SHIVA PARK
ATYANTA DEVELOPERS PRIVATE LIMITED
T.P.S.NO.-03(KARANJ) R.S. NO 27 O.P.NO.19, F.P.NO.-72 PAKIKEE SUB PLOT-01(KARANJ) SURAT
Approved
14th Nov 2018
Completed
1st Dec 2023
Registration No.
PR/GJ/SURAT/SURAT CITY/SUDA/PAA04025/141118
Acknowledgement No.
PR/SURAT/SURAT CITY/GANDHINAGAR TPO/181101/006335
Project Type
Plotted Development
Approving Authority
Surat Municipal Corporation
District
Surat
Taluka
Surat City
State
Gujarat
Project Details
| Project Name | SHIVA PARK |
| RERA Number | PR/GJ/SURAT/SURAT CITY/SUDA/PAA04025/141118 |
| Acknowledgement Number | PR/SURAT/SURAT CITY/GANDHINAGAR TPO/181101/006335 |
| Project Description | OPEN PLOTTING PROJECT |
| Project Type | Plotted Development |
| Project Status | Completed |
| District | Surat |
| Taluka | Surat City |
| Address | T.P.S.NO.-03(KARANJ) R.S. NO 27 O.P.NO.19, F.P.NO.-72 PAKIKEE SUB PLOT-01(KARANJ) SURAT |
| Pincode | 395010 |
| State | Gujarat |
| Approving Authority | Surat Municipal Corporation |
| Approved On | 2018-11-14 |
| Start Date | 2018-05-23 |
| End Date | 2023-12-01 |
| Submission Date | 2018-11-01 |
| Months Delayed | 0 |
Area & Cost Details
| Total Land Area | 27237.0 |
| Total Covered Area | 24498.33 |
| Total Open Area | 2738.67 |
| Open Parking Area | 0 |
| Covered Parking Area | 0.0 |
| Covered Parking Count | 0 |
| Parking for Sale Count | 0 |
| Cost of Land | 275636839 |
| Estimated Project Cost | 49675000 |
| Total Project Cost | 325311839 |
Land Details
| Moje | Surat |
| TP No. | 3 |
| TP Name | Karanj |
| Plot No. | Karanj |
Promoter Details
| Promoter Name | ATYANTA DEVELOPERS PRIVATE LIMITED |
| Promoter Type | COMPANY |
| shi********@gmail.com | |
| Mobile | 98******** |
| Company Registration No. | U45400GJ2013PTC076672 |
| PAN | AAL******* |
| Date of Incorporation | 2013-09-03 |
| Experience (Years) | 1 |
| Area Constructed (sqm) | 5250 |
| Projects Completed | 1 |
| Ongoing Projects | 1 |
Promoter Partners
| Partner 1 | PARESH GHELANI |
| PAN | CFY******* |
| Address | A-44, SAIFEE SOCIETY, BESIDE TRIKAM NAGAR. L.H.ROAD, SURAT |
| Partner 2 | NITIN PARSHOTTAMBHAI THESIA |
| PAN | ACA******* |
| Address | A-44, SAIFEE SOCIETY, BESIDE TRIKAM NAGAR. L.H.ROAD, SURAT |
| Partner 3 | KAMAL PARSHOTTAMBHAI THESIA |
| PAN | ABB******* |
| Address | A-44, SAIFEE SOCIETY, BESIDE TRIKAM NAGAR. L.H.ROAD, SURAT |
Building Blocks
| A - Start Date | 2018-05-23 |
| A - End Date | 2023-12-01 |
| A - FSI | 0.0 |
| A - Built-up Area | 0.0 |
| A - Progress | 0.0% |
| A - Booked Units | 0 |
| A - Unbooked Units | 1 |
| B - Start Date | 2018-05-23 |
| B - End Date | 2023-12-01 |
| B - FSI | 0.0 |
| B - Built-up Area | 0.0 |
| B - Progress | 64.29% |
| B - Booked Units | 9 |
| B - Unbooked Units | 5 |
| B1 - Start Date | 2018-05-23 |
| B1 - End Date | 2023-12-01 |
| B1 - FSI | 0.0 |
| B1 - Built-up Area | 0.0 |
| B1 - Progress | 100.0% |
| B1 - Booked Units | 1 |
| B1 - Unbooked Units | 0 |
| B2 - Start Date | 2018-05-23 |
