TANISHQ-21
OM INFRASTRUCTURE
TANISHQ-21 OPP PANJARA POL, KADI CHHATRAL ROAD
Approved
6th Sept 2019
Completed
30th Jun 2024
Registration No.
PR/GJ/MEHSANA/KADI/Others/MAA06005/060919
Acknowledgement No.
PR/MEHSANA/KADI/MEHSANA TPO/190717/007782
Project Type
Mixed Development
Approving Authority
Kadi Municipality
District
Mehsana
Taluka
Kadi
State
Gujarat
Project Details
| Project Name | TANISHQ-21 |
| RERA Number | PR/GJ/MEHSANA/KADI/Others/MAA06005/060919 |
| Acknowledgement Number | PR/MEHSANA/KADI/MEHSANA TPO/190717/007782 |
| Project Description | RESIDENTIAL AND COMMERCIAL UNIT PROJECT |
| Project Type | Mixed Development |
| Project Status | Completed |
| District | Mehsana |
| Taluka | Kadi |
| Address | TANISHQ-21 OPP PANJARA POL, KADI CHHATRAL ROAD |
| Pincode | 382715 |
| State | Gujarat |
| Approving Authority | Kadi Municipality |
| Approved On | 2019-09-06 |
| Start Date | 2019-05-15 |
| End Date | 2024-06-30 |
| Submission Date | 2019-07-09 |
| Months Delayed | 0 |
Area & Cost Details
| Total Land Area | 12140.0 |
| Total Covered Area | 7072.0 |
| Total Open Area | 5068.0 |
| Open Parking Area | 4722 |
| Covered Parking Area | 0.0 |
| Covered Parking Count | 0 |
| Parking for Sale Count | 140 |
| Cost of Land | 4742889 |
| Estimated Project Cost | 125700000 |
| Total Project Cost | 130442889 |
Land Details
| Moje | Kadi |
Promoter Details
| Promoter Name | OM INFRASTRUCTURE |
| Promoter Type | PARTNERSHIP FIRM |
| tan************@gmail.com | |
| Mobile | 98******** |
| Company Registration No. | GUJAMS38886 |
| PAN | AAC******* |
| Experience (Years) | 8 |
| Area Constructed (sqm) | 7913 |
| Projects Completed | 1 |
| Ongoing Projects | 1 |
Promoter Partners
| Partner 1 | VINODBHAI ISHWARBHAI PATEL |
| Address | 15, B R PARK SCIENCE CITY ROAD,, SOLA, AHMEDABAD |
| Partner 2 | ISHWARBHAI MAGANDAS PATEL |
| Address | 16, ANKUR SOCIETY, THOL ROAD, KADI |
| Partner 3 | VIJAY AMRUTLAL PATEL |
| Address | G-302, SHREERATNA APPARTMENT,, SURDHARA CIRCLE, THALTEJ |
| Partner 4 | AMRUTLAL MAGANDAS PATEL |
| Address | 14, ANKUR SOCIETY,, THOL ROAD, KADI |
| Partner 5 | PANKAJBHAI CHANDULAL PATEL |
| Address | B-12, SWAPNIL APPARTMENT,, OPP BHAVSAR SOCIETY, NAVA VADAJ |
| Partner 6 | MEHULKUMAR CHANDULAL PATEL |
| Address | 6, GAJANAN BUNGLOWS,, GIDC NEW COLONY, ANKLESHWAR |
| Partner 7 | BHARATBHAI BABALDAS PANCHAL |
| Address | BLOCK I-403, SHREE RATNA APPARMENT,, NEAR AVISHKAR TENAMENT, SURDHARA CIRCLE, THALTEJ |
| Partner 8 | MUKESHBHAI FULCHANDBHAI SUTHAR |
| Address | 7, SNEHDEEP SOCIETY, OPP VIVEK ANAND PARTY PLOT,, NEAR VEJALPUR POLICE CHOWKY, |
| Partner 9 | PATEL DEEP VINODKUMAR |
| Address | 15, B R PARK SOCIETY, SCIENCE CITY ROAD,, SOLA |
Building Blocks
| M - Start Date | 2019-05-15 |
| M - End Date | 2024-06-30 |
| M - Progress | 61.9% |
| M - Booked Units | 13 |
| M - Unbooked Units | 8 |
| N - Start Date | 2019-05-15 |
| N - End Date | 2024-06-30 |
| N - Progress | 92.86% |
| N - Booked Units | 52 |
| N - Unbooked Units | 4 |
| O - Start Date | 2019-05-15 |
| O - End Date | 2024-06-30 |
| O - Progress | 88.24% |
| O - Booked Units | 30 |
| O - Unbooked Units | 4 |
| A - Start Date | 2019-05-15 |
| A - End Date | 2024-06-30 |
| A - Progress | 100.0% |
| A - Booked Units | 1 |
| A - Unbooked Units | 0 |
| B - Start Date | 2019-05-15 |
| B - End Date | 2024-06-30 |
| B - Progress | 100.0% |
| B - Booked Units | 2 |
| B - Unbooked Units | 0 |
| C - Start Date | 2019-05-15 |
| C - End Date | 2024-06-30 |
| C - Progress | 100.0% |
| C - Booked Units | 5 |
| C - Unbooked Units | 0 |
| D - Start Date | 2019-05-15 |
| D - End Date | 2024-06-30 |
| D - Progress | 100.0% |
| D - Booked Units | 8 |
| D - Unbooked Units | 0 |
| E - Start Date | 2019-05-15 |
| E - End Date | 2024-06-30 |
| E - Progress | 100.0% |
| E - Booked Units | 7 |
| E - Unbooked Units | 0 |
Inventory Units
| 134 - Total Units | 134 |
| 134 - Carpet Area | 8134.0 |
| 134 - Exclusive Area | 517.0 |
| 134 - Open Terrace Area | 0.0 |
Quarterly Progress
| February 2020 | 61.19% |
| August 2020 | 65.46% |
| November 2020 | 72.74% |
| February 2021 | 75.7% |
| May 2021 | 78.61% |
| August 2021 | 80.37% |
| November 2021 | 88.88% |
| February 2022 | 98.01% |
| May 2022 | 98.01% |
| August 2022 | 98.01% |
| November 2022 | 98.01% |
| July 2024 | 98.01% |
Professionals
| Architect | BRIJESH CONSTRUCTION |
| Licence No. | CA/99/24588 |
| Engineer | AMI ASSOCIATES |
| Licence No. | AUDA SD-1/287 |
| Contractor | SREE OM ASSOCIATES |
The information provided on this page is collated from publicly available resources. PropTech Pulse does not guarantee the accuracy, completeness, or authority of this data and shall not be held liable for any discrepancies. For queries or further assistance, please contact us at pulse@aurumproptech.in