SURAT MUNICIPAL CORPORATION
Final Plot no. 113 AT T.P. 16 (PAL), VILLAGE- PAL,TA-ADAJAN,DIST-SURAT
Approved
10th Nov 2020
Completed
16th Oct 2024
Registration No.
PR/GJ/SURAT/SURAT CITY/SUDA/MAA07667/101120
Acknowledgement No.
PR/SURAT/SURAT CITY/SUDA/201027/009804
Project Type
Mixed Development
Approving Authority
Surat Municipal Corporation
District
Surat
Taluka
Surat City
State
Gujarat
| Project Name | SUMAN MUDRA EWS-48 TPS NO 16 (PAL) FP NO 113 |
| RERA Number | PR/GJ/SURAT/SURAT CITY/SUDA/MAA07667/101120 |
| Acknowledgement Number | PR/SURAT/SURAT CITY/SUDA/201027/009804 |
| Project Description | 1231 Residential Unit and 18 Shop |
| Project Type | Mixed Development |
| Project Status | APPROVED |
| District | Surat |
| Taluka | Surat City |
| Address | Final Plot no. 113 AT T.P. 16 (PAL), VILLAGE- PAL,TA-ADAJAN,DIST-SURAT |
| State | Gujarat |
| Approving Authority | Surat Municipal Corporation |
| Approved On | 2020-11-10 |
| Start Date | 2019-12-09 |
| End Date | 2024-10-16 |
| Submission Date | 2020-10-17 |
| Months Delayed | 0 |
| Total Land Area | 17885.0 |
| Total Land Area (Registered) | 17885.0 |
| Total Covered Area | 6555.0 |
| Total Open Area | 11330.0 |
| Total Carpet Area | 42575.61 |
| Open Parking Area | 564.15 |
| Covered Parking Area | 5618.2 |
| Covered Parking Count | 72 |
| Parking for Sale Count | 17 |
| Cost of Land | 339815000 |
| Estimated Project Cost | 906557640 |
| Total Project Cost | 1246372640 |
| Moje | Pal |
| TP No. | 16 |
| TP Name | PAL |
| Sub Plot No. | - |
| Promoter Name | SURAT MUNICIPAL CORPORATION |
| Promoter Type | COMPETENT AUTHORITY/ GOVERNMENT |
| smcsucews55@gmail.com | |
| Mobile | 9727142515 |
| Company Registration No. | NA |
| PAN | AAALS0678Q |
| Date of Incorporation | 1966-10-01 |
| Experience (Years) | 50 |
| Area Constructed (sqm) | 30000 |
| Projects Completed | 00 |
| Ongoing Projects | 14 |
| Partner 1 | JATINKUMAR MANUBHAI DESAI |
| PAN | ACBPD2112P |
| Address | Muglisara Main Road Opposite LIC Buildinng, Munghal sarai Surat Gujarat |
| A - Start Date | 2019-12-09 |
| A - End Date | 2024-10-16 |
| A - Progress | 89.29% |
| A - Booked Units | 75 |
| A - Unbooked Units | 9 |
| B - Start Date | 2019-12-09 |
| B - End Date | 2024-10-16 |
| B - Progress | 90.48% |
| B - Booked Units | 95 |
| B - Unbooked Units | 10 |
| C - Start Date | 2019-12-09 |
| C - End Date | 2024-10-16 |
| C - Progress | 99.17% |
| C - Booked Units | 119 |
| C - Unbooked Units | 1 |
| D - Start Date | 2019-12-09 |
| D - End Date | 2024-10-16 |
| D - Progress | 100.0% |
| D - Booked Units | 80 |
| D - Unbooked Units | 0 |
| E - Start Date | 2019-12-09 |
| E - End Date | 2024-10-16 |
| E - Progress | 98.0% |
| E - Booked Units | 98 |
| E - Unbooked Units | 2 |
| F - Start Date | 2019-12-09 |
| F - End Date | 2024-10-16 |
| F - Progress | 96.67% |
| F - Booked Units | 116 |
| F - Unbooked Units | 4 |
| G - Start Date | 2019-12-09 |
| G - End Date | 2024-10-16 |
| G - Progress | 100.0% |
| G - Booked Units | 120 |
| G - Unbooked Units | 0 |
| H - Start Date | 2019-12-09 |
| H - End Date | 2024-10-16 |
| H - Progress | 98.0% |
| H - Booked Units | 98 |
| H - Unbooked Units | 2 |
| I - Start Date | 2019-12-09 |
| I - End Date | 2024-10-16 |
| I - Progress | 97.5% |
| I - Booked Units | 78 |
| I - Unbooked Units | 2 |
| J - Start Date | 2019-12-09 |
| J - End Date | 2024-10-16 |
| J - Progress | 99.17% |
| J - Booked Units | 119 |
| J - Unbooked Units | 1 |
| K - Start Date | 2019-12-09 |
| K - End Date | 2024-10-16 |
| K - Progress | 98.0% |
| K - Booked Units | 98 |
| K - Unbooked Units | 2 |
| L - Start Date | 2019-12-09 |
| L - End Date | 2024-10-16 |
| L - Progress | 100.0% |
| L - Booked Units | 120 |
| L - Unbooked Units | 0 |
| Residential Unit - Total Units | 1231 |
| Residential Unit - Carpet Area | 42358.71 |
| Residential Unit - Exclusive Area | 2523.55 |
| Residential Unit - Open Terrace Area | 0.0 |
| Shop - Total Units | 18 |
| Shop - Carpet Area | 216.9 |
| Shop - Exclusive Area | 0.0 |
| Shop - Open Terrace Area | 0.0 |
| April 2021 | 14.34% |
| July 2021 | 31.01% |
| October 2021 | 38.02% |
| January 2022 | 41.77% |
| April 2022 | 46.59% |
| July 2022 | 55.5% |
| October 2022 | 65.26% |
| January 2023 | 69.47% |
| April 2023 | 73.16% |
| July 2023 | 100.0% |
| October 2023 | 100.0% |
| November 2024 | 100.0% |
| Architect | Himanshu ashok panchal |
| Licence No. | CA/2008/41868 |
| Engineer | Jayesh A Dalal |
| Licence No. | TDO/STDR/47 |
| Contractor | SHREE GANESH CORPORATION |