SHANTA GODAVARI INFRA
RS. No 299/2, tps no. 6, FP NO 41/1, VIP ROAD, VESU
Approved
24th Nov 2017
Completed
30th Jun 2023
Registration No.
PR/GJ/SURAT/CHORASI/SUDA/RAA00811/EX2/210223
Acknowledgement No.
PR/SURAT/CHORASI/SUDA/170817/001560
Project Type
Residential/Group Housing
Approving Authority
Surat Municipal Corporation
District
Surat
Taluka
Chorasi
State
Gujarat
| Project Name | SHANTA GODAVARI LUXURY VILLAS |
| RERA Number | PR/GJ/SURAT/CHORASI/SUDA/RAA00811/EX2/210223 |
| Acknowledgement Number | PR/SURAT/CHORASI/SUDA/170817/001560 |
| Project Description | LUXURY VILLAS WITH INHOUSE AMENITIES AND FACILITIES |
| Project Type | Residential/Group Housing |
| Project Status | APPROVED |
| District | Surat |
| Taluka | Chorasi |
| Address | RS. No 299/2, tps no. 6, FP NO 41/1, VIP ROAD, VESU |
| Pincode | 394518 |
| State | Gujarat |
| Approving Authority | Surat Municipal Corporation |
| Approved On | 2017-11-24 |
| Start Date | 2016-04-15 |
| End Date | 2023-06-30 |
| Submission Date | 2017-08-17 |
| Months Delayed | 0 |
| Total Land Area | 4554.5 |
| Total Land Area (Registered) | 4554.5 |
| Total Covered Area | 1635.04 |
| Total Open Area | 1655.19 |
| Total Carpet Area | 3211.0 |
| Open Parking Area | 0 |
| Covered Parking Area | 1093.28 |
| Covered Parking Count | 34 |
| Parking for Sale Count | 0 |
| Cost of Land | 127929000 |
| Estimated Project Cost | 120000000 |
| Total Project Cost | 247929000 |
| Moje | Vesu |
| TP No. | 6 |
| TP Name | Vesu |
| Sub Plot No. | 1 |
| Promoter Name | SHANTA GODAVARI INFRA |
| Promoter Type | PARTNERSHIP FIRM |
| mehul_metawala@yahoo.com | |
| Mobile | 9428627215 |
| Company Registration No. | NOT APPLICABLE |
| PAN | ADAFS1855J |
| Experience (Years) | 1 |
| Area Constructed (sqm) | 4555 |
| Projects Completed | 0 |
| Ongoing Projects | 1 |
| Partner 1 | VISHAL METAWALA |
| Address | 57,58,subhas nagar society ,behind st.xaviers school,, Ghod dod Road, Surat |
| Partner 2 | VISHAL METAWALA |
| Address | 57,58,subhas nagar society ,behind st.xaviers school,, Ghod dod Road, Surat |
| Unit 1 - Start Date | 2016-04-15 |
| Unit 1 - End Date | 2023-06-30 |
| Unit 1 - Progress | 100.0% |
| Unit 1 - Booked Units | 2 |
| Unit 1 - Unbooked Units | 0 |
| Unit 2 - Start Date | 2016-04-15 |
| Unit 2 - End Date | 2023-06-30 |
| Unit 2 - Progress | 100.0% |
| Unit 2 - Booked Units | 2 |
| Unit 2 - Unbooked Units | 0 |
| Unit 3 - Start Date | 2016-04-15 |
| Unit 3 - End Date | 2023-06-30 |
| Unit 3 - Progress | 100.0% |
| Unit 3 - Booked Units | 2 |
| Unit 3 - Unbooked Units | 0 |
| Unit 4 - Start Date | 2016-04-15 |
| Unit 4 - End Date | 2023-06-30 |
| Unit 4 - Progress | 100.0% |
| Unit 4 - Booked Units | 2 |
| Unit 4 - Unbooked Units | 0 |
| Unit 5 - Start Date | 2016-04-15 |
| Unit 5 - End Date | 2023-06-30 |
| Unit 5 - Progress | 0.0% |
| Unit 5 - Booked Units | 0 |
| Unit 5 - Unbooked Units | 2 |
| Unit 6 - Start Date | 2016-04-15 |
| Unit 6 - End Date | 2023-06-30 |
| Unit 6 - Progress | 100.0% |
| Unit 6 - Booked Units | 2 |
| Unit 6 - Unbooked Units | 0 |
| Unit 7 - Start Date | 2016-04-15 |
| Unit 7 - End Date | 2023-06-30 |
| Unit 7 - Progress | 100.0% |
| Unit 7 - Booked Units | 2 |