| B2 - End Date | 2023-12-01 |
| B2 - FSI | 0.0 |
| B2 - Built-up Area | 0.0 |
| B2 - Progress | 100.0% |
| B2 - Booked Units | 1 |
| B2 - Unbooked Units | 0 |
| B3 - Start Date | 2018-05-23 |
| B3 - End Date | 2023-12-01 |
| B3 - FSI | 0.0 |
| B3 - Built-up Area | 0.0 |
| B3 - Progress | 100.0% |
| B3 - Booked Units | 1 |
| B3 - Unbooked Units | 0 |
| C - Start Date | 2018-05-23 |
| C - End Date | 2023-12-01 |
| C - FSI | 0.0 |
| C - Built-up Area | 0.0 |
| C - Progress | 100.0% |
| C - Booked Units | 1 |
| C - Unbooked Units | 0 |
| C1 - Start Date | 2018-05-23 |
| C1 - End Date | 2023-12-01 |
| C1 - FSI | 0.0 |
| C1 - Built-up Area | 0.0 |
| C1 - Progress | 100.0% |
| C1 - Booked Units | 1 |
| C1 - Unbooked Units | 0 |
| D - Start Date | 2018-05-23 |
| D - End Date | 2023-12-01 |
| D - FSI | 0.0 |
| D - Built-up Area | 0.0 |
| D - Progress | 100.0% |
| D - Booked Units | 1 |
| D - Unbooked Units | 0 |
| D1 - Start Date | 2018-05-23 |
| D1 - End Date | 2023-12-01 |
| D1 - FSI | 0.0 |
| D1 - Built-up Area | 0.0 |
| D1 - Progress | 100.0% |
| D1 - Booked Units | 1 |
| D1 - Unbooked Units | 0 |
| D2 - Start Date | 2018-05-23 |
| D2 - End Date | 2023-12-01 |
| D2 - FSI | 0.0 |
| D2 - Built-up Area | 0.0 |
| D2 - Progress | 100.0% |
| D2 - Booked Units | 1 |
| D2 - Unbooked Units | 0 |
| E - Start Date | 2018-05-23 |
| E - End Date | 2023-12-01 |
| E - FSI | 0.0 |
| E - Built-up Area | 0.0 |
| E - Progress | 0.0% |
| E - Booked Units | 0 |
| E - Unbooked Units | 1 |
| E1 - Start Date | 2018-05-23 |
| E1 - End Date | 2023-12-01 |
| E1 - FSI | 0.0 |
| E1 - Built-up Area | 0.0 |
| E1 - Progress | 100.0% |
| E1 - Booked Units | 1 |
| E1 - Unbooked Units | 0 |
| E2 - Start Date | 2018-05-23 |
| E2 - End Date | 2023-12-01 |
| E2 - FSI | 0.0 |
| E2 - Built-up Area | 0.0 |
| E2 - Progress | 100.0% |
| E2 - Booked Units | 1 |
| E2 - Unbooked Units | 0 |
| E3 - Start Date | 2018-05-23 |
| E3 - End Date | 2023-12-01 |
| E3 - FSI | 0.0 |
| E3 - Built-up Area | 0.0 |
| E3 - Progress | 100.0% |
| E3 - Booked Units | 1 |
| E3 - Unbooked Units | 0 |
| E4 - Start Date | 2018-05-23 |
| E4 - End Date | 2023-12-01 |
| E4 - FSI | 0.0 |
| E4 - Built-up Area | 0.0 |
| E4 - Progress | 100.0% |
| E4 - Booked Units | 1 |
| E4 - Unbooked Units | 0 |
| F - Start Date | 2018-05-23 |
| F - End Date | 2023-12-01 |
| F - FSI | 0.0 |
| F - Built-up Area | 0.0 |
| F - Progress | 100.0% |
| F - Booked Units | 1 |
| F - Unbooked Units | 0 |
| G - Start Date | 2018-05-23 |
| G - End Date | 2023-12-01 |
| G - FSI | 0.0 |
| G - Built-up Area | 0.0 |
| G - Progress | 0.0% |
| G - Booked Units | 0 |
| G - Unbooked Units | 1 |
| H - Start Date | 2018-05-23 |
| H - End Date | 2023-12-01 |
| H - FSI | 0.0 |
| H - Built-up Area | 0.0 |
| H - Progress | 96.15% |
| H - Booked Units | 25 |
| H - Unbooked Units | 1 |
| I - Start Date | 2018-05-23 |
| I - End Date | 2023-12-01 |
| I - FSI | 0.0 |
| I - Built-up Area | 0.0 |
