
R46 - Built-up Area0.0
R46 - Progress0.0%
R46 - Booked Units0
R46 - Unbooked Units1
R47 - Start Date2017-04-19
R47 - End Date2019-03-31
R47 - FSI0.0
R47 - Built-up Area0.0
R47 - Progress0.0%
R47 - Booked Units0
R47 - Unbooked Units1
R48 - Start Date2017-04-19
R48 - End Date2019-03-31
R48 - FSI0.0
R48 - Built-up Area0.0
R48 - Progress0.0%
R48 - Booked Units0
R48 - Unbooked Units1
R49 - Start Date2017-04-19
R49 - End Date2019-03-31
R49 - FSI0.0
R49 - Built-up Area0.0
R49 - Progress0.0%
R49 - Booked Units0
R49 - Unbooked Units1
R50 - Start Date2017-04-19
R50 - End Date2019-03-31
R50 - FSI0.0
R50 - Built-up Area0.0
R50 - Progress0.0%
R50 - Booked Units0
R50 - Unbooked Units1
R51 - Start Date2017-04-19
R51 - End Date2019-03-31
R51 - FSI0.0
R51 - Built-up Area0.0
R51 - Progress0.0%
R51 - Booked Units0
R51 - Unbooked Units1
R52 - Start Date2017-04-19
R52 - End Date2019-03-31
R52 - FSI0.0
R52 - Built-up Area0.0
R52 - Progress0.0%
R52 - Booked Units0
R52 - Unbooked Units1
R53 - Start Date2017-04-19
R53 - End Date2019-03-31
R53 - FSI0.0
R53 - Built-up Area0.0
R53 - Progress0.0%
R53 - Booked Units0
R53 - Unbooked Units1
R54 - Start Date2017-04-19
R54 - End Date2019-03-31
R54 - FSI0.0
R54 - Built-up Area0.0
R54 - Progress0.0%
R54 - Booked Units0
R54 - Unbooked Units1
R55 - Start Date2017-04-19
R55 - End Date2019-03-31
R55 - FSI0.0
R55 - Built-up Area0.0
R55 - Progress0.0%
R55 - Booked Units0
R55 - Unbooked Units1
R56 - Start Date2017-04-19
R56 - End Date2019-03-31
R56 - FSI0.0
R56 - Built-up Area0.0
R56 - Progress0.0%
R56 - Booked Units0
R56 - Unbooked Units1
R57 - Start Date2017-04-19
R57 - End Date2019-03-31
R57 - FSI0.0
R57 - Built-up Area0.0
R57 - Progress0.0%
R57 - Booked Units0
R57 - Unbooked Units1
R58 - Start Date2017-04-19
R58 - End Date2019-03-31
R58 - FSI0.0
R58 - Built-up Area0.0
R58 - Progress0.0%
R58 - Booked Units0
R58 - Unbooked Units1
R59 - Start Date2017-04-19
R59 - End Date2019-03-31
R59 - FSI0.0
R59 - Built-up Area0.0
R59 - Progress0.0%
R59 - Booked Units0
R59 - Unbooked Units1
R60 - Start Date2017-04-19
R60 - End Date2019-03-31
R60 - FSI0.0
R60 - Built-up Area0.0
R60 - Progress0.0%
R60 - Booked Units0
R60 - Unbooked Units1
R61 - Start Date2017-04-19
R61 - End Date2019-03-31
R61 - FSI0.0
R61 - Built-up Area0.0
R61 - Progress0.0%
R61 - Booked Units0
R61 - Unbooked Units1
R62 - Start Date2017-04-19
R62 - End Date2019-03-31
R62 - FSI0.0
R62 - Built-up Area0.0
R62 - Progress0.0%
R62 - Booked Units0
R62 - Unbooked Units1
R63 - Start Date2017-04-19
R63 - End Date2019-03-31
R63 - FSI0.0
R63 - Built-up Area0.0
R63 - Progress0.0%
R63 - Booked Units0
R63 - Unbooked Units1
R64 - Start Date2017-04-19
R64 - End Date2019-03-31
R64 - FSI0.0
R64 - Built-up Area0.0
R64 - Progress0.0%
R64 - Booked Units0
R64 - Unbooked Units1
