RAJKOT MUNICIPAL CORPORATION
Near Jay Prakash Nagar, Bhagwati Para Main Road
Approved
11th Sept 2018
Completed
30th Jun 2022
Registration No.
PR/GJ/RAJKOT/RAJKOT/Others/RAA03397/EX1/170821
Acknowledgement No.
PR/RAJKOT/RAJKOT/RAJKOT TPO/171025/003816
Project Type
Residential/Group Housing
Approving Authority
Rajkot Municipal Corporation
District
Rajkot
Taluka
Rajkot
State
Gujarat
| Project Name | PMAY - Smart Ghar 6 |
| RERA Number | PR/GJ/RAJKOT/RAJKOT/Others/RAA03397/EX1/170821 |
| Acknowledgement Number | PR/RAJKOT/RAJKOT/RAJKOT TPO/171025/003816 |
| Project Description | Construction of 1584 EWS Units by Rajkot Municipal Corporation |
| Project Type | Residential/Group Housing |
| Project Status | RESCIND |
| District | Rajkot |
| Taluka | Rajkot |
| Address | Near Jay Prakash Nagar, Bhagwati Para Main Road |
| Pincode | 360003 |
| State | Gujarat |
| Approving Authority | Rajkot Municipal Corporation |
| Approved On | 2018-09-11 |
| Start Date | 2017-10-24 |
| End Date | 2022-06-30 |
| Submission Date | 2017-10-25 |
| Months Delayed | 0 |
| Total Land Area | 27468.0 |
| Total Land Area (Registered) | 27468.0 |
| Total Covered Area | 9715.0 |
| Total Open Area | 17752.82 |
| Total Carpet Area | 45646.8 |
| Open Parking Area | 10736 |
| Covered Parking Area | 8542.0 |
| Covered Parking Count | 19 |
| Parking for Sale Count | 1 |
| Cost of Land | 0 |
| Estimated Project Cost | 833904946 |
| Total Project Cost | 83390946 |
| Moje | Rajkot |
| TP No. | 31 |
| TP Name | Rajkot |
| Promoter Name | RAJKOT MUNICIPAL CORPORATION |
| Promoter Type | COMPETENT AUTHORITY/ GOVERNMENT |
| czp1fp12a@gmail.com | |
| Mobile | 9723797426 |
| Company Registration No. | NA |
| PAN | AAALR0138G |
| Date of Incorporation | 1973-11-19 |
| Experience (Years) | 50 |
| Area Constructed (sqm) | 62801 |
| Projects Completed | 29 |
| Ongoing Projects | 5 |
| Partner 1 | KAMLESH SHAMJIBHAI GOHEL |
| PAN | ABZPG7255M |
| Address | Krishna Nagar Civic Center, Guruprasad Chowk |
| A1 - Start Date | 2017-10-24 |
| A1 - End Date | 2022-06-30 |
| A1 - Progress | 0.0% |
| A1 - Booked Units | 0 |
| A1 - Unbooked Units | 97 |
| A2 - Start Date | 2017-10-24 |
| A2 - End Date | 2022-06-30 |
| A2 - Progress | 0.0% |
| A2 - Booked Units | 0 |
| A2 - Unbooked Units | 97 |
| A3 - Start Date | 2017-10-24 |
| A3 - End Date | 2022-06-30 |
| A3 - Progress | 0.0% |
| A3 - Booked Units | 0 |
| A3 - Unbooked Units | 97 |
| A4 - Start Date | 2017-10-24 |
| A4 - End Date | 2022-06-30 |
| A4 - Progress | 0.0% |
| A4 - Booked Units | 0 |
| A4 - Unbooked Units | 97 |
| A5 - Start Date | 2017-10-24 |
| A5 - End Date | 2022-06-30 |
| A5 - Progress | 0.0% |
| A5 - Booked Units | 0 |
| A5 - Unbooked Units | 97 |
| B1 - Start Date | 2017-10-24 |
| B1 - End Date | 2022-06-30 |
| B1 - Progress | 0.0% |
| B1 - Booked Units | 0 |
