MARUTI ENTERPRISE
F.P.56/P/SUB PLOT-2,TP.9-PALANPORE,NEAR GAURAV PATH ROAD,, PALANPORE
Approved
17th Sept 2022
Pending
31st Jul 2027
Registration No.
PR/GJ/SURAT/SURAT CITY/SUDA/RAA10669/170922
Acknowledgement No.
PR/SURAT/SURAT CITY/GUJRERA/220908/013338
Project Type
Residential/Group Housing
Approving Authority
SUDA
District
Surat
Taluka
Surat City
State
Gujarat
| Project Name | SANTVAN LEXON |
| RERA Number | PR/GJ/SURAT/SURAT CITY/SUDA/RAA10669/170922 |
| Acknowledgement Number | PR/SURAT/SURAT CITY/GUJRERA/220908/013338 |
| Project Description | RESIDENTIAL PROJECT |
| Project Type | Residential/Group Housing |
| Project Status | APPROVED |
| District | Surat |
| Taluka | Surat City |
| Address | F.P.56/P/SUB PLOT-2,TP.9-PALANPORE,NEAR GAURAV PATH ROAD,, PALANPORE |
| State | Gujarat |
| Approving Authority | SUDA |
| Approved On | 2022-09-17 |
| Start Date | 2022-04-01 |
| End Date | 2027-07-31 |
| Submission Date | 2022-09-03 |
| Months Delayed | 0 |
| Total Land Area | 8405.06 |
| Total Land Area (Registered) | 8405.06 |
| Total Covered Area | 2027.75 |
| Total Open Area | 6377.31 |
| Total Carpet Area | 21677.6 |
| Open Parking Area | 219.96 |
| Covered Parking Area | 7063.35 |
| Covered Parking Count | 280 |
| Parking for Sale Count | 20 |
| Cost of Land | 92136213 |
| Estimated Project Cost | 941629444 |
| Total Project Cost | 1033765657 |
| Promoter Name | MARUTI ENTERPRISE |
| Promoter Type | PARTNERSHIP FIRM |
| santvanseron1@gmail.com | |
| Mobile | 8141333334 |
| Company Registration No. | GUJSR106352 |
| PAN | ABTFM4600L |
| Date of Incorporation | 2022-03-08 |
| Experience (Years) | 0 |
| Area Constructed (sqm) | 0 |
| Projects Completed | 0 |
| Ongoing Projects | 0 |
| Partner 1 | FENILBHAI JAGDISHBHAI JASOLIYA |
| PAN | BCWPP1294E |
| Address | 28,narmad nagar society, hirabaug,varachha road |
| Partner 2 | RASHMINBHAI JERAMBHAI JASOLIYA |
| PAN | ADLPP8569K |
| Address | 48, Narmad Nagar Society, Hirabaug, Varachha Road |
| Partner 3 | RUMIT RAJENDRABHAI PATEL |
| PAN | CXMPP7723C |
| Address | A/41, VITTHALNAGAR SOCIETY, HIRABAUG, VARACHHA ROAD |
| Partner 4 | SAMIRBHAI SAVJIBHAI PATEL |
| PAN | ADLPP8568J |
| Address | A/41, VITTHALNAGAR SOCIETY, HIRABAUG, VARACHHA ROAD |
| Partner 5 | DHARMESHBHAI POPATBHAI DHOLIYA |
| PAN | AEPPD6971C |
| Address | 34, NANDIGRAM SOCIETY, B/H MINAXIWADI, NR. GAJERA SCHOOL |
| Partner 6 | HARDIK VALLABH BHAI LAKHANI |
| PAN | ABJPL9837G |
| Address | B-1002, BLUE LIFE, NR. RAJHANS MULTIPLEX, PAL, ADAJAN |
| Building A - Start Date | 2022-04-01 |
| Building A - End Date | 2027-07-31 |
| Building A - Progress | 39.29% |
| Building A - Booked Units | 11 |
| Building A - Unbooked Units | 17 |
| Building B - Start Date | 2022-04-01 |
| Building B - End Date | 2027-07-31 |
| Building B - Progress | 32.14% |
| Building B - Booked Units | 9 |
| Building B - Unbooked Units | 19 |
| Building C - Start Date | 2022-04-01 |
| Building C - End Date | 2027-07-31 |
| Building C - Progress | 14.29% |
| Building C - Booked Units | 4 |
| Building C - Unbooked Units | 24 |
| Building D - Start Date | 2022-04-01 |
| Building D - End Date | 2027-07-31 |
| Building D - Progress | 25.0% |
| Building D - Booked Units | 7 |
| Building D - Unbooked Units | 21 |
| Building E - Start Date | 2022-04-01 |
| Building E - End Date | 2027-07-31 |
| Building E - Progress | 21.43% |
| Building E - Booked Units | 6 |
| Building E - Unbooked Units | 22 |
| Building F - Start Date | 2022-04-01 |
| Building F - End Date | 2027-07-31 |
| Building F - Progress | 21.43% |
| Building F - Booked Units | 6 |
| Building F - Unbooked Units | 22 |
| Building G - Start Date | 2022-04-01 |
| Building G - End Date | 2027-07-31 |
| Building G - Progress | 39.29% |
| Building G - Booked Units | 11 |
| Building G - Unbooked Units | 17 |
| Building H - Start Date | 2022-04-01 |
| Building H - End Date | 2027-07-31 |
| Building H - Progress | 32.14% |
| Building H - Booked Units | 9 |
| Building H - Unbooked Units | 19 |
| Building I - Start Date | 2022-04-01 |
| Building I - End Date | 2027-07-31 |
| Building I - Progress | 60.71% |
| Building I - Booked Units | 17 |
| Building I - Unbooked Units | 11 |
| Building J - Start Date | 2022-04-01 |
| Building J - End Date | 2027-07-31 |
| Building J - Progress | 53.57% |
| Building J - Booked Units | 15 |
| Building J - Unbooked Units | 13 |
| FLATS - Total Units | 280 |
| FLATS - Carpet Area | 21677.6 |
| FLATS - Exclusive Area | 826.0 |
| FLATS - Open Terrace Area | 0.0 |
| February 2023 | 0.0% |
| May 2023 | 31.88% |
| August 2023 | 34.85% |
| November 2023 | 39.47% |
| January 2024 | 47.87% |
| April 2024 | 53.28% |
| July 2024 | 54.13% |
| October 2024 | 58.65% |
| October 2025 | 79.56% |
| January 2026 | 91.14% |
| April 2026 | 98.8% |
| Architect | Chirag sheta |
| Licence No. | COA/2016/78007 |
| Engineer | Ramesh N Shingala |
| Licence No. | TDO/ST/DR/353 |