R65 - Start Date2017-04-19
R65 - End Date2019-03-31
R65 - FSI0.0
R65 - Built-up Area0.0
R65 - Progress0.0%
R65 - Booked Units0
R65 - Unbooked Units1
R66 - Start Date2017-04-19
R66 - End Date2019-03-31
R66 - FSI0.0
R66 - Built-up Area0.0
R66 - Progress0.0%
R66 - Booked Units0
R66 - Unbooked Units1
R67 - Start Date2017-04-19
R67 - End Date2019-03-31
R67 - FSI0.0
R67 - Built-up Area0.0
R67 - Progress0.0%
R67 - Booked Units0
R67 - Unbooked Units1
R68 - Start Date2017-04-19
R68 - End Date2019-03-31
R68 - FSI0.0
R68 - Built-up Area0.0
R68 - Progress0.0%
R68 - Booked Units0
R68 - Unbooked Units1
R69 - Start Date2017-04-19
R69 - End Date2019-03-31
R69 - FSI0.0
R69 - Built-up Area0.0
R69 - Progress0.0%
R69 - Booked Units0
R69 - Unbooked Units1
R70 - Start Date2017-04-19
R70 - End Date2019-03-31
R70 - FSI0.0
R70 - Built-up Area0.0
R70 - Progress0.0%
R70 - Booked Units0
R70 - Unbooked Units1
C1 - Start Date2017-04-19
C1 - End Date2019-03-31
C1 - FSI0.0
C1 - Built-up Area0.0
C1 - Progress0.0%
C1 - Booked Units0
C1 - Unbooked Units1
C2 - Start Date2017-04-19
C2 - End Date2019-03-31
C2 - FSI0.0
C2 - Built-up Area0.0
C2 - Progress0.0%
C2 - Booked Units0
C2 - Unbooked Units1
C3 - Start Date2017-04-19
C3 - End Date2019-03-31
C3 - FSI0.0
C3 - Built-up Area0.0
C3 - Progress0.0%
C3 - Booked Units0
C3 - Unbooked Units1
C4 - Start Date2017-04-19
C4 - End Date2019-03-31
C4 - FSI0.0
C4 - Built-up Area0.0
C4 - Progress0.0%
C4 - Booked Units0
C4 - Unbooked Units1
C5 - Start Date2017-04-19
C5 - End Date2019-03-31
C5 - FSI0.0
C5 - Built-up Area0.0
C5 - Progress0.0%
C5 - Booked Units0
C5 - Unbooked Units1
C6 - Start Date2017-04-19
C6 - End Date2019-03-31
C6 - FSI0.0
C6 - Built-up Area0.0
C6 - Progress0.0%
C6 - Booked Units0
C6 - Unbooked Units1
C7 - Start Date2017-04-19
C7 - End Date2019-03-31
C7 - FSI0.0
C7 - Built-up Area0.0
C7 - Progress0.0%
C7 - Booked Units0
C7 - Unbooked Units1
C8 - Start Date2017-04-19
C8 - End Date2019-03-31
C8 - FSI0.0
C8 - Built-up Area0.0
C8 - Progress0.0%
C8 - Booked Units0
C8 - Unbooked Units1

Inventory Units

Residential - Total Units78
Residential - Completed Units0
Residential - Booked Units0
Residential - Carpet Area7565.71
Residential - Exclusive Area0.0
Residential - Open Terrace Area0.0

Quarterly Progress

April 20197.27%

Professionals

ArchitectSamved Chaudhary
Licence No.CA/0094/16849
EngineerMaulik M Kotak
Licence No.AADA Lic. No. ER/0073/050416

Top Properties in Surat

Pexo Icon

Ask Pulse Ai anything about real estate

Unlock the Latest in Real Estate

News, Infographics, Blogs & More! Delivered to your inbox.

Proptech Pulse Logo

Data that drives action.
Insight that inspires action.
Technology that empowers action.“

Made with Love

Statue

© PropTech Pulse 2026, All rights reserved.

Terms of Use and Privacy Policy