SHREEJI DEVELOPERS
PRAMUKH EXOTICA, ASOPALAV PARK, OPP. SARVODAY SCHOOL,, 80 FT ROAD, MAVDI, RAJKOT
Approved
25th Sept 2018
Completed
30th Jun 2024
Registration No.
PR/GJ/RAJKOT/RAJKOT/Others/RAA03484/250918
Acknowledgement No.
PR/RAJKOT/RAJKOT/RAJKOT TPO/180712/005747
Project Type
Residential/Group Housing
Approving Authority
Rajkot Municipal Corporation
District
Rajkot
Taluka
Rajkot
State
Gujarat
| Project Name | PRAMUKH EXOTICA |
| RERA Number | PR/GJ/RAJKOT/RAJKOT/Others/RAA03484/250918 |
| Acknowledgement Number | PR/RAJKOT/RAJKOT/RAJKOT TPO/180712/005747 |
| Project Description | RESIDENTIAL FLATS |
| Project Type | Residential/Group Housing |
| Project Status | APPROVED |
| District | Rajkot |
| Taluka | Rajkot |
| Address | PRAMUKH EXOTICA, ASOPALAV PARK, OPP. SARVODAY SCHOOL,, 80 FT ROAD, MAVDI, RAJKOT |
| Pincode | 360004 |
| State | Gujarat |
| Approving Authority | Rajkot Municipal Corporation |
| Approved On | 2018-09-25 |
| Start Date | 2018-06-01 |
| End Date | 2024-06-30 |
| Submission Date | 2018-07-12 |
| Months Delayed | 0 |
| Total Land Area | 4411.34 |
| Total Covered Area | 1750.26 |
| Total Open Area | 2661.08 |
| Open Parking Area | 399.94 |
| Covered Parking Area | 2784.59 |
| Covered Parking Count | 1 |
| Parking for Sale Count | 1 |
| Cost of Land | 22799751 |
| Estimated Project Cost | 157861000 |
| Total Project Cost | 192160751 |
| Moje | Rajkot |
| Plot No. | Mavdi |
| Sub Plot No. | - |
| Promoter Name | SHREEJI DEVELOPERS |
| Promoter Type | PARTNERSHIP FIRM |
| pramukhexotica.rera@gmail.com | |
| Mobile | 9426953554 |
| Company Registration No. | NOT APPLICABLE |
| PAN | ADOFS8912N |
| Experience (Years) | 5 |
| Area Constructed (sqm) | 0 |
| Projects Completed | 1 |
| Ongoing Projects | 0 |
| Partner 1 | VIMAL NAVINBHAI LALANI |
| Address | C-401, AVSAR VATIKA, SADHUVASVANI ROAD,, NEAR RAJ PALACE, RAJKOT |
| A1 - Start Date | 2018-06-01 |
| A1 - End Date | 2024-06-30 |
| A1 - Progress | 87.5% |
| A1 - Booked Units | 28 |
| A1 - Unbooked Units | 4 |
| A2 - Start Date | 2018-06-01 |
| A2 - End Date | 2024-06-30 |
| A2 - Progress | 90.62% |
| A2 - Booked Units | 29 |
| A2 - Unbooked Units | 3 |
| B1 - Start Date | 2018-06-01 |
| B1 - End Date | 2024-06-30 |
| B1 - Progress | 96.88% |
| B1 - Booked Units | 31 |
| B1 - Unbooked Units | 1 |
| B2 - Start Date | 2018-06-01 |
| B2 - End Date | 2024-06-30 |
| B2 - Progress | 93.75% |
| B2 - Booked Units | 30 |
| B2 - Unbooked Units | 2 |
| B3 - Start Date | 2018-06-01 |
| B3 - End Date | 2024-06-30 |
| B3 - Progress | 90.62% |
| B3 - Booked Units | 29 |
| B3 - Unbooked Units | 3 |
| Residential - Total Units | 160 |
| Residential - Completed Units | 0 |
| Residential - Booked Units | 0 |
| Residential - Carpet Area | 10120.88 |
| Residential - Exclusive Area | 338.51 |
| Residential - Open Terrace Area | 0.0 |
| February 2019 | 27.76% |
| May 2019 | 41.45% |
| August 2019 | 49.67% |
| November 2019 | 57.12% |
| February 2020 | 66.5% |
| August 2020 | 86.49% |
| November 2020 | 91.26% |
| February 2021 | 100.0% |
| July 2024 | 100.0% |