SANTVAN LEXON
MARUTI ENTERPRISE
F.P.56/P/SUB PLOT-2,TP.9-PALANPORE,NEAR GAURAV PATH ROAD,, PALANPORE
Approved
17th Sept 2022
Pending
31st Jul 2027
Registration No.
PR/GJ/SURAT/SURAT CITY/SUDA/RAA10669/170922
Acknowledgement No.
PR/SURAT/SURAT CITY/GUJRERA/220908/013338
Project Type
Residential/Group Housing
Approving Authority
SUDA
District
Surat
Taluka
Surat City
State
Gujarat
Project Details
| Project Name | SANTVAN LEXON |
| RERA Number | PR/GJ/SURAT/SURAT CITY/SUDA/RAA10669/170922 |
| Acknowledgement Number | PR/SURAT/SURAT CITY/GUJRERA/220908/013338 |
| Project Description | RESIDENTIAL PROJECT |
| Project Type | Residential/Group Housing |
| Project Status | APPROVED |
| District | Surat |
| Taluka | Surat City |
| Address | F.P.56/P/SUB PLOT-2,TP.9-PALANPORE,NEAR GAURAV PATH ROAD,, PALANPORE |
| State | Gujarat |
| Approving Authority | SUDA |
| Approved On | 2022-09-17 |
| Start Date | 2022-04-01 |
| End Date | 2027-07-31 |
| Submission Date | 2022-09-03 |
| Months Delayed | 0 |
Area & Cost Details
| Total Land Area | 8405.06 |
| Total Land Area (Registered) | 8405.06 |
| Total Covered Area | 2027.75 |
| Total Open Area | 6377.31 |
| Total Carpet Area | 21677.6 |
| Open Parking Area | 219.96 |
| Covered Parking Area | 7063.35 |
| Covered Parking Count | 280 |
| Parking for Sale Count | 20 |
| Cost of Land | 92136213 |
| Estimated Project Cost | 941629444 |
| Total Project Cost | 1033765657 |
Promoter Details
| Promoter Name | MARUTI ENTERPRISE |
| Promoter Type | PARTNERSHIP FIRM |
| san**********@gmail.com | |
| Mobile | 81******** |
| Company Registration No. | GUJSR106352 |
| PAN | ABT******* |
| Date of Incorporation | 2022-03-08 |
| Experience (Years) | 0 |
| Area Constructed (sqm) | 0 |
| Projects Completed | 0 |
| Ongoing Projects | 0 |
Promoter Partners
| Partner 1 | FENILBHAI JAGDISHBHAI JASOLIYA |
| PAN | BCW******* |
| Address | 28,narmad nagar society, hirabaug,varachha road |
| Partner 2 | RASHMINBHAI JERAMBHAI JASOLIYA |
| PAN | ADL******* |
| Address | 48, Narmad Nagar Society, Hirabaug, Varachha Road |
| Partner 3 | RUMIT RAJENDRABHAI PATEL |
| PAN | CXM******* |
| Address | A/41, VITTHALNAGAR SOCIETY, HIRABAUG, VARACHHA ROAD |
| Partner 4 | SAMIRBHAI SAVJIBHAI PATEL |
| PAN | ADL******* |
| Address | A/41, VITTHALNAGAR SOCIETY, HIRABAUG, VARACHHA ROAD |
| Partner 5 | DHARMESHBHAI POPATBHAI DHOLIYA |
| PAN | AEP******* |
| Address | 34, NANDIGRAM SOCIETY, B/H MINAXIWADI, NR. GAJERA SCHOOL |
| Partner 6 | HARDIK VALLABH BHAI LAKHANI |
| PAN | ABJ******* |
| Address | B-1002, BLUE LIFE, NR. RAJHANS MULTIPLEX, PAL, ADAJAN |
Building Blocks
| Building A - Start Date | 2022-04-01 |
| Building A - End Date | 2027-07-31 |
| Building A - Progress | 39.29% |
| Building A - Booked Units | 11 |
| Building A - Unbooked Units | 17 |
| Building B - Start Date | 2022-04-01 |
| Building B - End Date | 2027-07-31 |
| Building B - Progress | 32.14% |
| Building B - Booked Units | 9 |
| Building B - Unbooked Units | 19 |
| Building C - Start Date | 2022-04-01 |
| Building C - End Date | 2027-07-31 |
| Building C - Progress | 14.29% |
| Building C - Booked Units | 4 |
| Building C - Unbooked Units | 24 |
| Building D - Start Date | 2022-04-01 |
| Building D - End Date | 2027-07-31 |
| Building D - Progress | 25.0% |
| Building D - Booked Units | 7 |
| Building D - Unbooked Units | 21 |
| Building E - Start Date | 2022-04-01 |
| Building E - End Date | 2027-07-31 |
| Building E - Progress | 21.43% |
| Building E - Booked Units | 6 |
| Building E - Unbooked Units | 22 |
| Building F - Start Date | 2022-04-01 |
| Building F - End Date | 2027-07-31 |
| Building F - Progress | 21.43% |
| Building F - Booked Units | 6 |
| Building F - Unbooked Units | 22 |
| Building G - Start Date | 2022-04-01 |
| Building G - End Date | 2027-07-31 |
| Building G - Progress | 39.29% |
| Building G - Booked Units | 11 |
| Building G - Unbooked Units | 17 |
| Building H - Start Date | 2022-04-01 |
| Building H - End Date | 2027-07-31 |
| Building H - Progress | 32.14% |
| Building H - Booked Units | 9 |
| Building H - Unbooked Units | 19 |
| Building I - Start Date | 2022-04-01 |
| Building I - End Date | 2027-07-31 |
| Building I - Progress | 60.71% |
| Building I - Booked Units | 17 |
| Building I - Unbooked Units | 11 |
| Building J - Start Date | 2022-04-01 |
| Building J - End Date | 2027-07-31 |
| Building J - Progress | 53.57% |
| Building J - Booked Units | 15 |
| Building J - Unbooked Units | 13 |
Inventory Units
| FLATS - Total Units | 280 |
| FLATS - Carpet Area | 21677.6 |
| FLATS - Exclusive Area | 826.0 |
| FLATS - Open Terrace Area | 0.0 |
Quarterly Progress
| February 2023 | 0.0% |
| May 2023 | 31.88% |
| August 2023 | 34.85% |
| November 2023 | 39.47% |
| January 2024 | 47.87% |
| April 2024 | 53.28% |
| July 2024 | 54.13% |
| October 2024 | 58.65% |
| October 2025 | 79.56% |
| January 2026 | 91.14% |
| April 2026 | 98.8% |
Professionals
| Architect | Chirag sheta |
| Licence No. | COA/2016/78007 |
| Engineer | Ramesh N Shingala |
| Licence No. | TDO/ST/DR/353 |
The information provided on this page is collated from publicly available resources. PropTech Pulse does not guarantee the accuracy, completeness, or authority of this data and shall not be held liable for any discrepancies. For queries or further assistance, please contact us at pulse@aurumproptech.in