RAJKOT MUNICIPAL CORPORATION
Nr. Central Warehouse, Popatpara
Approved
1st Sept 2023
Pending
31st Dec 2026
Registration No.
PR/GJ/RAJKOT/RAJKOT/Others/MAA12280/010923
Acknowledgement No.
PR/RAJKOT/RAJKOT/GUJRERA/230720/015053
Project Type
Mixed Development
Approving Authority
Others
District
Rajkot
Taluka
Rajkot
State
Gujarat
| Project Name | Central Package 1 -FP 12B |
| RERA Number | PR/GJ/RAJKOT/RAJKOT/Others/MAA12280/010923 |
| Acknowledgement Number | PR/RAJKOT/RAJKOT/GUJRERA/230720/015053 |
| Project Description | Construction of 700 EWS-II Residential Units and 47 Shops at PMAY-AHP, TPS 19 Rajkot FP 12B |
| Project Type | Mixed Development |
| Project Status | APPROVED |
| District | Rajkot |
| Taluka | Rajkot |
| Address | Nr. Central Warehouse, Popatpara |
| State | Gujarat |
| Approving Authority | Others |
| Approved On | 2023-09-01 |
| Start Date | 2023-05-12 |
| End Date | 2026-12-31 |
| Submission Date | 2023-07-01 |
| Months Delayed | 0 |
| Total Land Area | 16251.55 |
| Total Land Area (Registered) | 16251.55 |
| Total Covered Area | 4270.01 |
| Total Open Area | 11981.54 |
| Total Carpet Area | 27598.72 |
| Open Parking Area | 1 |
| Covered Parking Area | 4654.03 |
| Covered Parking Count | 9 |
| Parking for Sale Count | 1 |
| Cost of Land | 0 |
| Estimated Project Cost | 806790450 |
| Total Project Cost | 806790450 |
| Promoter Name | RAJKOT MUNICIPAL CORPORATION |
| Promoter Type | COMPETENT AUTHORITY/ GOVERNMENT |
| czp1fp12a@gmail.com | |
| Mobile | 9723797426 |
| Company Registration No. | NA |
| PAN | AAALR0138G |
| Date of Incorporation | 1973-11-19 |
| Experience (Years) | 50 |
| Area Constructed (sqm) | 62801 |
| Projects Completed | 29 |
| Ongoing Projects | 5 |
| Partner 1 | KAMLESH SHAMJIBHAI GOHEL |
| PAN | ABZPG7255M |
| Address | Krishna Nagar Civic Center, Guruprasad Chowk |
| A - Start Date | 2023-05-12 |
| A - End Date | 2026-12-31 |
| A - Progress | 98.86% |
| A - Booked Units | 87 |
| A - Unbooked Units | 1 |
| B - Start Date | 2023-05-12 |
| B - End Date | 2026-12-31 |
| B - Progress | 95.45% |
| B - Booked Units | 42 |
| B - Unbooked Units | 2 |
| C - Start Date | 2023-05-12 |
| C - End Date | 2026-12-31 |
| C - Progress | 95.45% |
| C - Booked Units | 84 |
| C - Unbooked Units | 4 |
| D - Start Date | 2023-05-12 |
| D - End Date | 2026-12-31 |
| D - Progress | 96.59% |
| D - Booked Units | 85 |
| D - Unbooked Units | 3 |
| E - Start Date | 2023-05-12 |
| E - End Date | 2026-12-31 |
| E - Progress | 97.73% |
| E - Booked Units | 86 |
| E - Unbooked Units | 2 |
| F - Start Date | 2023-05-12 |
| F - End Date | 2026-12-31 |
| F - Progress | 97.73% |
| F - Booked Units | 86 |
| F - Unbooked Units | 2 |
| G - Start Date | 2023-05-12 |
| G - End Date | 2026-12-31 |
| G - Progress | 100.0% |
| G - Booked Units | 88 |
| G - Unbooked Units | 0 |
| H - Start Date | 2023-05-12 |
| H - End Date | 2026-12-31 |
| H - Progress | 92.5% |
| H - Booked Units | 37 |
| H - Unbooked Units | 3 |
| I - Start Date | 2023-05-12 |
| I - End Date | 2026-12-31 |
| I - Progress | 95.45% |
| I - Booked Units | 84 |
| I - Unbooked Units | 4 |
| J - Start Date | 2023-05-12 |
| J - End Date | 2026-12-31 |
| J - Progress | 0.0% |
| J - Booked Units | 0 |
| J - Unbooked Units | 47 |
| Mix Development - Total Units | 747 |
| Mix Development - Carpet Area | 27598.72 |
| Mix Development - Exclusive Area | 1365.0 |
| Mix Development - Open Terrace Area | 0.0 |
| January 2024 | 16.47% |
| April 2024 | 24.93% |
| July 2024 | 27.37% |
| October 2024 | 35.52% |
| October 2025 | 73.93% |
| January 2026 | 90.86% |
| April 2026 | 92.91% |
| Architect | Khyati J. Dalal |
| Licence No. | CA/2020/125376 |
| Engineer | Savan Kakadiya |
| Licence No. | S-121 |
| Contractor | Vinay Infratech Pvt.Ltd. |