| Project Name | AVADH ERCOLE |
| RERA Number | PR/GJ/SURAT/CHORASI/SUDA/RAA10610/300822 |
| Acknowledgement Number | PR/SURAT/CHORASI/GUJRERA/220729/013175 |
| Project Description | 371 RESIDENTIAL UNIT |
| Project Type | Residential/Group Housing |
| Project Status | APPROVED |
| District | Surat |
| Taluka | Chorasi |
| Address | T.P.S. NO: 26 (ABHVA), F.P. NO: 84 + 85/1 + 92 + 93 + 94, O.P. NO : 84 + 85/1 + 92 + 93 + 94, BLOCK NO.394,389,393+395/1+,395/2,396 AT : ABHVA, TA : MAJURA, DIST : SURAT |
| State | Gujarat |
| Approving Authority | SUDA |
| Approved On | 2022-08-30 |
| Start Date | 2022-06-16 |
| End Date | 2028-12-31 |
| Submission Date | 2022-07-25 |
| Months Delayed | 0 |
| Total Land Area | 27039.0 |
| Total Land Area (Registered) | 27039.0 |
| Total Covered Area | 10005.07 |
| Total Open Area | 17033.93 |
| Total Carpet Area | 86972.4 |
| Open Parking Area | 0 |
| Covered Parking Area | 44677.14 |
| Covered Parking Count | 69 |
| Parking for Sale Count | 0 |
| Cost of Land | 552898968 |
| Estimated Project Cost | 5210000000 |
| Total Project Cost | 5762898968 |
| Promoter Name | AVADH INFRABUILD |
| Promoter Type | PARTNERSHIP FIRM |
| avadhercole@gmail.com | |
| Mobile | 9328135235 |
| Company Registration No. | GUJSR105602 |
| PAN | ABVFA8035B |
| Date of Incorporation | 2021-08-12 |
| Experience (Years) | 2 |
| Area Constructed (sqm) | 1000 |
| Projects Completed | 0 |
| Ongoing Projects | 1 |
| Partner 1 | DILIPKUMAR DAYALAL UNDHAD |
| PAN | AAFPU4623E |
| Address | 101 AVADH ORLENA NEAR RAJHANCE MAXIMA, UMRA SURAT |
| Partner 2 | BHARATKUMAR DAYABHAI UNDHAD |
| PAN | AAFPU4624D |
| Address | C 801 RIVER HEAVEN NEAR KRISHNA TOWNSHIP, MOTA VARACHHA SURAT |
| Partner 3 | MUKESH KESHUBHAI UNDHAD |
| PAN | AANPU1146L |
| Address | C 802 RIVER HEAVEN NEAR KRISHNA TOWNSHIP, MOTA VARACHHA SURAT |
| Partner 4 | BHAVESH CHANDUBHAI LAKHANKIYA |
| PAN | AKFPP0650C |
| Address | A 37 TRIKAM NAGAR SOCIETY 1, LH ROAD SURAT |
| Partner 5 | MITESH CHHAGANLAL BHADANI |
| PAN | AAOPB5402B |
| Address | A 104 LAXMI RESIDENCY, NEAR GAJERA SCHOOL KATARGAM |
| Partner 6 | KIRANKUMAR VALLABHBHAI PATEL |
| PAN | AOXPP4776P |
| Address | SHERI NUMBER 3 AND 5, SUKNATHPARA AMRELI |
| Partner 7 | KIRIT BHIMJIBHAI PATEL |
| PAN | AAQPM5168H |
| Address | B 323 DIVYA VASUNDHARA SOC, LH ROAD |
| A - Start Date | 2022-06-16 |
| A - End Date | 2028-12-31 |
| A - Progress | 65.22% |
| A - Booked Units | 15 |
| A - Unbooked Units | 8 |
| B - Start Date | 2022-06-16 |
| B - End Date | 2028-12-31 |
| B - Progress | 68.18% |
| B - Booked Units | 15 |
| B - Unbooked Units | 7 |
| C - Start Date | 2022-06-16 |
| C - End Date | 2028-12-31 |
| C - Progress | 45.45% |
| C - Booked Units | 10 |
| C - Unbooked Units | 12 |
| D+E - Start Date | 2022-06-16 |
| D+E - End Date | 2028-12-31 |
| D+E - Progress | 72.92% |
| D+E - Booked Units | 35 |
| D+E - Unbooked Units | 13 |
| F - Start Date | 2022-06-16 |
| F - End Date | 2028-12-31 |
| F - Progress | 58.82% |
| F - Booked Units | 20 |
| F - Unbooked Units | 14 |
| G - Start Date | 2022-06-16 |
| G - End Date | 2028-12-31 |
| G - Progress | 63.64% |
| G - Booked Units | 14 |
| G - Unbooked Units | 8 |
| H - Start Date | 2022-06-16 |
| H - End Date | 2028-12-31 |
| H - Progress | 95.45% |
| H - Booked Units | 21 |
| H - Unbooked Units | 1 |
| I - Start Date | 2022-06-16 |
| I - End Date | 2028-12-31 |
| I - Progress | 63.64% |
| I - Booked Units | 14 |
| I - Unbooked Units | 8 |
| J - Start Date | 2022-06-16 |
| J - End Date | 2028-12-31 |
| J - Progress | 40.91% |
| J - Booked Units | 9 |
| J - Unbooked Units | 13 |
| K - Start Date | 2022-06-16 |
| K - End Date | 2028-12-31 |
| K - Progress | 54.55% |
| K - Booked Units | 12 |
| K - Unbooked Units | 10 |
| L - Start Date | 2022-06-16 |
| L - End Date | 2028-12-31 |
| L - Progress | 72.73% |
| L - Booked Units | 16 |
| L - Unbooked Units | 6 |
| M - Start Date | 2022-06-16 |
| M - End Date | 2028-12-31 |
| M - Progress | 68.18% |
| M - Booked Units | 15 |
| M - Unbooked Units | 7 |
| N - Start Date | 2022-06-16 |
| N - End Date | 2028-12-31 |
| N - Progress | 68.18% |
| N - Booked Units | 15 |
| N - Unbooked Units | 7 |
| O - Start Date | 2022-06-16 |
| O - End Date | 2028-12-31 |
| O - Progress | 79.17% |
| O - Booked Units | 19 |
| O - Unbooked Units | 5 |
| P - Start Date | 2022-06-16 |
| P - End Date | 2028-12-31 |
| P - Progress | 86.36% |
| P - Booked Units | 19 |
| P - Unbooked Units | 3 |
| RESIDENTIAL UNIT - Total Units | 371 |
| RESIDENTIAL UNIT - Carpet Area | 86972.4 |
| RESIDENTIAL UNIT - Exclusive Area | 7380.72 |
| RESIDENTIAL UNIT - Open Terrace Area | 0.0 |
| January 2023 | 12.12% |
| April 2023 | 24.91% |
| July 2023 | 40.11% |
| October 2023 | 46.98% |
| July 2024 | 58.83% |
| October 2024 | 65.92% |
| October 2025 | 60.25% |
| January 2026 | 75.99% |
| April 2026 | 85.93% |
| Architect | SANJAY JOSSHI |
| Licence No. | CA/2005/36025 |
| Engineer | Patoliya Dhaval Vrajlal |
| Licence No. | TDO/STDR/419 |


Ask Pulse Ai anything about real estate
News, Infographics, Blogs & More! Delivered to your inbox.