RAJVI PARK
RAJVI ESTATE LLP
SURVEY NO. 33, KIDANA
Approved
25th Apr 2018
Completed
30th Jun 2024
Registration No.
PR/GJ/KUTCH/GANDHIDHAM/Others/RAA02493/250418
Acknowledgement No.
PR/KUTCH/GANDHIDHAM/BHUJ TPO/180216/004656
Project Type
Residential/Group Housing
Approving Authority
Gandhidham Development Authority
District
Kutch
Taluka
Gandhidham
State
Gujarat
Project Details
| Project Name | RAJVI PARK |
| RERA Number | PR/GJ/KUTCH/GANDHIDHAM/Others/RAA02493/250418 |
| Acknowledgement Number | PR/KUTCH/GANDHIDHAM/BHUJ TPO/180216/004656 |
| Project Description | AFFORDABLE HOUSING SCHEME |
| Project Type | Residential/Group Housing |
| Project Status | Completed |
| District | Kutch |
| Taluka | Gandhidham |
| Address | SURVEY NO. 33, KIDANA |
| Pincode | 370230 |
| State | Gujarat |
| Approving Authority | Gandhidham Development Authority |
| Approved On | 2018-04-25 |
| Start Date | 2017-09-07 |
| End Date | 2024-06-30 |
| Submission Date | 2018-02-16 |
| Months Delayed | 0 |
Area & Cost Details
| Total Land Area | 10063.15 |
| Total Covered Area | 10063.15 |
| Total Open Area | 0.0 |
| Open Parking Area | 0 |
| Covered Parking Area | 0.0 |
| Covered Parking Count | 0 |
| Parking for Sale Count | 0 |
| Cost of Land | 5000000 |
| Estimated Project Cost | 126200000 |
| Total Project Cost | 131200000 |
Land Details
| Moje | Kidana |
| Sub Plot No. | 158 to 177 , 180 to 201 , 249 to 282 , 331 to 358 |
Promoter Details
| Promoter Name | RAJVI ESTATE LLP |
| Promoter Type | LIMITED LIABILITY PARTNERSHIP FIRM |
| raj****************@gmail.com | |
| Mobile | 98******** |
| Company Registration No. | AAD3492 |
| PAN | AAS******* |
| Date of Incorporation | 2015-02-12 |
| Experience (Years) | 8 |
| Area Constructed (sqm) | 13469 |
| Projects Completed | 0 |
| Ongoing Projects | 1 |
Promoter Partners
| Partner 1 | DHAVAL BHAVESHBHAI ACHARYA |
| PAN | ABI******* |
| Address | Plot no.267, Bhaipratap Chowk, Ward No.12/B, Gandhidham |
| Partner 2 | BHAVESH FULCHAND ACHARYA |
| PAN | ABI******* |
| Address | Plot No. 172 & 173, Sector -4, Gandhidham |
Building Blocks
| 5 to 10 - Start Date | 2017-09-07 |
| 5 to 10 - End Date | 2024-06-30 |
| 5 to 10 - Progress | 100.0% |
| 5 to 10 - Booked Units | 6 |
| 5 to 10 - Unbooked Units | 0 |
| 44 to 54 - Start Date | 2017-09-07 |
| 44 to 54 - End Date | 2024-06-30 |
| 44 to 54 - Progress | 27.27% |
| 44 to 54 - Booked Units | 3 |
| 44 to 54 - Unbooked Units | 8 |
| 55 to 65 - Start Date | 2017-09-07 |
| 55 to 65 - End Date | 2024-06-30 |
| 55 to 65 - Progress | 90.91% |
| 55 to 65 - Booked Units | 10 |
| 55 to 65 - Unbooked Units | 1 |
| 101 to 110 - Start Date | 2017-09-07 |
| 101 to 110 - End Date | 2024-06-30 |
| 101 to 110 - Progress | 100.0% |
| 101 to 110 - Booked Units | 10 |
| 101 to 110 - Unbooked Units | 0 |
| 111 to 117 - Start Date | 2017-09-07 |
| 111 to 117 - End Date | 2024-06-30 |
| 111 to 117 - Progress | 100.0% |
| 111 to 117 - Booked Units | 7 |
| 111 to 117 - Unbooked Units | 0 |
| 170 to 179 - Start Date | 2017-09-07 |
| 170 to 179 - End Date | 2024-06-30 |
| 170 to 179 - Progress | 100.0% |
| 170 to 179 - Booked Units | 10 |
| 170 to 179 - Unbooked Units | 0 |
| 180 to 189 - Start Date | 2017-09-07 |
| 180 to 189 - End Date | 2024-06-30 |
| 180 to 189 - Progress | 80.0% |
| 180 to 189 - Booked Units | 8 |
| 180 to 189 - Unbooked Units | 2 |
