West Zone Package 1 -FP S2

RAJKOT MUNICIPAL CORPORATION

Ward no 1, b/h raiyadhar water tank, 150 feet ring road

Approved

20th Nov 2019

Completed

30th Mar 2023

Registration No.

PR/GJ/RAJKOT/RAJKOT/Others/MAA06354/201119

Acknowledgement No.

PR/RAJKOT/RAJKOT/RAJKOT TPO/191106/008313

Project Type

Mixed Development

Approving Authority

Rajkot Municipal Corporation

District

Rajkot

Taluka

Rajkot

State

Gujarat

Project Details

Project NameWest Zone Package 1 -FP S2
RERA NumberPR/GJ/RAJKOT/RAJKOT/Others/MAA06354/201119
Acknowledgement NumberPR/RAJKOT/RAJKOT/RAJKOT TPO/191106/008313
Project DescriptionConstruction of 448 MIG Units and 34 Shops at PMAY-AHP, TPS 9 Rajkot FP S2
Project TypeMixed Development
Project StatusAPPROVED
DistrictRajkot
TalukaRajkot
AddressWard no 1, b/h raiyadhar water tank, 150 feet ring road
StateGujarat
Approving AuthorityRajkot Municipal Corporation
Approved On2019-11-20
Start Date2019-03-15
End Date2023-03-30
Submission Date2019-10-20
Months Delayed0

Area & Cost Details

Total Land Area16114.0
Total Land Area (Registered)16114.0
Total Covered Area5700.6
Total Open Area10413.4
Total Carpet Area27481.02
Open Parking Area0
Covered Parking Area8100.73
Covered Parking Count8
Parking for Sale Count0
Cost of Land0
Estimated Project Cost624753935
Total Project Cost624753935

Land Details

MojeRajkot
TP No.9
TP NameRajkot

Promoter Details

Promoter NameRAJKOT MUNICIPAL CORPORATION
Promoter TypeCOMPETENT AUTHORITY/ GOVERNMENT
Emailczp1fp12a@gmail.com
Mobile9723797426
Company Registration No.NA
PANAAALR0138G
Date of Incorporation1973-11-19
Experience (Years)50
Area Constructed (sqm)62801
Projects Completed29
Ongoing Projects5

Promoter Partners

Partner 1KAMLESH SHAMJIBHAI GOHEL
PANABZPG7255M
AddressKrishna Nagar Civic Center, Guruprasad Chowk

Building Blocks

A - Start Date2019-03-15
A - End Date2023-03-30
A - Progress58.93%
A - Booked Units33
A - Unbooked Units23
B - Start Date2019-03-15
B - End Date2023-03-30
B - Progress67.86%
B - Booked Units38
B - Unbooked Units18
C - Start Date2019-03-15
C - End Date2023-03-30
C - Progress73.21%
C - Booked Units41
C - Unbooked Units15
D - Start Date2019-03-15
D - End Date2023-03-30
D - Progress73.21%
D - Booked Units41
D - Unbooked Units15
E - Start Date2019-03-15
E - End Date2023-03-30
E - Progress69.64%
E - Booked Units39
E - Unbooked Units17
F - Start Date2019-03-15
F - End Date2023-03-30
F - Progress67.86%
F - Booked Units38
F - Unbooked Units18
G - Start Date2019-03-15
G - End Date2023-03-30
G - Progress64.29%
G - Booked Units36
G - Unbooked Units20
H - Start Date2019-03-15
H - End Date2023-03-30
H - Progress66.07%
H - Booked Units37
H - Unbooked Units19
I - Start Date2019-03-15
I - End Date2023-03-30
I - Progress0.0%
I - Booked Units0
I - Unbooked Units34

Inventory Units

Mix Development - Total Units482
Mix Development - Carpet Area27024.06
Mix Development - Exclusive Area456.96
Mix Development - Open Terrace Area0.0

Quarterly Progress

April 202030.45%
October 202036.67%
January 202150.22%
April 202156.18%
July 202159.62%
October 202162.55%
January 202266.07%
April 202270.91%
July 202271.72%
October 202281.46%
April 202385.63%

Professionals

ArchitectHimanshu Panchal
Licence No.CA/2008/41868
EngineerSavan Kakadiya
Licence No.S-121
ContractorShanti Construction Co.

Top Properties in Surat

Pexo Icon

Ask Pulse Ai anything about real estate

Unlock the Latest in Real Estate

News, Infographics, Blogs & More! Delivered to your inbox.

Proptech Pulse Logo

Data that drives action.
Insight that inspires action.
Technology that empowers action.“

Made with Love

Statue

© PropTech Pulse 2026, All rights reserved.

Terms of Use and Privacy Policy