| I - Progress | 100.0% |
| I - Booked Units | 1 |
| I - Unbooked Units | 0 |
| J - Start Date | 2018-05-23 |
| J - End Date | 2023-12-01 |
| J - FSI | 0.0 |
| J - Built-up Area | 0.0 |
| J - Progress | 0.0% |
| J - Booked Units | 0 |
| J - Unbooked Units | 1 |
| K - Start Date | 2018-05-23 |
| K - End Date | 2023-12-01 |
| K - FSI | 0.0 |
| K - Built-up Area | 0.0 |
| K - Progress | 92.0% |
| K - Booked Units | 23 |
| K - Unbooked Units | 2 |
| L - Start Date | 2018-05-23 |
| L - End Date | 2023-12-01 |
| L - FSI | 0.0 |
| L - Built-up Area | 0.0 |
| L - Progress | 0.0% |
| L - Booked Units | 0 |
| L - Unbooked Units | 1 |
| M - Start Date | 2018-05-23 |
| M - End Date | 2023-12-01 |
| M - FSI | 0.0 |
| M - Built-up Area | 0.0 |
| M - Progress | 0.0% |
| M - Booked Units | 0 |
| M - Unbooked Units | 1 |
| N - Start Date | 2018-05-23 |
| N - End Date | 2023-12-01 |
| N - FSI | 0.0 |
| N - Built-up Area | 0.0 |
| N - Progress | 65.0% |
| N - Booked Units | 13 |
| N - Unbooked Units | 7 |
| O - Start Date | 2018-05-23 |
| O - End Date | 2023-12-01 |
| O - FSI | 0.0 |
| O - Built-up Area | 0.0 |
| O - Progress | 100.0% |
| O - Booked Units | 1 |
| O - Unbooked Units | 0 |
| P - Start Date | 2018-05-23 |
| P - End Date | 2023-12-01 |
| P - FSI | 0.0 |
| P - Built-up Area | 0.0 |
| P - Progress | 100.0% |
| P - Booked Units | 1 |
| P - Unbooked Units | 0 |
| Q - Start Date | 2018-05-23 |
| Q - End Date | 2023-12-01 |
| Q - FSI | 0.0 |
| Q - Built-up Area | 0.0 |
| Q - Progress | 87.5% |
| Q - Booked Units | 7 |
| Q - Unbooked Units | 1 |
| R - Start Date | 2018-05-23 |
| R - End Date | 2023-12-01 |
| R - FSI | 0.0 |
| R - Built-up Area | 0.0 |
| R - Progress | 0.0% |
| R - Booked Units | 0 |
| R - Unbooked Units | 1 |
| S - Start Date | 2018-05-23 |
| S - End Date | 2023-12-01 |
| S - FSI | 0.0 |
| S - Built-up Area | 0.0 |
| S - Progress | 0.0% |
| S - Booked Units | 0 |
| S - Unbooked Units | 1 |
| T - Start Date | 2018-05-23 |
| T - End Date | 2023-12-01 |
| T - FSI | 0.0 |
| T - Built-up Area | 0.0 |
| T - Progress | 0.0% |
| T - Booked Units | 0 |
| T - Unbooked Units | 1 |
| T1 - Start Date | 2018-05-23 |
| T1 - End Date | 2023-12-01 |
| T1 - FSI | 0.0 |
| T1 - Built-up Area | 0.0 |
| T1 - Progress | 100.0% |
| T1 - Booked Units | 1 |
| T1 - Unbooked Units | 0 |
| T2 - Start Date | 2018-05-23 |
| T2 - End Date | 2023-12-01 |
| T2 - FSI | 0.0 |
| T2 - Built-up Area | 0.0 |
| T2 - Progress | 100.0% |
| T2 - Booked Units | 1 |
| T2 - Unbooked Units | 0 |
| T3 - Start Date | 2018-05-23 |
| T3 - End Date | 2023-12-01 |
| T3 - FSI | 0.0 |
| T3 - Built-up Area | 0.0 |
| T3 - Progress | 100.0% |
| T3 - Booked Units | 1 |
| T3 - Unbooked Units | 0 |
| U - Start Date | 2018-05-23 |
| U - End Date | 2023-12-01 |
| U - FSI | 0.0 |
| U - Built-up Area | 0.0 |
| U - Progress | 100.0% |
| U - Booked Units | 1 |
| U - Unbooked Units | 0 |
| U1 - Start Date | 2018-05-23 |
| U1 - End Date | 2023-12-01 |
