VICEPAN BUILDCONE
BLOCK NO 647 FP 84 TP 25 SHUBHAM AVENUE, ABARAMA ROAD MOTA VARCHHA
Approved
27th Dec 2017
Completed
30th Jun 2022
Registration No.
PR/GJ/SURAT/SURAT CITY/SUDA/MAA01111/271217
Acknowledgement No.
PR/SURAT/SURAT CITY/SUDA/170919/002396
Project Type
Mixed Development
Approving Authority
Surat Municipal Corporation
District
Surat
Taluka
Surat City
State
Gujarat
| Project Name | SHUBHAM AVENUE |
| RERA Number | PR/GJ/SURAT/SURAT CITY/SUDA/MAA01111/271217 |
| Acknowledgement Number | PR/SURAT/SURAT CITY/SUDA/170919/002396 |
| Project Description | Residential & Commercial |
| Project Type | Mixed Development |
| Project Status | APPROVED |
| District | Surat |
| Taluka | Surat City |
| Address | BLOCK NO 647 FP 84 TP 25 SHUBHAM AVENUE, ABARAMA ROAD MOTA VARCHHA |
| Pincode | 394101 |
| State | Gujarat |
| Approving Authority | Surat Municipal Corporation |
| Approved On | 2017-12-27 |
| Start Date | 2016-09-30 |
| End Date | 2022-06-30 |
| Submission Date | 2017-09-19 |
| Months Delayed | 0 |
| Total Land Area | 11122.0 |
| Total Covered Area | 6286.0 |
| Total Open Area | 4836.0 |
| Open Parking Area | 3367 |
| Covered Parking Area | 0.0 |
| Covered Parking Count | 0 |
| Parking for Sale Count | 0 |
| Cost of Land | 75381436 |
| Estimated Project Cost | 386043737 |
| Total Project Cost | 502356600 |
| Moje | Mota |
| TP No. | 35 |
| TP Name | Mota Varachha |
| Promoter Name | VICEPAN BUILDCONE |
| Promoter Type | PARTNERSHIP FIRM |
| vicepanbuildcon647@gmail.com | |
| Mobile | 9825348144 |
| Company Registration No. | GUJSR200406 |
| PAN | AANFV0469K |
| Experience (Years) | 0 |
| Area Constructed (sqm) | 11122 |
| Projects Completed | 0 |
| Ongoing Projects | 0 |
| Partner 1 | SUTARIYA HARESHBHAI LABHUBHAI |
| Address | A.68 SHANTINIKETAN SOCIETY, MOTA VARACHHA |
| A - Start Date | 2016-09-30 |
| A - End Date | 2022-06-30 |
| A - Progress | 88.89% |
| A - Booked Units | 16 |
| A - Unbooked Units | 2 |
| B - Start Date | 2016-09-30 |
| B - End Date | 2022-06-30 |
| B - Progress | 90.0% |
| B - Booked Units | 18 |
| B - Unbooked Units | 2 |
| C - Start Date | 2016-09-30 |
| C - End Date | 2022-06-30 |
| C - Progress | 95.0% |
| C - Booked Units | 19 |
| C - Unbooked Units | 1 |
| D - Start Date | 2016-09-30 |
| D - End Date | 2022-06-30 |
| D - Progress | 89.47% |
| D - Booked Units | 17 |
| D - Unbooked Units | 2 |
| E - Start Date | 2016-09-30 |
| E - End Date | 2022-06-30 |
| E - Progress | 95.24% |
| E - Booked Units | 20 |
| E - Unbooked Units | 1 |
| F - Start Date | 2016-09-30 |
| F - End Date | 2022-06-30 |
| F - Progress | 95.0% |
| F - Booked Units | 19 |
| F - Unbooked Units | 1 |
| G - Start Date | 2016-09-30 |
| G - End Date | 2022-06-30 |
| G - Progress | 75.0% |
| G - Booked Units | 15 |
| G - Unbooked Units | 5 |
| H - Start Date | 2016-09-30 |
| H - End Date | 2022-06-30 |
| H - Progress | 60.0% |
| H - Booked Units | 12 |
| H - Unbooked Units | 8 |
| I - Start Date | 2016-09-30 |
| I - End Date | 2022-06-30 |
| I - Progress | 66.67% |
| I - Booked Units | 12 |
| I - Unbooked Units | 6 |
| J - Start Date | 2016-09-30 |
| J - End Date | 2022-06-30 |
| J - Progress | 94.44% |
| J - Booked Units | 17 |
| J - Unbooked Units | 1 |
| K - Start Date | 2016-09-30 |
| K - End Date | 2022-06-30 |
| K - Progress | 57.89% |
| K - Booked Units | 11 |
| K - Unbooked Units | 8 |
| L - Start Date | 2016-09-30 |
| L - End Date | 2022-06-30 |
| L - Progress | 57.14% |
| L - Booked Units | 12 |
| L - Unbooked Units | 9 |
| M - Start Date | 2016-09-30 |
| M - End Date | 2022-06-30 |
| M - Progress | 90.0% |
| M - Booked Units | 18 |
| M - Unbooked Units | 2 |
| N - Start Date | 2016-09-30 |
| N - End Date | 2022-06-30 |
| N - Progress | 60.0% |
| N - Booked Units | 12 |
| N - Unbooked Units | 8 |
| O - Start Date | 2016-09-30 |
| O - End Date | 2022-06-30 |
| O - Progress | 55.56% |
| O - Booked Units | 10 |
| O - Unbooked Units | 8 |
| P - Start Date | 2016-09-30 |
| P - End Date | 2022-06-30 |
| P - Progress | 72.22% |
| P - Booked Units | 13 |
| P - Unbooked Units | 5 |
| Q - Start Date | 2016-09-30 |
| Q - End Date | 2022-06-30 |
| Q - Progress | 50.0% |
| Q - Booked Units | 9 |
| Q - Unbooked Units | 9 |
| R - Start Date | 2016-09-30 |
| R - End Date | 2022-06-30 |
| R - Progress | 89.71% |
| R - Booked Units | 61 |
| R - Unbooked Units | 7 |
| FLAT - Total Units | 345 |
| FLAT - Carpet Area | 18573.0 |
| FLAT - Exclusive Area | 1133.0 |
| FLAT - Open Terrace Area | 0.0 |
| SHOP - Total Units | 51 |
| SHOP - Carpet Area | 955.0 |
| SHOP - Exclusive Area | 0.0 |
| SHOP - Open Terrace Area | 0.0 |
| May 2018 | 38.18% |
| August 2018 | 48.95% |
| November 2018 | 69.47% |
| February 2019 | 79.03% |
| May 2019 | 88.47% |
| August 2019 | 96.99% |
| November 2019 | 100.0% |
| February 2020 | 100.0% |
| August 2020 | 100.0% |
| July 2022 | 100.0% |
| Architect | JAGDISH H GELANI |
| Licence No. | TDOER848 |
| Engineer | HEMANT SHUKLA |
| Licence No. | SUDALSTR5 |
| Contractor | SAHIL A KATHIRIYA |