BLUE CITY
BLUE CITY ENTERPRISE
B No 91, F P No 53/A, TP No.38, Nana varachha, Beh Angel hospital,
Approved
22nd Apr 2019
Completed
30th May 2024
Registration No.
PR/GJ/SURAT/SURAT CITY/SUDA/MAA05303/220419
Acknowledgement No.
PR/SURAT/SURAT CITY/SUDA/190313/006982
Project Type
Mixed Development
Approving Authority
Surat Municipal Corporation
District
Surat
Taluka
Surat City
State
Gujarat
Project Details
| Project Name | BLUE CITY |
| RERA Number | PR/GJ/SURAT/SURAT CITY/SUDA/MAA05303/220419 |
| Acknowledgement Number | PR/SURAT/SURAT CITY/SUDA/190313/006982 |
| Project Description | Affordable highrise housing project having 360 flat and 16 shops in to 7 building and 13 wings |
| Project Type | Mixed Development |
| Project Status | Completed |
| District | Surat |
| Taluka | Surat City |
| Address | B No 91, F P No 53/A, TP No.38, Nana varachha, Beh Angel hospital, |
| Pincode | 395006 |
| State | Gujarat |
| Approving Authority | Surat Municipal Corporation |
| Approved On | 2019-04-22 |
| Start Date | 2018-07-28 |
| End Date | 2024-05-30 |
| Submission Date | 2019-03-04 |
| Months Delayed | 0 |
Area & Cost Details
| Total Land Area | 9917.0 |
| Total Covered Area | 3979.0 |
| Total Open Area | 5938.0 |
| Open Parking Area | 642 |
| Covered Parking Area | 8905.0 |
| Covered Parking Count | 3 |
| Parking for Sale Count | 1 |
| Cost of Land | 211051344 |
| Estimated Project Cost | 425300000 |
| Total Project Cost | 667649344 |
Land Details
| Moje | Nana Varachha |
| TP No. | 38 |
| TP Name | Nana Varachha |
Promoter Details
| Promoter Name | BLUE CITY ENTERPRISE |
| Promoter Type | PARTNERSHIP FIRM |
| blu********************@gmail.com | |
| Mobile | 98******** |
| Company Registration No. | GUJSR203334 |
| PAN | AAS******* |
| Date of Incorporation | 2017-08-01 |
| Experience (Years) | 5 |
| Area Constructed (sqm) | 24432 |
| Projects Completed | 1 |
| Ongoing Projects | 1 |
Promoter Partners
| Partner 1 | ROSHANKUMAR DHIRAJLAL PATEL |
| PAN | AOM******* |
| Address | 186, 187, 188, Kamalbaug Soc.,, Ambavadi L H road |
| Partner 2 | DHIRUBHAI LALLUBHAI GALANI |
| PAN | ABC******* |
| Address | 186, 187, 188, Kamalbaug Soc.,, Ambavadi L H road |
| Partner 3 | PRAVINBHAI LALLUBHAI GALANI |
| PAN | ADH******* |
| Address | 186, 187, 188, Kamalbaug Soc.,, Ambavadi L H road |
| Partner 4 | JAYANTIBHAI LALLUBHAI GALANI |
| PAN | ADL******* |
| Address | 186, 187, 188, Kamalbaug Soc.,, Ambavadi L H road |
| Partner 5 | PURVANG DHIRUBHAI GALANI |
| PAN | BGX******* |
| Address | 186, 187, 188, Kamalbaug Soc.,, Ambavadi L H road |
| Partner 6 | KIRITBHAI DAHYABHAI GALANI |
| PAN | ACL******* |
| Address | A 6, Jay Jalaram Society,, Varachha road |
Building Blocks
| A+B - Start Date | 2018-07-28 |
| A+B - End Date | 2024-05-30 |
| A+B - Progress | 92.06% |
| A+B - Booked Units | 58 |
| A+B - Unbooked Units | 5 |
| C+D - Start Date | 2018-07-28 |
| C+D - End Date | 2024-05-30 |
| C+D - Progress | 94.64% |
| C+D - Booked Units | 53 |
| C+D - Unbooked Units | 3 |
| E+F - Start Date | 2018-07-28 |
| E+F - End Date | 2024-05-30 |
| E+F - Progress | 53.57% |
| E+F - Booked Units | 30 |
| E+F - Unbooked Units | 26 |
| G - Start Date | 2018-07-28 |
| G - End Date | 2024-05-30 |
| G - Progress | 21.88% |
| G - Booked Units | 7 |
| G - Unbooked Units | 25 |
| H+I - Start Date | 2018-07-28 |
| H+I - End Date | 2024-05-30 |
| H+I - Progress | 20.31% |
| H+I - Booked Units | 13 |
| H+I - Unbooked Units | 51 |
| J+K - Start Date | 2018-07-28 |
| J+K - End Date | 2024-05-30 |
| J+K - Progress | 37.5% |
| J+K - Booked Units | 18 |
| J+K - Unbooked Units | 30 |
| L+M - Start Date | 2018-07-28 |
| L+M - End Date | 2024-05-30 |
| L+M - Progress | 10.0% |
| L+M - Booked Units | 6 |
| L+M - Unbooked Units | 54 |
Inventory Units
| Flat - Total Units | 360 |
| Flat - Carpet Area | 24044.0 |
| Flat - Exclusive Area | 0.0 |
| Flat - Open Terrace Area | 0.0 |
| Shop - Total Units | 16 |
| Shop - Carpet Area | 389.0 |
| Shop - Exclusive Area | 0.0 |
| Shop - Open Terrace Area | 0.0 |
Quarterly Progress
| September 2019 | 17.24% |
| December 2019 | 21.58% |
| September 2020 | 40.79% |
| December 2020 | 46.89% |
| March 2021 | 55.85% |
| June 2021 | 66.07% |
| September 2021 | 70.39% |
| December 2021 | 83.72% |
| March 2022 | 87.53% |
| June 2022 | 95.13% |
| September 2022 | 97.59% |
| December 2022 | 98.18% |
| March 2023 | 98.18% |
| June 2023 | 98.18% |
| September 2023 | 98.18% |
| December 2023 | 98.18% |
| April 2024 | 87.86% |
| June 2024 | 87.86% |
Professionals
| Architect | Kaushal S Laheri |
| Licence No. | CA201255846 |
| Engineer | ANIL MISTRY |
| Licence No. | BMC252016 |
| Contractor | Piyush Bhagwanbhai Desai |
The information provided on this page is collated from publicly available resources. PropTech Pulse does not guarantee the accuracy, completeness, or authority of this data and shall not be held liable for any discrepancies. For queries or further assistance, please contact us at pulse@aurumproptech.in