SHUBHAM AVENUE
VICEPAN BUILDCONE
BLOCK NO 647 FP 84 TP 25 SHUBHAM AVENUE, ABARAMA ROAD MOTA VARCHHA
Approved
27th Dec 2017
Completed
30th Jun 2022
Registration No.
PR/GJ/SURAT/SURAT CITY/SUDA/MAA01111/271217
Acknowledgement No.
PR/SURAT/SURAT CITY/SUDA/170919/002396
Project Type
Mixed Development
Approving Authority
Surat Municipal Corporation
District
Surat
Taluka
Surat City
State
Gujarat
Project Details
| Project Name | SHUBHAM AVENUE |
| RERA Number | PR/GJ/SURAT/SURAT CITY/SUDA/MAA01111/271217 |
| Acknowledgement Number | PR/SURAT/SURAT CITY/SUDA/170919/002396 |
| Project Description | Residential & Commercial |
| Project Type | Mixed Development |
| Project Status | Completed |
| District | Surat |
| Taluka | Surat City |
| Address | BLOCK NO 647 FP 84 TP 25 SHUBHAM AVENUE, ABARAMA ROAD MOTA VARCHHA |
| Pincode | 394101 |
| State | Gujarat |
| Approving Authority | Surat Municipal Corporation |
| Approved On | 2017-12-27 |
| Start Date | 2016-09-30 |
| End Date | 2022-06-30 |
| Submission Date | 2017-09-19 |
| Months Delayed | 0 |
Area & Cost Details
| Total Land Area | 11122.0 |
| Total Covered Area | 6286.0 |
| Total Open Area | 4836.0 |
| Open Parking Area | 3367 |
| Covered Parking Area | 0.0 |
| Covered Parking Count | 0 |
| Parking for Sale Count | 0 |
| Cost of Land | 75381436 |
| Estimated Project Cost | 386043737 |
| Total Project Cost | 502356600 |
Land Details
| Moje | Mota |
| TP No. | 35 |
| TP Name | Mota Varachha |
Promoter Details
| Promoter Name | VICEPAN BUILDCONE |
| Promoter Type | PARTNERSHIP FIRM |
| vic***************@gmail.com | |
| Mobile | 98******** |
| Company Registration No. | GUJSR200406 |
| PAN | AAN******* |
| Experience (Years) | 0 |
| Area Constructed (sqm) | 11122 |
| Projects Completed | 0 |
| Ongoing Projects | 0 |
Promoter Partners
| Partner 1 | SUTARIYA HARESHBHAI LABHUBHAI |
| Address | A.68 SHANTINIKETAN SOCIETY, MOTA VARACHHA |
Building Blocks
| A - Start Date | 2016-09-30 |
| A - End Date | 2022-06-30 |
| A - Progress | 88.89% |
| A - Booked Units | 16 |
| A - Unbooked Units | 2 |
| B - Start Date | 2016-09-30 |
| B - End Date | 2022-06-30 |
| B - Progress | 90.0% |
| B - Booked Units | 18 |
| B - Unbooked Units | 2 |
| C - Start Date | 2016-09-30 |
| C - End Date | 2022-06-30 |
| C - Progress | 95.0% |
| C - Booked Units | 19 |
| C - Unbooked Units | 1 |
| D - Start Date | 2016-09-30 |
| D - End Date | 2022-06-30 |
| D - Progress | 89.47% |
| D - Booked Units | 17 |
| D - Unbooked Units | 2 |
| E - Start Date | 2016-09-30 |
| E - End Date | 2022-06-30 |
| E - Progress | 95.24% |
| E - Booked Units | 20 |
| E - Unbooked Units | 1 |
| F - Start Date | 2016-09-30 |
| F - End Date | 2022-06-30 |
| F - Progress | 95.0% |
| F - Booked Units | 19 |
| F - Unbooked Units | 1 |
| G - Start Date | 2016-09-30 |
| G - End Date | 2022-06-30 |
| G - Progress | 75.0% |
| G - Booked Units | 15 |
| G - Unbooked Units | 5 |
| H - Start Date | 2016-09-30 |
| H - End Date | 2022-06-30 |
| H - Progress | 60.0% |
| H - Booked Units | 12 |
| H - Unbooked Units | 8 |
| I - Start Date | 2016-09-30 |
| I - End Date | 2022-06-30 |
| I - Progress | 66.67% |
| I - Booked Units | 12 |
| I - Unbooked Units | 6 |
| J - Start Date | 2016-09-30 |
| J - End Date | 2022-06-30 |
| J - Progress | 94.44% |
| J - Booked Units | 17 |
| J - Unbooked Units | 1 |
| K - Start Date | 2016-09-30 |
| K - End Date | 2022-06-30 |
| K - Progress | 57.89% |
| K - Booked Units | 11 |
| K - Unbooked Units | 8 |
| L - Start Date | 2016-09-30 |
| L - End Date | 2022-06-30 |
| L - Progress | 57.14% |
| L - Booked Units | 12 |
| L - Unbooked Units | 9 |
| M - Start Date | 2016-09-30 |
| M - End Date | 2022-06-30 |
| M - Progress | 90.0% |
| M - Booked Units | 18 |
| M - Unbooked Units | 2 |
| N - Start Date | 2016-09-30 |
| N - End Date | 2022-06-30 |
| N - Progress | 60.0% |
| N - Booked Units | 12 |
| N - Unbooked Units | 8 |
| O - Start Date | 2016-09-30 |
| O - End Date | 2022-06-30 |
| O - Progress | 55.56% |
| O - Booked Units | 10 |
| O - Unbooked Units | 8 |
| P - Start Date | 2016-09-30 |
| P - End Date | 2022-06-30 |
| P - Progress | 72.22% |
| P - Booked Units | 13 |
| P - Unbooked Units | 5 |
| Q - Start Date | 2016-09-30 |
| Q - End Date | 2022-06-30 |
| Q - Progress | 50.0% |
| Q - Booked Units | 9 |
| Q - Unbooked Units | 9 |
| R - Start Date | 2016-09-30 |
| R - End Date | 2022-06-30 |
| R - Progress | 89.71% |
| R - Booked Units | 61 |
| R - Unbooked Units | 7 |
Inventory Units
| FLAT - Total Units | 345 |
| FLAT - Carpet Area | 18573.0 |
| FLAT - Exclusive Area | 1133.0 |
| FLAT - Open Terrace Area | 0.0 |
| SHOP - Total Units | 51 |
| SHOP - Carpet Area | 955.0 |
| SHOP - Exclusive Area | 0.0 |
| SHOP - Open Terrace Area | 0.0 |
Quarterly Progress
| May 2018 | 38.18% |
| August 2018 | 48.95% |
| November 2018 | 69.47% |
| February 2019 | 79.03% |
| May 2019 | 88.47% |
| August 2019 | 96.99% |
| November 2019 | 100.0% |
| February 2020 | 100.0% |
| August 2020 | 100.0% |
| July 2022 | 100.0% |
Professionals
| Architect | JAGDISH H GELANI |
| Licence No. | TDOER848 |
| Engineer | HEMANT SHUKLA |
| Licence No. | SUDALSTR5 |
| Contractor | SAHIL A KATHIRIYA |
The information provided on this page is collated from publicly available resources. PropTech Pulse does not guarantee the accuracy, completeness, or authority of this data and shall not be held liable for any discrepancies. For queries or further assistance, please contact us at pulse@aurumproptech.in