AADARSH GREEN CITY DEVELOPERS
NEAR AADARSH CITY,80FIT ROAD,PUNIT NAGAR CIRCUL,, 150FIT RING ROAD,MAVDI,RAJKOT.
Approved
7th May 2018
Completed
31st Mar 2019
Registration No.
PR/GJ/RAJKOT/RAJKOT/Others/RAA02568/070518
Acknowledgement No.
PR/RAJKOT/RAJKOT/RAJKOT TPO/180209/004622
Project Type
Residential/Group Housing
Approving Authority
Rajkot Municipal Corporation
District
Rajkot
Taluka
Rajkot
State
Gujarat
| Project Name | AADARSH GREEN CITY |
| RERA Number | PR/GJ/RAJKOT/RAJKOT/Others/RAA02568/070518 |
| Acknowledgement Number | PR/RAJKOT/RAJKOT/RAJKOT TPO/180209/004622 |
| Project Description | BANGLOW & FLAT |
| Project Type | Residential/Group Housing |
| Project Status | APPROVED |
| District | Rajkot |
| Taluka | Rajkot |
| Address | NEAR AADARSH CITY,80FIT ROAD,PUNIT NAGAR CIRCUL,, 150FIT RING ROAD,MAVDI,RAJKOT. |
| Pincode | 360004 |
| State | Gujarat |
| Approving Authority | Rajkot Municipal Corporation |
| Approved On | 2018-05-07 |
| Start Date | 2017-10-13 |
| End Date | 2019-03-31 |
| Submission Date | 2018-02-09 |
| Months Delayed | 0 |
| Total Land Area | 11196.0 |
| Total Covered Area | 4675.0 |
| Total Open Area | 6237.0 |
| Open Parking Area | 0 |
| Covered Parking Area | 3001.0 |
| Covered Parking Count | 76 |
| Parking for Sale Count | 0 |
| Cost of Land | 115200000 |
| Estimated Project Cost | 175200000 |
| Total Project Cost | 290400000 |
| Moje | Mavdi |
| Sub Plot No. | 1 To 11/1 , 1 To 11/2 , 11 To 11/3, 12 To 17/1 , 12 To 17 /2 , 18 To 74 , 77 To 89 |
| Promoter Name | AADARSH GREEN CITY DEVELOPERS |
| Promoter Type | PARTNERSHIP FIRM |
| aadarshgreencity@gmail.com | |
| Mobile | 9825215472 |
| Company Registration No. | 103070 |
| PAN | ABJFA6728R |
| Experience (Years) | 10 |
| Area Constructed (sqm) | 18659 |
| Projects Completed | 4 |
| Ongoing Projects | 2 |
| Partner 1 | BHAVESH DHANJIBHAI CHOVATIYA |
| Address | "OM' ARJUNPARK, NEAR ASTRON SOCIETY,, AMIN MARG, RAJKOT |
| Wing A - Start Date | 2017-10-13 |
| Wing A - End Date | 2019-03-31 |
| Wing A - Progress | 0.0% |
| Wing A - Booked Units | 0 |
| Wing A - Unbooked Units | 10 |
| Wing B - Start Date | 2017-10-13 |
| Wing B - End Date | 2019-03-31 |
| Wing B - Progress | 0.0% |
| Wing B - Booked Units | 0 |
| Wing B - Unbooked Units | 10 |
| Wing C - Start Date | 2017-10-13 |
| Wing C - End Date | 2019-03-31 |
| Wing C - Progress | 0.0% |
| Wing C - Booked Units | 0 |
| Wing C - Unbooked Units | 10 |
| Wing D - Start Date | 2017-10-13 |
| Wing D - End Date | 2019-03-31 |
| Wing D - Progress | 0.0% |
| Wing D - Booked Units | 0 |
| Wing D - Unbooked Units | 10 |
| Wing E - Start Date | 2017-10-13 |
| Wing E - End Date | 2019-03-31 |
| Wing E - Progress | 0.0% |
