VIVANTA DEVELOPERS
F.P. NO. 50/2, T.P. NO. 5 ( VESU-BHIMRAD),, O.P. NO. 50/2, R S.NO. - 117/3/A,
Approved
31st Mar 2021
Pending
31st Dec 2027
Registration No.
PR/GJ/SURAT/SURAT CITY/SUDA/RAA08274/310321
Acknowledgement No.
PR/SURAT/SURAT CITY/SURAT TPO/210301/010490
Project Type
Residential/Group Housing
Approving Authority
SUDA
District
Surat
Taluka
Surat City
State
Gujarat
| Project Name | ANANTA |
| RERA Number | PR/GJ/SURAT/SURAT CITY/SUDA/RAA08274/310321 |
| Acknowledgement Number | PR/SURAT/SURAT CITY/SURAT TPO/210301/010490 |
| Project Description | 4BHK RESIDENTIAL PROJECT HAVING 4 TOWERS |
| Project Type | Residential/Group Housing |
| Project Status | APPROVED |
| District | Surat |
| Taluka | Surat City |
| Address | F.P. NO. 50/2, T.P. NO. 5 ( VESU-BHIMRAD),, O.P. NO. 50/2, R S.NO. - 117/3/A, |
| State | Gujarat |
| Approving Authority | SUDA |
| Approved On | 2021-03-31 |
| Start Date | 2021-02-12 |
| End Date | 2027-12-31 |
| Submission Date | 2021-02-18 |
| Months Delayed | 0 |
| Total Land Area | 5492.0 |
| Total Land Area (Registered) | 5492.0 |
| Total Covered Area | 2063.27 |
| Total Open Area | 3428.73 |
| Total Carpet Area | 16452.0 |
| Open Parking Area | 268.82 |
| Covered Parking Area | 6008.84 |
| Covered Parking Count | 288 |
| Parking for Sale Count | 26 |
| Cost of Land | 266500000 |
| Estimated Project Cost | 923341670 |
| Total Project Cost | 1189841670 |
| Promoter Name | VIVANTA DEVELOPERS |
| Promoter Type | PARTNERSHIP FIRM |
| anantapramukh@gmail.com | |
| Mobile | 9913867643 |
| Company Registration No. | GUJRJ201660 |
| PAN | AAQFV4994C |
| Date of Incorporation | 2018-05-12 |
| Experience (Years) | 15 |
| Area Constructed (sqm) | 16452 |
| Projects Completed | 0 |
| Ongoing Projects | 1 |
| Partner 1 | RAJESH BHATU |
| PAN | BUAPB5260Q |
| Address | C 1001 VIVANTA, VESU |
| Partner 2 | PRASHANT NATUBHAI BHATU |
| PAN | AJBPB0044K |
| Address | B-803, ABHISHEK PARK,, B/H. POOJA ABHISHEK, ATHWALINES |
| Partner 3 | KISHORBHAI BHIKHABHAI CHAVDA |
| PAN | AFFPC0701C |
| Address | B2 503, SAI TIRTH SOCIETY, PALANPUR GAM, OPP. NAKSHATRA PLATINUM |
| A - Start Date | 2021-02-12 |
| A - End Date | 2027-12-31 |
| A - Progress | 91.67% |
| A - Booked Units | 22 |
| A - Unbooked Units | 2 |
| B - Start Date | 2021-02-12 |
| B - End Date | 2027-12-31 |
| B - Progress | 91.67% |
| B - Booked Units | 22 |
| B - Unbooked Units | 2 |
| C - Start Date | 2021-02-12 |
| C - End Date | 2027-12-31 |
| C - Progress | 83.33% |
| C - Booked Units | 20 |
| C - Unbooked Units | 4 |
| D - Start Date | 2021-02-12 |
| D - End Date | 2027-12-31 |
| D - Progress | 79.17% |
| D - Booked Units | 19 |
| D - Unbooked Units | 5 |
| 48 - Total Units | 48 |
| 48 - Carpet Area | 176.9 |
| 48 - Exclusive Area | 18.3 |
| 48 - Open Terrace Area | 0.0 |
| 24 - Total Units | 24 |
| 24 - Carpet Area | 162.7 |
| 24 - Exclusive Area | 13.01 |
| 24 - Open Terrace Area | 0.0 |
| 24 - Total Units | 24 |
| 24 - Carpet Area | 169.0 |
| 24 - Exclusive Area | 13.84 |
| 24 - Open Terrace Area | 0.0 |
| August 2021 | 16.27% |
| November 2021 | 34.3% |
| February 2022 | 38.08% |
| May 2022 | 43.66% |
| August 2022 | 46.13% |
| November 2022 | 60.39% |
| February 2023 | 63.06% |
| May 2023 | 65.81% |
| August 2023 | 72.47% |
| November 2023 | 81.21% |
| January 2024 | 84.37% |
| April 2024 | 85.6% |
| July 2024 | 87.25% |
| October 2024 | 87.25% |
| January 2028 | 87.25% |
| Architect | ADDA ARCHITECTS AND URBAN DESIGNERS |
| Licence No. | CA/2009/44461 |
| Engineer | HEMANT A SHUKLA (TECHNOCRAT CONSULTANT) |
| Licence No. | TDO/ST.DR./36 |
| Contractor | Konark Infratech |