| B1 - Unbooked Units | 84 |
| B2 - Start Date | 2017-10-24 |
| B2 - End Date | 2022-06-30 |
| B2 - Progress | 0.0% |
| B2 - Booked Units | 0 |
| B2 - Unbooked Units | 84 |
| B3 - Start Date | 2017-10-24 |
| B3 - End Date | 2022-06-30 |
| B3 - Progress | 0.0% |
| B3 - Booked Units | 0 |
| B3 - Unbooked Units | 84 |
| B4 - Start Date | 2017-10-24 |
| B4 - End Date | 2022-06-30 |
| B4 - Progress | 0.0% |
| B4 - Booked Units | 0 |
| B4 - Unbooked Units | 84 |
| B5 - Start Date | 2017-10-24 |
| B5 - End Date | 2022-06-30 |
| B5 - Progress | 0.0% |
| B5 - Booked Units | 0 |
| B5 - Unbooked Units | 84 |
| B6 - Start Date | 2017-10-24 |
| B6 - End Date | 2022-06-30 |
| B6 - Progress | 0.0% |
| B6 - Booked Units | 0 |
| B6 - Unbooked Units | 84 |
| B7 - Start Date | 2017-10-24 |
| B7 - End Date | 2022-06-30 |
| B7 - Progress | 0.0% |
| B7 - Booked Units | 0 |
| B7 - Unbooked Units | 84 |
| B8 - Start Date | 2017-10-24 |
| B8 - End Date | 2022-06-30 |
| B8 - Progress | 0.0% |
| B8 - Booked Units | 0 |
| B8 - Unbooked Units | 84 |
| B9 - Start Date | 2017-10-24 |
| B9 - End Date | 2022-06-30 |
| B9 - Progress | 0.0% |
| B9 - Booked Units | 0 |
| B9 - Unbooked Units | 84 |
| B10 - Start Date | 2017-10-24 |
| B10 - End Date | 2022-06-30 |
| B10 - Progress | 0.0% |
| B10 - Booked Units | 0 |
| B10 - Unbooked Units | 84 |
| B11 - Start Date | 2017-10-24 |
| B11 - End Date | 2022-06-30 |
| B11 - Progress | 0.0% |
| B11 - Booked Units | 0 |
| B11 - Unbooked Units | 84 |
| B12 - Start Date | 2017-10-24 |
| B12 - End Date | 2022-06-30 |
| B12 - Progress | 0.0% |
| B12 - Booked Units | 0 |
| B12 - Unbooked Units | 84 |
| B13 - Start Date | 2017-10-24 |
| B13 - End Date | 2022-06-30 |
| B13 - Progress | 0.0% |
| B13 - Booked Units | 0 |
| B13 - Unbooked Units | 84 |
| C - Start Date | 2017-10-24 |
| C - End Date | 2022-06-30 |
| C - Progress | 0.0% |
| C - Booked Units | 0 |
| C - Unbooked Units | 72 |
| Residential - Total Units | 1584 |
| Residential - Completed Units | 0 |
| Residential - Booked Units | 0 |
| Residential - Carpet Area | 44668.8 |
| Residential - Exclusive Area | 0.0 |
| Residential - Open Terrace Area | 0.0 |
| Shop - Total Units | 65 |
| Shop - Completed Units | 0 |
| Shop - Booked Units | 0 |
| Shop - Carpet Area | 978.0 |
| Shop - Exclusive Area | 0.0 |
| Shop - Open Terrace Area | 0.0 |
| February 2019 | 12.75% |
| May 2019 | 23.27% |
| August 2019 | 34.36% |
| November 2019 | 45.92% |
| February 2020 | 59.04% |
| May 2020 | 59.77% |
| November 2020 | 60.78% |
| August 2020 | 60.91% |
| February 2021 | 63.0% |
| May 2021 | 63.92% |
| November 2021 | 66.98% |
| February 2022 | 68.39% |
| May 2022 | 71.01% |
| Architect | Jayesh A. Dalal |
| Licence No. | E283 |
| Engineer | Jayesh A. Dalal |
| Licence No. | SE149 |
| Contractor | Shreeji Krupa Projects Ltd. |