HERITAGE TOWNSHIP
VEDIKA DEVELOPERS
HERITAGE TOWNSHIP, KADA CROSS ROAD
Approved
24th Jul 2018
Completed
31st Mar 2020
Registration No.
PR/GJ/MEHSANA/VISNAGAR/Others/RAA03234/240718
Acknowledgement No.
PR/MEHSANA/VISNAGAR/MEHSANA TPO/180505/005300
Project Type
Residential/Group Housing
Approving Authority
Visnagar Municipality
District
Mehsana
Taluka
Visnagar
State
Gujarat
Project Details
| Project Name | HERITAGE TOWNSHIP |
| RERA Number | PR/GJ/MEHSANA/VISNAGAR/Others/RAA03234/240718 |
| Acknowledgement Number | PR/MEHSANA/VISNAGAR/MEHSANA TPO/180505/005300 |
| Project Description | RESIDENTIAL AND PLOT |
| Project Type | Residential/Group Housing |
| Project Status | Completed |
| District | Mehsana |
| Taluka | Visnagar |
| Address | HERITAGE TOWNSHIP, KADA CROSS ROAD |
| Pincode | 384315 |
| State | Gujarat |
| Approving Authority | Visnagar Municipality |
| Approved On | 2018-07-24 |
| Start Date | 2018-03-01 |
| End Date | 2020-03-31 |
| Submission Date | 2018-05-05 |
| Months Delayed | 0 |
Area & Cost Details
| Total Land Area | 11790.0 |
| Total Covered Area | 3992.0 |
| Total Open Area | 7798.0 |
| Open Parking Area | 0 |
| Covered Parking Area | 0.0 |
| Covered Parking Count | 0 |
| Parking for Sale Count | 0 |
| Cost of Land | 3131731 |
| Estimated Project Cost | 78250000 |
| Total Project Cost | 88931731 |
Land Details
| Moje | Visnagar |
| Sub Plot No. | - |
Promoter Details
| Promoter Name | VEDIKA DEVELOPERS |
| Promoter Type | PARTNERSHIP FIRM |
| har***********@gmail.com | |
| Mobile | 98******** |
| Company Registration No. | NOT APPLICABLE |
| PAN | AAP******* |
| Experience (Years) | 2 |
| Area Constructed (sqm) | 3018 |
| Projects Completed | 0 |
| Ongoing Projects | 1 |
Promoter Partners
| Partner 1 | JAIMIN RAJESHBHAI PATEL |
| Address | 5, RAJHANS SOCIETY,, DHAROI COLONY ROAD, VISNAGAR |
Building Blocks
| 1to4 - Start Date | 2018-03-01 |
| 1to4 - End Date | 2020-03-31 |
| 1to4 - Progress | 0.0% |
| 1to4 - Booked Units | 0 |
| 1to4 - Unbooked Units | 4 |
| 5to13 - Start Date | 2018-03-01 |
| 5to13 - End Date | 2020-03-31 |
| 5to13 - Progress | 0.0% |
| 5to13 - Booked Units | 0 |
| 5to13 - Unbooked Units | 9 |
| 14to21 - Start Date | 2018-03-01 |
| 14to21 - End Date | 2020-03-31 |
| 14to21 - Progress | 0.0% |
| 14to21 - Booked Units | 0 |
| 14to21 - Unbooked Units | 8 |
| 22to25 - Start Date | 2018-03-01 |
| 22to25 - End Date | 2020-03-31 |
| 22to25 - Progress | 0.0% |
| 22to25 - Booked Units | 0 |
| 22to25 - Unbooked Units | 4 |
| V1to6 - Start Date | 2018-03-01 |
| V1to6 - End Date | 2020-03-31 |
| V1to6 - Progress | 0.0% |
| V1to6 - Booked Units | 0 |
| V1to6 - Unbooked Units | 6 |
| V7to22 - Start Date | 2018-03-01 |
| V7to22 - End Date | 2020-03-31 |
| V7to22 - Progress | 75.0% |
| V7to22 - Booked Units | 12 |
| V7to22 - Unbooked Units | 4 |
| V23to30 - Start Date | 2018-03-01 |
| V23to30 - End Date | 2020-03-31 |
| V23to30 - Progress | 75.0% |
| V23to30 - Booked Units | 6 |
| V23to30 - Unbooked Units | 2 |
| V31to38 - Start Date | 2018-03-01 |
| V31to38 - End Date | 2020-03-31 |
| V31to38 - Progress | 100.0% |
| V31to38 - Booked Units | 8 |
| V31to38 - Unbooked Units | 0 |
| V39to54 - Start Date | 2018-03-01 |
| V39to54 - End Date | 2020-03-31 |
| V39to54 - Progress | 100.0% |
| V39to54 - Booked Units | 16 |
| V39to54 - Unbooked Units | 0 |
| V55+56+65+66 - Start Date | 2018-03-01 |
| V55+56+65+66 - End Date | 2020-03-31 |
| V55+56+65+66 - Progress | 100.0% |
| V55+56+65+66 - Booked Units | 4 |
| V55+56+65+66 - Unbooked Units | 0 |
| V57to64 - Start Date | 2018-03-01 |
| V57to64 - End Date | 2020-03-31 |
| V57to64 - Progress | 75.0% |
| V57to64 - Booked Units | 6 |
| V57to64 - Unbooked Units | 2 |
| V67to70 - Start Date | 2018-03-01 |
| V67to70 - End Date | 2020-03-31 |
| V67to70 - Progress | 100.0% |
| V67to70 - Booked Units | 4 |
| V67to70 - Unbooked Units | 0 |
| V71to72 - Start Date | 2018-03-01 |
| V71to72 - End Date | 2020-03-31 |
| V71to72 - Progress | 0.0% |
| V71to72 - Booked Units | 0 |
| V71to72 - Unbooked Units | 2 |
| V73to76 - Start Date | 2018-03-01 |
| V73to76 - End Date | 2020-03-31 |
| V73to76 - Progress | 75.0% |
| V73to76 - Booked Units | 3 |
| V73to76 - Unbooked Units | 1 |
Inventory Units
| PLOT - Total Units | 12 |
| PLOT - Carpet Area | 729.49 |
| PLOT - Exclusive Area | 0.0 |
| PLOT - Open Terrace Area | 0.0 |
| RESIDENTIAL - Total Units | 64 |
| RESIDENTIAL - Carpet Area | 3018.15 |
| RESIDENTIAL - Exclusive Area | 244.48 |
| RESIDENTIAL - Open Terrace Area | 0.0 |
Quarterly Progress
| December 2018 | 15.22% |
| March 2019 | 18.74% |
| June 2019 | 26.06% |
| September 2019 | 36.33% |
| December 2019 | 47.63% |
| April 2020 | 63.57% |
Professionals
| Architect | KAPIL R MODI |
| Licence No. | CA/2015/67171 |
| Engineer | MUKESH PATEL |
| Licence No. | 04 |
The information provided on this page is collated from publicly available resources. PropTech Pulse does not guarantee the accuracy, completeness, or authority of this data and shall not be held liable for any discrepancies. For queries or further assistance, please contact us at pulse@aurumproptech.in
Top Properties in Ahmedabad