| Unit 7 - Unbooked Units | 0 |
| Unit 8 - Start Date | 2016-04-15 |
| Unit 8 - End Date | 2023-06-30 |
| Unit 8 - Progress | 100.0% |
| Unit 8 - Booked Units | 2 |
| Unit 8 - Unbooked Units | 0 |
| Unit 9 - Start Date | 2016-04-15 |
| Unit 9 - End Date | 2023-06-30 |
| Unit 9 - Progress | 100.0% |
| Unit 9 - Booked Units | 2 |
| Unit 9 - Unbooked Units | 0 |
| Unit 10 - Start Date | 2016-04-15 |
| Unit 10 - End Date | 2023-06-30 |
| Unit 10 - Progress | 100.0% |
| Unit 10 - Booked Units | 2 |
| Unit 10 - Unbooked Units | 0 |
| Unit 11 - Start Date | 2016-04-15 |
| Unit 11 - End Date | 2023-06-30 |
| Unit 11 - Progress | 100.0% |
| Unit 11 - Booked Units | 2 |
| Unit 11 - Unbooked Units | 0 |
| Unit 12 - Start Date | 2016-04-15 |
| Unit 12 - End Date | 2023-06-30 |
| Unit 12 - Progress | 100.0% |
| Unit 12 - Booked Units | 2 |
| Unit 12 - Unbooked Units | 0 |
| Unit 13 - Start Date | 2016-04-15 |
| Unit 13 - End Date | 2023-06-30 |
| Unit 13 - Progress | 100.0% |
| Unit 13 - Booked Units | 2 |
| Unit 13 - Unbooked Units | 0 |
| Unit 14 - Start Date | 2016-04-15 |
| Unit 14 - End Date | 2023-06-30 |
| Unit 14 - Progress | 100.0% |
| Unit 14 - Booked Units | 2 |
| Unit 14 - Unbooked Units | 0 |
| Unit 15 - Start Date | 2016-04-15 |
| Unit 15 - End Date | 2023-06-30 |
| Unit 15 - Progress | 100.0% |
| Unit 15 - Booked Units | 2 |
| Unit 15 - Unbooked Units | 0 |
| Unit 16 - Start Date | 2016-04-15 |
| Unit 16 - End Date | 2023-06-30 |
| Unit 16 - Progress | 100.0% |
| Unit 16 - Booked Units | 2 |
| Unit 16 - Unbooked Units | 0 |
| Unit 17 - Start Date | 2016-04-15 |
| Unit 17 - End Date | 2023-06-30 |
| Unit 17 - Progress | 0.0% |
| Unit 17 - Booked Units | 0 |
| Unit 17 - Unbooked Units | 2 |
| Unit 18 - Start Date | 2016-04-15 |
| Unit 18 - End Date | 2023-06-30 |
| Unit 18 - Progress | 0.0% |
| Unit 18 - Booked Units | 0 |
| Unit 18 - Unbooked Units | 2 |
| Unit 19 - Start Date | 2016-04-15 |
| Unit 19 - End Date | 2023-06-30 |
| Unit 19 - Progress | 100.0% |
| Unit 19 - Booked Units | 2 |
| Unit 19 - Unbooked Units | 0 |
| Unit 20 - Start Date | 2016-04-15 |
| Unit 20 - End Date | 2023-06-30 |
| Unit 20 - Progress | 100.0% |
| Unit 20 - Booked Units | 2 |
| Unit 20 - Unbooked Units | 0 |
| Unit 21 - Start Date | 2016-04-15 |
| Unit 21 - End Date | 2023-06-30 |
| Unit 21 - Progress | 0.0% |
| Unit 21 - Booked Units | 0 |
| Unit 21 - Unbooked Units | 2 |
| Unit 22 - Start Date | 2016-04-15 |
| Unit 22 - End Date | 2023-06-30 |
| Unit 22 - Progress | 0.0% |
| Unit 22 - Booked Units | 0 |
| Unit 22 - Unbooked Units | 2 |
| Residential - Total Units | 44 |
| Residential - Completed Units | 0 |
| Residential - Booked Units | 0 |
| Residential - Carpet Area | 6423.4 |
| Residential - Exclusive Area | 0.0 |
| Residential - Open Terrace Area | 0.0 |
| January 2019 | 46.9% |
| April 2019 | 80.45% |
| July 2019 | 72.36% |
| October 2019 | 73.44% |
| January 2020 | 72.68% |
| April 2020 | 72.82% |
| October 2020 | 72.82% |
| January 2021 | 75.81% |
| April 2021 | 76.5% |
| July 2021 | 79.82% |
| October 2021 | 80.4% |
| January 2022 | 80.63% |
| April 2022 | 80.75% |
| July 2022 | 80.75% |
| April 2023 | 99.0% |
| July 2023 | 100.0% |
| July 2023 | 100.0% |