RAMAA RESIDENCY
RAMAA BUILDCON
BLOCK NO.102/2/B R.S.NO.163/A,164 PAIKEE 3, TP-44 FP-16 CANAL ROAD JAHANGIRABAD
Approved
4th Jun 2018
Completed
13th Oct 2024
Registration No.
PR/GJ/SURAT/SURAT CITY/SUDA/RAA02816/A1R/170519
Acknowledgement No.
PR/SURAT/SURAT CITY/SUDA/180521/005398
Project Type
Residential/Group Housing
Approving Authority
Surat Municipal Corporation
District
Surat
Taluka
Surat City
State
Gujarat
Project Details
| Project Name | RAMAA RESIDENCY |
| RERA Number | PR/GJ/SURAT/SURAT CITY/SUDA/RAA02816/A1R/170519 |
| Acknowledgement Number | PR/SURAT/SURAT CITY/SUDA/180521/005398 |
| Project Description | 1 BHK AND 2 BHK |
| Project Type | Residential/Group Housing |
| Project Status | Completed |
| District | Surat |
| Taluka | Surat City |
| Address | BLOCK NO.102/2/B R.S.NO.163/A,164 PAIKEE 3, TP-44 FP-16 CANAL ROAD JAHANGIRABAD |
| Pincode | 395005 |
| State | Gujarat |
| Approving Authority | Surat Municipal Corporation |
| Approved On | 2018-06-04 |
| Start Date | 2018-04-13 |
| End Date | 2024-10-13 |
| Submission Date | 2018-05-21 |
| Months Delayed | 0 |
Area & Cost Details
| Total Land Area | 7590.0 |
| Total Land Area (Registered) | 7590.0 |
| Total Covered Area | 2502.06 |
| Total Open Area | 5087.94 |
| Open Parking Area | 0 |
| Covered Parking Area | 8536.92 |
| Covered Parking Count | 0 |
| Parking for Sale Count | 0 |
| Cost of Land | 112080930 |
| Estimated Project Cost | 800040000 |
| Total Project Cost | 1028445078 |
Promoter Details
| Promoter Name | RAMAA BUILDCON |
| Promoter Type | PARTNERSHIP FIRM |
| ram**********@gmail.com | |
| Mobile | 97******** |
| Company Registration No. | GUJSR102168 |
| PAN | AAW******* |
| Date of Incorporation | 2017-08-22 |
| Experience (Years) | 0 |
| Area Constructed (sqm) | 0 |
| Projects Completed | 0 |
| Ongoing Projects | 0 |
Promoter Partners
| Partner 1 | PARTH BHARATBHAI DUNGRANI |
| PAN | BIQ******* |
| Address | 25 VAIBHAV BAUNGLOWS, PIPLOD SURAT |
| Partner 2 | BHARATBHAI ODHABHAI DUNGRANI |
| PAN | ACF******* |
| Address | 25 VAIBHAV BUNGLOWS, PIPLOD SURAT |
| Partner 3 | RAMABAHEN BHARATBHAI DUNGRANI |
| PAN | ABZ******* |
| Address | 25 VAIBHAV BUNGLOWS, PIPLOD SURAT |
| Partner 4 | PRUTHA PARTH DUNGRANI |
| PAN | BAS******* |
| Address | 25 VAIBHAV BUNGLOWS, PIPLOD SURAT |
| Partner 5 | MEET NARENDRA DIYORA |
| PAN | CLW******* |
| Address | 103, MAHAVIR NAGAR SOCIETY, KATARGAM SURAT |
| Partner 6 | TRISHABEN BHARATBHAI DUNGRANI |
| PAN | CNS******* |
| Address | 25 VAIBHAV BAUNGLOWS, PIPLOD SURAT |
Building Blocks
| A1 - Start Date | 2018-04-13 |
| A1 - End Date | 2024-10-13 |
| A1 - Progress | 100.0% |
| A1 - Booked Units | 56 |
| A1 - Unbooked Units | 0 |
| A2 - Start Date | 2018-04-13 |
| A2 - End Date | 2024-10-13 |
| A2 - Progress | 89.29% |
| A2 - Booked Units | 50 |
| A2 - Unbooked Units | 6 |
| B1 - Start Date | 2018-04-13 |
| B1 - End Date | 2024-10-13 |
| B1 - Progress | 91.07% |
| B1 - Booked Units | 51 |
| B1 - Unbooked Units | 5 |
| B2 - Start Date | 2018-04-13 |
| B2 - End Date | 2024-10-13 |
| B2 - Progress | 100.0% |
| B2 - Booked Units | 56 |
| B2 - Unbooked Units | 0 |
| C1 - Start Date | 2018-04-13 |
| C1 - End Date | 2024-10-13 |
| C1 - Progress | 100.0% |
| C1 - Booked Units | 56 |
| C1 - Unbooked Units | 0 |
| C2 - Start Date | 2018-04-13 |
| C2 - End Date | 2024-10-13 |
| C2 - Progress | 98.21% |
| C2 - Booked Units | 55 |
| C2 - Unbooked Units | 1 |
| D1 - Start Date | 2018-04-13 |
| D1 - End Date | 2024-10-13 |
| D1 - Progress | 98.21% |
| D1 - Booked Units | 55 |
| D1 - Unbooked Units | 1 |
| D2 - Start Date | 2018-04-13 |
| D2 - End Date | 2024-10-13 |
| D2 - Progress | 100.0% |
| D2 - Booked Units | 56 |
| D2 - Unbooked Units | 0 |
| D3 - Start Date | 2018-04-13 |
| D3 - End Date | 2024-10-13 |
| D3 - Progress | 96.43% |
| D3 - Booked Units | 54 |
| D3 - Unbooked Units | 2 |
Inventory Units
| Residential - Total Units | 504 |
| Residential - Completed Units | 0 |
| Residential - Booked Units | 96 |
| Residential - Carpet Area | 25438.56 |
| Residential - Exclusive Area | 0.0 |
| Residential - Open Terrace Area | 0.0 |
Quarterly Progress
| November 2018 | 19.92% |
| February 2019 | 31.88% |
| May 2019 | 36.12% |
| August 2019 | 38.89% |
| November 2019 | 40.91% |
| February 2020 | 41.75% |
| May 2020 | 43.53% |
| August 2020 | 43.86% |
| November 2020 | 44.04% |
| February 2021 | 44.81% |
| May 2021 | 47.38% |
| August 2021 | 50.12% |
| November 2021 | 53.18% |
| February 2022 | 55.86% |
| May 2022 | 62.22% |
| August 2022 | 63.67% |
| November 2022 | 64.97% |
| February 2023 | 80.65% |
| May 2023 | 82.96% |
| August 2023 | 85.86% |
| November 2023 | 91.77% |
| January 2024 | 93.91% |
| April 2024 | 96.68% |
| July 2024 | 98.15% |
| October 2024 | 100.0% |
| November 2024 | 100.0% |
The information provided on this page is collated from publicly available resources. PropTech Pulse does not guarantee the accuracy, completeness, or authority of this data and shall not be held liable for any discrepancies. For queries or further assistance, please contact us at pulse@aurumproptech.in