| U1 - FSI | 0.0 |
| U1 - Built-up Area | 0.0 |
| U1 - Progress | 100.0% |
| U1 - Booked Units | 1 |
| U1 - Unbooked Units | 0 |
| U2 - Start Date | 2018-05-23 |
| U2 - End Date | 2023-12-01 |
| U2 - FSI | 0.0 |
| U2 - Built-up Area | 0.0 |
| U2 - Progress | 100.0% |
| U2 - Booked Units | 1 |
| U2 - Unbooked Units | 0 |
| U3 - Start Date | 2018-05-23 |
| U3 - End Date | 2023-12-01 |
| U3 - FSI | 0.0 |
| U3 - Built-up Area | 0.0 |
| U3 - Progress | 100.0% |
| U3 - Booked Units | 1 |
| U3 - Unbooked Units | 0 |
| V - Start Date | 2018-05-23 |
| V - End Date | 2023-12-01 |
| V - FSI | 0.0 |
| V - Built-up Area | 0.0 |
| V - Progress | 100.0% |
| V - Booked Units | 1 |
| V - Unbooked Units | 0 |
| W - Start Date | 2018-05-23 |
| W - End Date | 2023-12-01 |
| W - FSI | 0.0 |
| W - Built-up Area | 0.0 |
| W - Progress | 100.0% |
| W - Booked Units | 1 |
| W - Unbooked Units | 0 |
| X - Start Date | 2018-05-23 |
| X - End Date | 2023-12-01 |
| X - FSI | 0.0 |
| X - Built-up Area | 0.0 |
| X - Progress | 100.0% |
| X - Booked Units | 1 |
| X - Unbooked Units | 0 |
| Y - Start Date | 2018-05-23 |
| Y - End Date | 2023-12-01 |
| Y - FSI | 0.0 |
| Y - Built-up Area | 0.0 |
| Y - Progress | 100.0% |
| Y - Booked Units | 1 |
| Y - Unbooked Units | 0 |
| Z - Start Date | 2018-05-23 |
| Z - End Date | 2023-12-01 |
| Z - FSI | 0.0 |
| Z - Built-up Area | 0.0 |
| Z - Progress | 100.0% |
| Z - Booked Units | 1 |
| Z - Unbooked Units | 0 |
| Z1 - Start Date | 2018-05-23 |
| Z1 - End Date | 2023-12-01 |
| Z1 - FSI | 0.0 |
| Z1 - Built-up Area | 0.0 |
| Z1 - Progress | 100.0% |
| Z1 - Booked Units | 1 |
| Z1 - Unbooked Units | 0 |
| Z2 - Start Date | 2018-05-23 |
| Z2 - End Date | 2023-12-01 |
| Z2 - FSI | 0.0 |
| Z2 - Built-up Area | 0.0 |
| Z2 - Progress | 100.0% |
| Z2 - Booked Units | 1 |
| Z2 - Unbooked Units | 0 |
| Z3 - Start Date | 2018-05-23 |
| Z3 - End Date | 2023-12-01 |
| Z3 - FSI | 0.0 |
| Z3 - Built-up Area | 0.0 |
| Z3 - Progress | 100.0% |
| Z3 - Booked Units | 1 |
| Z3 - Unbooked Units | 0 |
| Z4 - Start Date | 2018-05-23 |
| Z4 - End Date | 2023-12-01 |
| Z4 - FSI | 0.0 |
| Z4 - Built-up Area | 0.0 |
| Z4 - Progress | 100.0% |
| Z4 - Booked Units | 1 |
| Z4 - Unbooked Units | 0 |
Inventory Units
| OPEN PLOT - Total Units | 134 |
| OPEN PLOT - Carpet Area | 18099.69 |
| OPEN PLOT - Exclusive Area | 0.0 |
| OPEN PLOT - Open Terrace Area | 0.0 |
Quarterly Progress
| April 2019 | 8.59% |
| July 2019 | 8.59% |
| October 2019 | 8.59% |
| January 2020 | 6.91% |
| April 2020 | 6.91% |
| October 2020 | 8.59% |
| January 2021 | 6.91% |
| April 2021 | 9.14% |
| July 2021 | 11.11% |
| January 2024 | 11.11% |
The information provided on this page is collated from publicly available resources. PropTech Pulse does not guarantee the accuracy, completeness, or authority of this data and shall not be held liable for any discrepancies. For queries or further assistance, please contact us at pulse@aurumproptech.in