| Wing E - Booked Units | 0 |
| Wing E - Unbooked Units | 10 |
| Bunglow 18 to 27 - Start Date | 2017-10-13 |
| Bunglow 18 to 27 - End Date | 2019-03-31 |
| Bunglow 18 to 27 - Progress | 20.0% |
| Bunglow 18 to 27 - Booked Units | 2 |
| Bunglow 18 to 27 - Unbooked Units | 8 |
| Bunglow 28 to 38 - Start Date | 2017-10-13 |
| Bunglow 28 to 38 - End Date | 2019-03-31 |
| Bunglow 28 to 38 - Progress | 72.73% |
| Bunglow 28 to 38 - Booked Units | 8 |
| Bunglow 28 to 38 - Unbooked Units | 3 |
| Bunglow 39 to 40 - Start Date | 2017-10-13 |
| Bunglow 39 to 40 - End Date | 2019-03-31 |
| Bunglow 39 to 40 - Progress | 0.0% |
| Bunglow 39 to 40 - Booked Units | 0 |
| Bunglow 39 to 40 - Unbooked Units | 2 |
| Bunglow 41 to 49 - Start Date | 2017-10-13 |
| Bunglow 41 to 49 - End Date | 2019-03-31 |
| Bunglow 41 to 49 - Progress | 66.67% |
| Bunglow 41 to 49 - Booked Units | 6 |
| Bunglow 41 to 49 - Unbooked Units | 3 |
| Bunglow 50 to 56 - Start Date | 2017-10-13 |
| Bunglow 50 to 56 - End Date | 2019-03-31 |
| Bunglow 50 to 56 - Progress | 57.14% |
| Bunglow 50 to 56 - Booked Units | 4 |
| Bunglow 50 to 56 - Unbooked Units | 3 |
| Bunglow 57 to 61 - Start Date | 2017-10-13 |
| Bunglow 57 to 61 - End Date | 2019-03-31 |
| Bunglow 57 to 61 - Progress | 20.0% |
| Bunglow 57 to 61 - Booked Units | 1 |
| Bunglow 57 to 61 - Unbooked Units | 4 |
| Bunglow 62 to 67 - Start Date | 2017-10-13 |
| Bunglow 62 to 67 - End Date | 2019-03-31 |
| Bunglow 62 to 67 - Progress | 50.0% |
| Bunglow 62 to 67 - Booked Units | 3 |
| Bunglow 62 to 67 - Unbooked Units | 3 |
| Bunglow 68 to 74 - Start Date | 2017-10-13 |
| Bunglow 68 to 74 - End Date | 2019-03-31 |
| Bunglow 68 to 74 - Progress | 14.29% |
| Bunglow 68 to 74 - Booked Units | 1 |
| Bunglow 68 to 74 - Unbooked Units | 6 |
| Bunglow 77 to 83 - Start Date | 2017-10-13 |
| Bunglow 77 to 83 - End Date | 2019-03-31 |
| Bunglow 77 to 83 - Progress | 57.14% |
| Bunglow 77 to 83 - Booked Units | 4 |
| Bunglow 77 to 83 - Unbooked Units | 3 |
| Bunglow 84 to 89 - Start Date | 2017-10-13 |
| Bunglow 84 to 89 - End Date | 2019-03-31 |
| Bunglow 84 to 89 - Progress | 66.67% |
| Bunglow 84 to 89 - Booked Units | 4 |
| Bunglow 84 to 89 - Unbooked Units | 2 |
| Residential - Total Units | 120 |
| Residential - Completed Units | 0 |
| Residential - Booked Units | 0 |
| Residential - Carpet Area | 11164.33 |
| Residential - Exclusive Area | 0.0 |
| Residential - Open Terrace Area | 0.0 |
| October 2018 | 44.19% |
| January 2019 | 50.65% |
| April 2019 | 65.36% |
| April 2019 | 84.06% |
| Architect | CHIRAG GIRISHBHAI TANTI |
| Licence No. | CA201048563 |
| Engineer | KALPESH J. SATASIYA |
| Licence No. | S115 |
| Contractor | RUSHITBHAI KHIMJIBHAI PATEL |