SHUBHAM DEVELOPERS
TPS NO. 61 (PARVAT-GODADRA),FP NO. 56/PAIKEY SUBPLOT NO. 2, OP NO. 56, BLOCK NO. 9,MOJE-GODADRA, TAL-CITY,DIST-SURAT
Approved
20th Apr 2018
Completed
31st Mar 2021
Registration No.
PR/GJ/SURAT/SURAT CITY/SUDA/MAA02432/EX1/121120
Acknowledgement No.
PR/SURAT/SURAT CITY/SUDA/180329/005004
Project Type
Mixed Development
Approving Authority
Surat Municipal Corporation
District
Surat
Taluka
Surat City
State
Gujarat
| Project Name | SHUBHAM RESIDENCY |
| RERA Number | PR/GJ/SURAT/SURAT CITY/SUDA/MAA02432/EX1/121120 |
| Acknowledgement Number | PR/SURAT/SURAT CITY/SUDA/180329/005004 |
| Project Description | LOW RISE BUILDING |
| Project Type | Mixed Development |
| Project Status | APPROVED |
| District | Surat |
| Taluka | Surat City |
| Address | TPS NO. 61 (PARVAT-GODADRA),FP NO. 56/PAIKEY SUBPLOT NO. 2, OP NO. 56, BLOCK NO. 9,MOJE-GODADRA, TAL-CITY,DIST-SURAT |
| Pincode | 395012 |
| State | Gujarat |
| Approving Authority | Surat Municipal Corporation |
| Approved On | 2018-04-20 |
| Start Date | 2014-04-28 |
| End Date | 2021-03-31 |
| Submission Date | 2018-03-29 |
| Months Delayed | 0 |
| Total Land Area | 3543.04 |
| Total Land Area (Registered) | 3543.04 |
| Total Covered Area | 1381.67 |
| Total Open Area | 2161.37 |
| Total Carpet Area | 5444.33 |
| Open Parking Area | 0 |
| Covered Parking Area | 1187.17 |
| Covered Parking Count | 0 |
| Parking for Sale Count | 0 |
| Cost of Land | 25337520 |
| Estimated Project Cost | 63500000 |
| Total Project Cost | 88837520 |
| Moje | Godadara |
| TP No. | 61 |
| TP Name | ( Parvat - Godadara ) |
| Promoter Name | SHUBHAM DEVELOPERS |
| Promoter Type | PARTNERSHIP FIRM |
| shubhamresidency02@yahoo.com | |
| Mobile | 9825417608 |
| Company Registration No. | 0 |
| PAN | ACSFS9213R |
| Experience (Years) | 0 |
| Area Constructed (sqm) | 1381 |
| Projects Completed | 0 |
| Ongoing Projects | 1 |
| Partner 1 | VALLABHBHAI ARJANBHAI HADIYA AND JAYSUKHBHAI VALLABHBHAI BALDANIYA |
| Address | 249,KAMAL PARK SOCIETY, L.H. ROAD. SURAT |
| A BUILDING - Start Date | 2014-04-28 |
| A BUILDING - End Date | 2021-03-31 |
| A BUILDING - Progress | 81.48% |
| A BUILDING - Booked Units | 22 |
| A BUILDING - Unbooked Units | 5 |
| B BUILDING - Start Date | 2014-04-28 |
| B BUILDING - End Date | 2021-03-31 |
| B BUILDING - Progress | 96.3% |
| B BUILDING - Booked Units | 26 |
| B BUILDING - Unbooked Units | 1 |
| C BUILDING - Start Date | 2014-04-28 |
| C BUILDING - End Date | 2021-03-31 |
| C BUILDING - Progress | 100.0% |
| C BUILDING - Booked Units | 27 |
| C BUILDING - Unbooked Units | 0 |
| D BUILDING - Start Date | 2014-04-28 |
| D BUILDING - End Date | 2021-03-31 |
| D BUILDING - Progress | 90.0% |
| D BUILDING - Booked Units | 18 |
| D BUILDING - Unbooked Units | 2 |
| E BUILDING - Start Date | 2014-04-28 |
| E BUILDING - End Date | 2021-03-31 |
| E BUILDING - Progress | 100.0% |
| E BUILDING - Booked Units | 20 |
| E BUILDING - Unbooked Units | 0 |
| FLAT AND SHOP - Total Units | 121 |
| FLAT AND SHOP - Carpet Area | 5445.0 |
| FLAT AND SHOP - Exclusive Area | 340.2 |
| FLAT AND SHOP - Open Terrace Area | 0.0 |
| September 2018 | 89.31% |
| December 2018 | 98.34% |
| March 2019 | 98.76% |
| June 2019 | 100.0% |
| September 2019 | 100.0% |
| December 2019 | 100.0% |
| March 2020 | 100.0% |
| September 2020 | 100.0% |
| March 2021 | 100.0% |
| April 2021 | 100.0% |