RAJ ICON
M M INFRASTRUCTURE
BLOCK NO38 GODADRA, CANAL ROAD SURAT
Approved
26th Oct 2018
Completed
30th Jun 2025
Registration No.
PR/GJ/SURAT/SURAT CITY/SUDA/MAA03853/261018
Acknowledgement No.
PR/SURAT/SURAT CITY/SUDA/180820/005976
Project Type
Mixed Development
Approving Authority
Surat Municipal Corporation
District
Surat
Taluka
Surat City
State
Gujarat
Project Details
| Project Name | RAJ ICON |
| RERA Number | PR/GJ/SURAT/SURAT CITY/SUDA/MAA03853/261018 |
| Acknowledgement Number | PR/SURAT/SURAT CITY/SUDA/180820/005976 |
| Project Description | RAJ ICONE |
| Project Type | Mixed Development |
| Project Status | Completed |
| District | Surat |
| Taluka | Surat City |
| Address | BLOCK NO38 GODADRA, CANAL ROAD SURAT |
| Pincode | 395012 |
| State | Gujarat |
| Approving Authority | Surat Municipal Corporation |
| Approved On | 2018-10-26 |
| Start Date | 2018-04-16 |
| End Date | 2025-06-30 |
| Submission Date | 2018-08-20 |
| Months Delayed | 0 |
Area & Cost Details
| Total Land Area | 8088.0 |
| Total Land Area (Registered) | 8088.0 |
| Total Covered Area | 5519.46 |
| Total Open Area | 2568.54 |
| Total Carpet Area | 27151.69 |
| Open Parking Area | 314.83 |
| Covered Parking Area | 2568.54 |
| Covered Parking Count | 0 |
| Parking for Sale Count | 0 |
| Cost of Land | 180000000 |
| Estimated Project Cost | 499161425 |
| Total Project Cost | 719161425 |
Land Details
| Moje | Choryasi |
| TP No. | 61 |
| TP Name | Parvat-Godadra |
| Plot No. | Godadra |
| Sub Plot No. | - |
Promoter Details
| Promoter Name | M M INFRASTRUCTURE |
| Promoter Type | PARTNERSHIP FIRM |
| raj********@gmail.com | |
| Mobile | 98******** |
| Company Registration No. | GUJSR102216 |
| PAN | ABH******* |
| Date of Incorporation | 2017-12-19 |
| Experience (Years) | 0 |
| Area Constructed (sqm) | 0 |
| Projects Completed | 0 |
| Ongoing Projects | 0 |
Promoter Partners
| Partner 1 | BHAVESH MAGANBHAI ZINZALA |
| PAN | AAK******* |
| Address | 1 BHAVYA PALACE, AAI MATA ROAD |
| Partner 2 | MAGANBHAI MATHURBHAI JINJALA |
| PAN | AAV******* |
| Address | BHAVYA PALACE, OPP. RAGHUVIR BUSINESS EMPIRE, AAI MATA ROAD, PARVATPATIYA, SURAT. |
| Partner 3 | MAHESH MAGANBHAI ZINZALA |
| PAN | AAE******* |
| Address | BHAVYA PALACE, OPP. RAGHUVIR BUSINESS EMPIRE, AAI MATA ROAD,PARVAT PATIYA, SURAT. |
Building Blocks
| A - Start Date | 2018-04-16 |
| A - End Date | 2025-06-30 |
| A - Progress | 95.16% |
| A - Booked Units | 59 |
| A - Unbooked Units | 3 |
| B - Start Date | 2018-04-16 |
| B - End Date | 2025-06-30 |
| B - Progress | 66.13% |
| B - Booked Units | 41 |
| B - Unbooked Units | 21 |
| C - Start Date | 2018-04-16 |
| C - End Date | 2025-06-30 |
| C - Progress | 91.94% |
| C - Booked Units | 57 |
| C - Unbooked Units | 5 |
| D - Start Date | 2018-04-16 |
| D - End Date | 2025-06-30 |
| D - Progress | 92.86% |
| D - Booked Units | 52 |
| D - Unbooked Units | 4 |
| E - Start Date | 2018-04-16 |
| E - End Date | 2025-06-30 |
| E - Progress | 94.64% |
| E - Booked Units | 53 |
| E - Unbooked Units | 3 |
| F - Start Date | 2018-04-16 |
| F - End Date | 2025-06-30 |
| F - Progress | 96.43% |
| F - Booked Units | 54 |
| F - Unbooked Units | 2 |
| G - Start Date | 2018-04-16 |
| G - End Date | 2025-06-30 |
| G - Progress | 94.64% |
| G - Booked Units | 53 |
| G - Unbooked Units | 3 |
Inventory Units
| FLAT - Total Units | 392 |
| FLAT - Carpet Area | 26750.5 |
| FLAT - Exclusive Area | 663.06 |
| FLAT - Open Terrace Area | 0.0 |
| SHOP - Total Units | 18 |
| SHOP - Carpet Area | 475.0 |
| SHOP - Exclusive Area | 0.0 |
| SHOP - Open Terrace Area | 0.0 |
Quarterly Progress
| March 2019 | 18.09% |
| June 2019 | 20.83% |
| September 2019 | 28.44% |
| December 2019 | 30.62% |
| March 2020 | 30.94% |
| June 2020 | 32.54% |
| September 2020 | 33.09% |
| December 2020 | 34.47% |
| March 2021 | 37.64% |
| June 2021 | 47.26% |
| September 2021 | 49.78% |
| December 2021 | 51.78% |
| March 2022 | 54.96% |
| June 2022 | 62.84% |
| September 2022 | 65.56% |
| December 2022 | 71.74% |
| March 2023 | 88.17% |
| June 2023 | 88.35% |
| September 2023 | 88.62% |
| January 2024 | 85.8% |
| April 2024 | 87.25% |
| July 2024 | 87.25% |
| October 2024 | 87.25% |
| July 2025 | 87.25% |
Professionals
| Architect | MANSUKH B KELAWALA |
| Licence No. | TDO/ER/653 |
| Engineer | JALIL A SHEIKH |
| Licence No. | TDO/STDR/98 |
| Contractor | SHUBHA CONSTRUCTION |
The information provided on this page is collated from publicly available resources. PropTech Pulse does not guarantee the accuracy, completeness, or authority of this data and shall not be held liable for any discrepancies. For queries or further assistance, please contact us at pulse@aurumproptech.in