BLUE CITY ENTERPRISE
B No 91, F P No 53/A, TP No.38, Nana varachha, Beh Angel hospital,
Approved
22nd Apr 2019
Completed
30th May 2024
Registration No.
PR/GJ/SURAT/SURAT CITY/SUDA/MAA05303/220419
Acknowledgement No.
PR/SURAT/SURAT CITY/SUDA/190313/006982
Project Type
Mixed Development
Approving Authority
Surat Municipal Corporation
District
Surat
Taluka
Surat City
State
Gujarat
| Project Name | BLUE CITY |
| RERA Number | PR/GJ/SURAT/SURAT CITY/SUDA/MAA05303/220419 |
| Acknowledgement Number | PR/SURAT/SURAT CITY/SUDA/190313/006982 |
| Project Description | Affordable highrise housing project having 360 flat and 16 shops in to 7 building and 13 wings |
| Project Type | Mixed Development |
| Project Status | APPROVED |
| District | Surat |
| Taluka | Surat City |
| Address | B No 91, F P No 53/A, TP No.38, Nana varachha, Beh Angel hospital, |
| Pincode | 395006 |
| State | Gujarat |
| Approving Authority | Surat Municipal Corporation |
| Approved On | 2019-04-22 |
| Start Date | 2018-07-28 |
| End Date | 2024-05-30 |
| Submission Date | 2019-03-04 |
| Months Delayed | 0 |
| Total Land Area | 9917.0 |
| Total Covered Area | 3979.0 |
| Total Open Area | 5938.0 |
| Open Parking Area | 642 |
| Covered Parking Area | 8905.0 |
| Covered Parking Count | 3 |
| Parking for Sale Count | 1 |
| Cost of Land | 211051344 |
| Estimated Project Cost | 425300000 |
| Total Project Cost | 667649344 |
| Moje | Nana Varachha |
| TP No. | 38 |
| TP Name | Nana Varachha |
| Promoter Name | BLUE CITY ENTERPRISE |
| Promoter Type | PARTNERSHIP FIRM |
| bluecity.enterprise3114@gmail.com | |
| Mobile | 9825219145 |
| Company Registration No. | GUJSR203334 |
| PAN | AASFB2672B |
| Date of Incorporation | 2017-08-01 |
| Experience (Years) | 5 |
| Area Constructed (sqm) | 24432 |
| Projects Completed | 1 |
| Ongoing Projects | 1 |
| Partner 1 | ROSHANKUMAR DHIRAJLAL PATEL |
| PAN | AOMPP1192G |
| Address | 186, 187, 188, Kamalbaug Soc.,, Ambavadi L H road |
| Partner 2 | DHIRUBHAI LALLUBHAI GALANI |
| PAN | ABCPG0616M |
| Address | 186, 187, 188, Kamalbaug Soc.,, Ambavadi L H road |
| Partner 3 | PRAVINBHAI LALLUBHAI GALANI |
| PAN | ADHPG2157N |
| Address | 186, 187, 188, Kamalbaug Soc.,, Ambavadi L H road |
| Partner 4 | JAYANTIBHAI LALLUBHAI GALANI |
| PAN | ADLPG4153C |
| Address | 186, 187, 188, Kamalbaug Soc.,, Ambavadi L H road |
| Partner 5 | PURVANG DHIRUBHAI GALANI |
| PAN | BGXPG5923Q |
| Address | 186, 187, 188, Kamalbaug Soc.,, Ambavadi L H road |
| Partner 6 | KIRITBHAI DAHYABHAI GALANI |
| PAN | ACLPG5773D |
| Address | A 6, Jay Jalaram Society,, Varachha road |
| A+B - Start Date | 2018-07-28 |
| A+B - End Date | 2024-05-30 |
| A+B - Progress | 92.06% |
| A+B - Booked Units | 58 |
| A+B - Unbooked Units | 5 |
| C+D - Start Date | 2018-07-28 |
| C+D - End Date | 2024-05-30 |
| C+D - Progress | 94.64% |
| C+D - Booked Units | 53 |
| C+D - Unbooked Units | 3 |
| E+F - Start Date | 2018-07-28 |
| E+F - End Date | 2024-05-30 |
| E+F - Progress | 53.57% |
| E+F - Booked Units | 30 |
| E+F - Unbooked Units | 26 |
| G - Start Date | 2018-07-28 |
| G - End Date | 2024-05-30 |
| G - Progress | 21.88% |
| G - Booked Units | 7 |
| G - Unbooked Units | 25 |
| H+I - Start Date | 2018-07-28 |
| H+I - End Date | 2024-05-30 |
| H+I - Progress | 20.31% |
| H+I - Booked Units | 13 |
| H+I - Unbooked Units | 51 |
| J+K - Start Date | 2018-07-28 |
| J+K - End Date | 2024-05-30 |
| J+K - Progress | 37.5% |
| J+K - Booked Units | 18 |
| J+K - Unbooked Units | 30 |
| L+M - Start Date | 2018-07-28 |
| L+M - End Date | 2024-05-30 |
| L+M - Progress | 10.0% |
| L+M - Booked Units | 6 |
| L+M - Unbooked Units | 54 |
| Flat - Total Units | 360 |
| Flat - Carpet Area | 24044.0 |
| Flat - Exclusive Area | 0.0 |
| Flat - Open Terrace Area | 0.0 |
| Shop - Total Units | 16 |
| Shop - Carpet Area | 389.0 |
| Shop - Exclusive Area | 0.0 |
| Shop - Open Terrace Area | 0.0 |
| September 2019 | 17.24% |
| December 2019 | 21.58% |
| September 2020 | 40.79% |
| December 2020 | 46.89% |
| March 2021 | 55.85% |
| June 2021 | 66.07% |
| September 2021 | 70.39% |
| December 2021 | 83.72% |
| March 2022 | 87.53% |
| June 2022 | 95.13% |
| September 2022 | 97.59% |
| December 2022 | 98.18% |
| March 2023 | 98.18% |
| June 2023 | 98.18% |
| September 2023 | 98.18% |
| December 2023 | 98.18% |
| April 2024 | 87.86% |
| June 2024 | 87.86% |
| Architect | Kaushal S Laheri |
| Licence No. | CA201255846 |
| Engineer | ANIL MISTRY |
| Licence No. | BMC252016 |
| Contractor | Piyush Bhagwanbhai Desai |