Ami Exotica
Ami Infrastructure
From Madhapar Circle to Morbi Bypass,, Before ADB Hotel, 150ft Ring Road,
Approved
22nd Jul 2021
Completed
31st Dec 2024
Registration No.
PR/GJ/RAJKOT/RAJKOT/Others/MAA08799/220721
Acknowledgement No.
PR/RAJKOT/RAJKOT/GUJRERA/210629/011131
Project Type
Mixed Development
Approving Authority
Others
District
Rajkot
Taluka
Rajkot
State
Gujarat
Project Details
| Project Name | Ami Exotica |
| RERA Number | PR/GJ/RAJKOT/RAJKOT/Others/MAA08799/220721 |
| Acknowledgement Number | PR/RAJKOT/RAJKOT/GUJRERA/210629/011131 |
| Project Description | It is a mixed project having Bungalows, Flats and shops |
| Project Type | Mixed Development |
| Project Status | Completed |
| District | Rajkot |
| Taluka | Rajkot |
| Address | From Madhapar Circle to Morbi Bypass,, Before ADB Hotel, 150ft Ring Road, |
| State | Gujarat |
| Approving Authority | Others |
| Approved On | 2021-07-22 |
| Start Date | 2020-12-16 |
| End Date | 2024-12-31 |
| Submission Date | 2021-06-23 |
| Months Delayed | 0 |
Area & Cost Details
| Total Land Area | 8896.61 |
| Total Land Area (Registered) | 8896.61 |
| Total Covered Area | 5820.13 |
| Total Open Area | 3076.48 |
| Total Carpet Area | 9327.14 |
| Open Parking Area | 81.49 |
| Covered Parking Area | 0.0 |
| Covered Parking Count | 0 |
| Parking for Sale Count | 1 |
| Cost of Land | 18639680 |
| Estimated Project Cost | 182000000 |
| Total Project Cost | 200639680 |
Promoter Details
| Promoter Name | Ami Infrastructure |
| Promoter Type | PARTNERSHIP FIRM |
| ami********@gmail.com | |
| Mobile | 98******** |
| Company Registration No. | GUJRJ108837 |
| PAN | ABT******* |
| Experience (Years) | 1 |
| Area Constructed (sqm) | 9327 |
| Projects Completed | 0 |
| Ongoing Projects | 1 |
Promoter Partners
| Partner 1 | Paraskumar Navinchandra Ajmera |
| Address | D/17 - Indraprasth Complex,, Raiya Road, |
| Partner 2 | Sheth Nilesh M HUF |
| Address | Block No. 301, 3rd Floor,, Royal Families Appartment, Kalawad Road, |
| Partner 3 | Matalia Tushar P HUF |
| Address | Block No. 302, 3rd Floor,, Royal Families Appartment, Kalawad Road, |
| Partner 4 | Mahendrasinh Bhikhubha Jadeja |
| Address | Radhakrushna 39, Navyug Society,, Near Rameshwar Chowk, Behind Raiya Road, |
| Partner 5 | Jayendrakumar Veljibhai Panchasara |
| Address | Plot No. 27, Vastu, 2 - Tapas Society,, Nana Mauva Main Road, |
| Partner 6 | Huseni Taherali Sadikot |
| Address | Block no. 16/95101, Patrakar Colony Street No. 1,, Airport Road, |
| Partner 7 | Bhavnaben Jentibhai Pithadiya |
| Address | Ashray, Silver Stone Society,, Street No. 2, Opp Big Bazar, |
| Partner 8 | Kishor Hansrajbhai Baldha |
| Address | Gramy Vistar,, Jamkandorna, |
| Partner 9 | Dev Janishbhai Ajmera |
| Address | D/17 - Indraprasth Complex,, Nr. Ambika Park, Raiya Road, |
