CELLESTIAL DREAMS
DRB RAVANI DEVELOPERS
R.S. NO. 140 /p1 to p8 ,O.P.-3,F.P.NO.-3 , Notional Plot -A , T.P. Scheme -5 (Vesu - Bhimrad), Canal Rd, Behind South Gujarat University, New Airport Road, Vesu
Approved
9th Nov 2017
Completed
29th Jun 2022
Registration No.
PR/GJ/SURAT/SURAT CITY/SUDA/RAA00654/EX1/090621
Acknowledgement No.
PR/SURAT/SURAT CITY/SUDA/171012/003669
Project Type
Residential/Group Housing
Approving Authority
Surat Municipal Corporation
District
Surat
Taluka
Surat City
State
Gujarat
Project Details
| Project Name | CELLESTIAL DREAMS |
| RERA Number | PR/GJ/SURAT/SURAT CITY/SUDA/RAA00654/EX1/090621 |
| Acknowledgement Number | PR/SURAT/SURAT CITY/SUDA/171012/003669 |
| Project Description | High Rise Residential Building |
| Project Type | Residential/Group Housing |
| Project Status | Completed |
| District | Surat |
| Taluka | Surat City |
| Address | R.S. NO. 140 /p1 to p8 ,O.P.-3,F.P.NO.-3 , Notional Plot -A , T.P. Scheme -5 (Vesu - Bhimrad), Canal Rd, Behind South Gujarat University, New Airport Road, Vesu |
| Pincode | 395007 |
| State | Gujarat |
| Approving Authority | Surat Municipal Corporation |
| Approved On | 2017-11-09 |
| Start Date | 2012-06-26 |
| End Date | 2022-06-29 |
| Submission Date | 2017-10-12 |
| Months Delayed | 0 |
Area & Cost Details
| Total Land Area | 29771.76 |
| Total Land Area (Registered) | 29771.76 |
| Total Covered Area | 9490.28 |
| Total Open Area | 20281.48 |
| Total Carpet Area | 89940.96 |
| Open Parking Area | 3820.25 |
| Covered Parking Area | 51679.0 |
| Covered Parking Count | 400 |
| Parking for Sale Count | 25 |
| Cost of Land | 843125261 |
| Estimated Project Cost | 4042083196 |
| Total Project Cost | 4885208457 |
Land Details
| Moje | Vesu |
| TP No. | 5 |
| TP Name | Vesu - Bhimrad |
| Sub Plot No. | A |
Promoter Details
| Promoter Name | DRB RAVANI DEVELOPERS |
| Promoter Type | PARTNERSHIP FIRM |
| drb******@pradeepsinghi.com | |
| Mobile | 98******** |
| Company Registration No. | NOT APPLICABLE |
| PAN | AAH******* |
| Experience (Years) | 15 |
| Area Constructed (sqm) | 159357 |
| Projects Completed | 0 |
| Ongoing Projects | 1 |
Promoter Partners
| Partner 1 | Dilipbhai Ravani |
| Address | A/202,Four Seasons Appartment ,Opp. Ginger Hotel, Piplod |
Building Blocks
| Building A - Start Date | 2012-06-26 |
| Building A - End Date | 2022-06-29 |
| Building A - Progress | 98.04% |
| Building A - Booked Units | 50 |
| Building A - Unbooked Units | 1 |
| Building B - Start Date | 2012-06-26 |
| Building B - End Date | 2022-06-29 |
| Building B - Progress | 100.0% |
| Building B - Booked Units | 20 |
| Building B - Unbooked Units | 0 |
| Building C - Start Date | 2012-06-26 |
| Building C - End Date | 2022-06-29 |
| Building C - Progress | 92.59% |
| Building C - Booked Units | 50 |
| Building C - Unbooked Units | 4 |
| Building D - Start Date | 2012-06-26 |
| Building D - End Date | 2022-06-29 |
| Building D - Progress | 100.0% |
| Building D - Booked Units | 20 |
| Building D - Unbooked Units | 0 |
| Building E - Start Date | 2012-06-26 |
| Building E - End Date | 2022-06-29 |
| Building E - Progress | 100.0% |
| Building E - Booked Units | 33 |
| Building E - Unbooked Units | 0 |
| Building F - Start Date | 2012-06-26 |
| Building F - End Date | 2022-06-29 |
| Building F - Progress | 100.0% |
| Building F - Booked Units | 20 |
| Building F - Unbooked Units | 0 |
| Building G - Start Date | 2012-06-26 |
| Building G - End Date | 2022-06-29 |
| Building G - Progress | 100.0% |
| Building G - Booked Units | 20 |
| Building G - Unbooked Units | 0 |
Inventory Units
| Flats - Total Units | 219 |
| Flats - Carpet Area | 90040.96 |
| Flats - Exclusive Area | 9077.08 |
| Flats - Open Terrace Area | 0.0 |
Quarterly Progress
| April 2018 | 87.16% |
| July 2018 | 87.98% |
| October 2018 | 89.41% |
| January 2019 | 90.7% |
| April 2019 | 91.46% |
| July 2019 | 92.57% |
| October 2019 | 93.08% |
| January 2020 | 93.5% |
| April 2020 | 93.69% |
| July 2020 | 93.8% |
| October 2020 | 94.25% |
| January 2021 | 94.39% |
| April 2021 | 94.52% |
| July 2021 | 94.52% |
| October 2021 | 99.87% |
| January 2022 | 99.89% |
| April 2022 | 99.89% |
| July 2022 | 99.89% |
| July 2022 | 100.0% |
Professionals
| Architect | BLACK INK |
| Licence No. | TDO/AR/158 |
| Engineer | JW CONSULTANTS LLP |
| Licence No. | TDO/ST EX/2 |
The information provided on this page is collated from publicly available resources. PropTech Pulse does not guarantee the accuracy, completeness, or authority of this data and shall not be held liable for any discrepancies. For queries or further assistance, please contact us at pulse@aurumproptech.in