Shiv Shakti Builders
F.P. NO. 51/B/1, T.P. NO. 24, BEHIND KRISHNA TOWNSHIP, NEAR RAJHANS ROW HOUSE, SUDAMA CHOWK, MOTA VARACHHA
Approved
26th Dec 2018
Pending
18th Jan 2029
Registration No.
PR/GJ/SURAT/CHORASI/SUDA/RAA04473/261218
Acknowledgement No.
PR/SURAT/CHORASI/SUDA/180822/005929
Project Type
Residential/Group Housing
Approving Authority
Surat Municipal Corporation
District
Surat
Taluka
Chorasi
State
Gujarat
| Project Name | SHIV SHAKTI PARADISE |
| RERA Number | PR/GJ/SURAT/CHORASI/SUDA/RAA04473/261218 |
| Acknowledgement Number | PR/SURAT/CHORASI/SUDA/180822/005929 |
| Project Description | 1. The project “SHIV SHAKTI PARADISE” is located at Block No. 191/B/1, F.P. No. 51/B/1, O.P. 191/B/1, T.P. No. 24, Mota Varachha in Surat City, Gujarat. 394101. 2. The project cosist of 5 buildings with gray and brown colour. The project has two parking |
| Project Type | Residential/Group Housing |
| Project Status | APPROVED |
| District | Surat |
| Taluka | Chorasi |
| Address | F.P. NO. 51/B/1, T.P. NO. 24, BEHIND KRISHNA TOWNSHIP, NEAR RAJHANS ROW HOUSE, SUDAMA CHOWK, MOTA VARACHHA |
| Pincode | 394101 |
| State | Gujarat |
| Approving Authority | Surat Municipal Corporation |
| Approved On | 2018-12-26 |
| Start Date | 2017-07-19 |
| End Date | 2029-01-18 |
| Submission Date | 2018-08-22 |
| Months Delayed | 0 |
| Total Land Area | 4625.0 |
| Total Covered Area | 2584.57 |
| Total Open Area | 2040.43 |
| Open Parking Area | 0 |
| Covered Parking Area | 3353.44 |
| Covered Parking Count | 360 |
| Parking for Sale Count | 0 |
| Cost of Land | 34703173 |
| Estimated Project Cost | 266198278 |
| Total Project Cost | 300901451 |
| Moje | Surat City |
| TP No. | 24 |
| TP Name | Mota Varachha |
| Plot No. | Mota Varachha |
| Sub Plot No. | - |
| Promoter Name | Shiv Shakti Builders |
| Promoter Type | PARTNERSHIP FIRM |
| shivshaktibuilders@rvaghasia.net | |
| Mobile | 9879555331 |
| Company Registration No. | NOTAPPLICABLE |
| PAN | ADOFS0209G |
| Date of Incorporation | 2017-12-13 |
| Experience (Years) | 0 |
| Area Constructed (sqm) | 0 |
| Projects Completed | 0 |
| Ongoing Projects | 0 |
| Partner 1 | ALPESHBHAI KANUBHAI SELADIA |
| PAN | AFAPS0543P |
| Address | 33, DHARMISHTHA PARK, B/H UMIYA DHAM TEMPLE, A.K. ROAD |
| Partner 2 | RIPULBHAI KANUBHAI SELADIA |
| PAN | ADZPS8577J |
| Address | 33, Dharmishta Park Society, A.K. Road |
| Partner 3 | HASMUKHBHAI MOHANBHAI PATEL |
| PAN | AAVPP7792F |
| Address | 36, Sahaj Park Row House, Nr. P.P. Savani School, A.K. Road |
| Partner 4 | KEVINKUMAR VASANTBHAI PATEL |
| PAN | ARAPP2989E |
| Address | 114, Patel Faliyu, Nansad |
| BUILDING A - Start Date | 2017-07-19 |
| BUILDING A - End Date | 2029-01-18 |
| BUILDING A - Progress | 59.38% |
| BUILDING A - Booked Units | 19 |
| BUILDING A - Unbooked Units | 13 |
| BUILDING B - Start Date | 2017-07-19 |
| BUILDING B - End Date | 2029-01-18 |
| BUILDING B - Progress | 65.62% |
| BUILDING B - Booked Units | 21 |
| BUILDING B - Unbooked Units | 11 |
| BUILDING C - Start Date | 2017-07-19 |
| BUILDING C - End Date | 2029-01-18 |
| BUILDING C - Progress | 59.38% |
| BUILDING C - Booked Units | 19 |
| BUILDING C - Unbooked Units | 13 |
| BUILDING D - Start Date | 2017-07-19 |
| BUILDING D - End Date | 2029-01-18 |
| BUILDING D - Progress | 28.12% |
| BUILDING D - Booked Units | 9 |
| BUILDING D - Unbooked Units | 23 |
| BUILDING E - Start Date | 2017-07-19 |
| BUILDING E - End Date | 2029-01-18 |
| BUILDING E - Progress | 21.88% |
| BUILDING E - Booked Units | 7 |
| BUILDING E - Unbooked Units | 25 |
| Residential - Total Units | 160 |
| Residential - Completed Units | 0 |
| Residential - Booked Units | 0 |
| Residential - Carpet Area | 10041.28 |
| Residential - Exclusive Area | 753.28 |
| Residential - Open Terrace Area | 0.0 |
| May 2019 | 37.52% |
| August 2019 | 38.58% |
| November 2019 | 41.31% |
| February 2020 | 43.69% |
| August 2020 | 45.49% |
| November 2020 | 46.57% |
| February 2021 | 50.61% |
| May 2021 | 52.78% |
| August 2021 | 53.42% |
| November 2021 | 53.79% |
| February 2022 | 55.65% |
| July 2022 | 51.47% |
| October 2022 | 62.17% |
| January 2023 | 68.1% |
| April 2023 | 68.95% |
| July 2023 | 74.5% |
| October 2023 | 75.35% |
| January 2024 | 76.69% |
| April 2024 | 77.76% |
| July 2024 | 83.52% |
| October 2024 | 100.0% |
| February 2029 | 100.0% |
| Architect | CHIRAG L. GOTI |
| Licence No. | CA/2017/86499 |
| Engineer | HEMANT SHUKLA |
| Licence No. | TDO/ST.DR/36 |