Building Blocks
| 14TO21+83TO85/1 TO 9 - Start Date | 2020-12-16 |
| 14TO21+83TO85/1 TO 9 - End Date | 2024-12-31 |
| 14TO21+83TO85/1 TO 9 - Progress | 77.78% |
| 14TO21+83TO85/1 TO 9 - Booked Units | 7 |
| 14TO21+83TO85/1 TO 9 - Unbooked Units | 2 |
| 22 TO 57/1 TO 22 - Start Date | 2020-12-16 |
| 22 TO 57/1 TO 22 - End Date | 2024-12-31 |
| 22 TO 57/1 TO 22 - Progress | 90.91% |
| 22 TO 57/1 TO 22 - Booked Units | 20 |
| 22 TO 57/1 TO 22 - Unbooked Units | 2 |
| 58 TO 82/1 TO 16 - Start Date | 2020-12-16 |
| 58 TO 82/1 TO 16 - End Date | 2024-12-31 |
| 58 TO 82/1 TO 16 - Progress | 100.0% |
| 58 TO 82/1 TO 16 - Booked Units | 16 |
| 58 TO 82/1 TO 16 - Unbooked Units | 0 |
| 86 TO 130/1 TO 29 - Start Date | 2020-12-16 |
| 86 TO 130/1 TO 29 - End Date | 2024-12-31 |
| 86 TO 130/1 TO 29 - Progress | 82.76% |
| 86 TO 130/1 TO 29 - Booked Units | 24 |
| 86 TO 130/1 TO 29 - Unbooked Units | 5 |
| 131 TO 135/1 TO 3 - Start Date | 2020-12-16 |
| 131 TO 135/1 TO 3 - End Date | 2024-12-31 |
| 131 TO 135/1 TO 3 - Progress | 66.67% |
| 131 TO 135/1 TO 3 - Booked Units | 2 |
| 131 TO 135/1 TO 3 - Unbooked Units | 1 |
| 136 TO 148/1 TO 8 - Start Date | 2020-12-16 |
| 136 TO 148/1 TO 8 - End Date | 2024-12-31 |
| 136 TO 148/1 TO 8 - Progress | 100.0% |
| 136 TO 148/1 TO 8 - Booked Units | 8 |
| 136 TO 148/1 TO 8 - Unbooked Units | 0 |
| 149 TO 153/1 TO 3 - Start Date | 2020-12-16 |
| 149 TO 153/1 TO 3 - End Date | 2024-12-31 |
| 149 TO 153/1 TO 3 - Progress | 66.67% |
| 149 TO 153/1 TO 3 - Booked Units | 2 |
| 149 TO 153/1 TO 3 - Unbooked Units | 1 |
| 149 TO 153/4 - Start Date | 2020-12-16 |
| 149 TO 153/4 - End Date | 2024-12-31 |
| 149 TO 153/4 - Progress | 77.78% |
| 149 TO 153/4 - Booked Units | 7 |
| 149 TO 153/4 - Unbooked Units | 2 |
Inventory Units
| Residential and Commercial - Total Units | 99 |
| Residential and Commercial - Carpet Area | 9327.14 |
| Residential and Commercial - Exclusive Area | 244.0 |
| Residential and Commercial - Open Terrace Area | 9.67 |
Quarterly Progress
| December 2021 | 46.24% |
| March 2022 | 43.83% |
| June 2022 | 53.92% |
| September 2022 | 57.04% |
| December 2022 | 68.1% |
| March 2023 | 79.09% |
| June 2023 | 88.24% |
| September 2023 | 100.0% |
| January 2025 | 100.0% |
Professionals
| Architect | Prem Trivedi |
| Licence No. | CA/2021/128627 |
| Engineer | SANJAY GOPALBHAI UNJIA |
| Licence No. | ST-35 |
| Contractor | Bhavesh Bhagwanjibhai Rathod |
| Contractor | Praful M Solanki |
The information provided on this page is collated from publicly available resources. PropTech Pulse does not guarantee the accuracy, completeness, or authority of this data and shall not be held liable for any discrepancies. For queries or further assistance, please contact us at pulse@aurumproptech.in