| 261 to 267 - Start Date | 2017-09-07 |
| 261 to 267 - End Date | 2024-06-30 |
| 261 to 267 - Progress | 57.14% |
| 261 to 267 - Booked Units | 4 |
| 261 to 267 - Unbooked Units | 3 |
| 268 to 270 - Start Date | 2017-09-07 |
| 268 to 270 - End Date | 2024-06-30 |
| 268 to 270 - Progress | 0.0% |
| 268 to 270 - Booked Units | 0 |
| 268 to 270 - Unbooked Units | 3 |
| 158 to 169 - Start Date | 2017-09-07 |
| 158 to 169 - End Date | 2024-06-30 |
| 158 to 169 - Progress | 100.0% |
| 158 to 169 - Booked Units | 12 |
| 158 to 169 - Unbooked Units | 0 |
| 190 to 201 - Start Date | 2017-09-07 |
| 190 to 201 - End Date | 2024-06-30 |
| 190 to 201 - Progress | 83.33% |
| 190 to 201 - Booked Units | 10 |
| 190 to 201 - Unbooked Units | 2 |
| 249 to 260 - Start Date | 2017-09-07 |
| 249 to 260 - End Date | 2024-06-30 |
| 249 to 260 - Progress | 8.33% |
| 249 to 260 - Booked Units | 1 |
| 249 to 260 - Unbooked Units | 11 |
| 271 to 282 - Start Date | 2017-09-07 |
| 271 to 282 - End Date | 2024-06-30 |
| 271 to 282 - Progress | 0.0% |
| 271 to 282 - Booked Units | 0 |
| 271 to 282 - Unbooked Units | 12 |
| 343 to 346 - Start Date | 2017-09-07 |
| 343 to 346 - End Date | 2024-06-30 |
| 343 to 346 - Progress | 0.0% |
| 343 to 346 - Booked Units | 0 |
| 343 to 346 - Unbooked Units | 4 |
| 331 to 342 - Start Date | 2017-09-07 |
| 331 to 342 - End Date | 2024-06-30 |
| 331 to 342 - Progress | 0.0% |
| 331 to 342 - Booked Units | 0 |
| 331 to 342 - Unbooked Units | 12 |
| 347 to 358 - Start Date | 2017-09-07 |
| 347 to 358 - End Date | 2024-06-30 |
| 347 to 358 - Progress | 0.0% |
| 347 to 358 - Booked Units | 0 |
| 347 to 358 - Unbooked Units | 12 |
| 407 to 413 - Start Date | 2017-09-07 |
| 407 to 413 - End Date | 2024-06-30 |
| 407 to 413 - Progress | 0.0% |
| 407 to 413 - Booked Units | 0 |
| 407 to 413 - Unbooked Units | 7 |
Inventory Units
| ROW HOUSES - Total Units | 158 |
| ROW HOUSES - Carpet Area | 5660.43 |
| ROW HOUSES - Exclusive Area | 345.19 |
| ROW HOUSES - Open Terrace Area | 6299.9 |
| ROW HOUSES - Total Units | 158 |
| ROW HOUSES - Completed Units | 0 |
| ROW HOUSES - Booked Units | 0 |
| ROW HOUSES - Carpet Area | 5660.43 |
| ROW HOUSES - Exclusive Area | 345.19 |
| ROW HOUSES - Open Terrace Area | 6299.9 |
Quarterly Progress
| September 2018 | 6.05% |
| December 2018 | 14.58% |
| March 2019 | 25.01% |
| June 2019 | 36.55% |
| September 2019 | 44.49% |
| December 2019 | 51.46% |
| March 2020 | 63.42% |
| June 2020 | 68.14% |
| September 2020 | 69.72% |
| December 2020 | 69.8% |
| March 2021 | 70.0% |
| June 2021 | 70.0% |
| September 2021 | 70.0% |
| December 2021 | 70.0% |
| March 2022 | 77.36% |
| June 2022 | 75.97% |
| September 2022 | 76.4% |
| December 2022 | 83.97% |
| March 2023 | 86.09% |
| June 2023 | 90.17% |
| September 2023 | 93.81% |
| December 2023 | 100.0% |
| July 2024 | 87.25% |
Professionals
| Architect | DIVYESH DESAI & ASSOCIATES |
| Licence No. | CA/92/15014 |
| Engineer | KALPEN D SOMPURA |
| Licence No. | 343 |
| Contractor | SHIV KRUPA ASSOCIATES |
| Contractor | UMIYA CONSTRUCTION |
The information provided on this page is collated from publicly available resources. PropTech Pulse does not guarantee the accuracy, completeness, or authority of this data and shall not be held liable for any discrepancies. For queries or further assistance, please contact us at pulse@aurumproptech.in