SWAPNA BUILDCON
SWAPNA VILLA PHASE-1, BLOCK NO. 343,BEHIND DADA BHAGWAN TEMPLE,, KAMREJ-VAV ROAD, KAMREJ,
Approved
6th Oct 2018
Completed
1st Dec 2023
Registration No.
PR/GJ/SURAT/KAMREJ/SUDA/RAA03616/061018
Acknowledgement No.
PR/SURAT/KAMREJ/SUDA/170929/002573
Project Type
Residential/Group Housing
Approving Authority
Town Planning and Valuation Department, Surat
District
Surat
Taluka
Kamrej
State
Gujarat
| Project Name | SWAPNA VILLA |
| RERA Number | PR/GJ/SURAT/KAMREJ/SUDA/RAA03616/061018 |
| Acknowledgement Number | PR/SURAT/KAMREJ/SUDA/170929/002573 |
| Project Description | 361 ROW HOUSES AND 3 COMMON PLOTS |
| Project Type | Residential/Group Housing |
| Project Status | APPROVED |
| District | Surat |
| Taluka | Kamrej |
| Address | SWAPNA VILLA PHASE-1, BLOCK NO. 343,BEHIND DADA BHAGWAN TEMPLE,, KAMREJ-VAV ROAD, KAMREJ, |
| Pincode | 394180 |
| State | Gujarat |
| Approving Authority | Town Planning and Valuation Department, Surat |
| Approved On | 2018-10-06 |
| Start Date | 2013-07-15 |
| End Date | 2023-12-01 |
| Submission Date | 2017-09-29 |
| Months Delayed | 0 |
| Total Land Area | 50658.0 |
| Total Covered Area | 45591.17 |
| Total Open Area | 5066.83 |
| Open Parking Area | 0 |
| Covered Parking Area | 0.0 |
| Covered Parking Count | 0 |
| Parking for Sale Count | 0 |
| Cost of Land | 111446180 |
| Estimated Project Cost | 390000000 |
| Total Project Cost | 501446180 |
| Moje | Kamrej |
| Plot No. | - |
| Promoter Name | SWAPNA BUILDCON |
| Promoter Type | PARTNERSHIP FIRM |
| swapnabuildcon@gmail.com | |
| Mobile | 8238570000 |
| Company Registration No. | GU/SRT/(17)36370 |
| PAN | ACHFS9871J |
| Date of Incorporation | 2013-04-04 |
| Experience (Years) | 6 |
| Area Constructed (sqm) | 2700 |
| Projects Completed | 0 |
| Ongoing Projects | 3 |
| Partner 1 | MANSUKH VITTHALBHAI DOBARIYA |
| PAN | ABQPD3459B |
| Address | 7, SARDAR PATEL PARK,, PARVAT PATIYA, |
| Partner 2 | SHANTILAL BACHUBHAI SOJITRA |
| PAN | AEPPP6311J |
| Address | 43,SUN STAR CITY SOC. SARTHANA JAKATNAKA |
| Partner 3 | DINESHBHAI HARIBHAI HIRPARA |
| PAN | ABJPP3390C |
| Address | 120, GOKULDHAM BUNGLOWS, MOTA VARACHHA |
| Partner 4 | PRAVINBHAI MOHANBHAI AKBARI |
| PAN | AAKPA8251D |
| Address | 301, KASHAM SOCIETY |
| Partner 5 | ranchhodbhai veljibhai korat |
| PAN | AJPPK5386D |
| Address | 72,shantivilla bunglows, kamrej char rasta |
| Partner 6 | bhanubhai kalyanbhai panchani |
| PAN | AAVPP7432J |
| Address | 28, sunstar city society, sarthana |
| Partner 7 | mayurbhai madhabhai bhadarka |
| PAN | ABVPA6925C |
| Address | A-602 SHEPHHIRE COURT, V I P ROAD |
| Partner 8 | ARVINDBHAI SHAMBHUBHAI VADADORIYA |
| PAN | ACLPV9157C |
| Address | 11, KAILASHDHAM SOCIETY, A K ROAD |
| Partner 9 | nitin labhubhai vaddoriya |
| PAN | ADRPV7760Q |
| Address | 30, SUNSTAR CITY SOCIETY, SARTHANA JAKAT NAKA, |
| A - Start Date | 2013-07-15 |
| A - End Date | 2023-12-01 |
| A - Progress | 81.44% |
| A - Booked Units | 79 |
| A - Unbooked Units | 18 |
| B - Start Date | 2013-07-15 |
| B - End Date | 2023-12-01 |
| B - Progress | 88.41% |
| B - Booked Units | 122 |
| B - Unbooked Units | 16 |
| C - Start Date | 2013-07-15 |
| C - End Date | 2023-12-01 |
| C - Progress | 62.5% |
| C - Booked Units | 5 |
| C - Unbooked Units | 3 |
| D - Start Date | 2013-07-15 |
| D - End Date | 2023-12-01 |
| D - Progress | 27.27% |
| D - Booked Units | 3 |
| D - Unbooked Units | 8 |
| E - Start Date | 2013-07-15 |
| E - End Date | 2023-12-01 |
| E - Progress | 36.36% |
| E - Booked Units | 8 |
| E - Unbooked Units | 14 |
| F - Start Date | 2013-07-15 |
| F - End Date | 2023-12-01 |
| F - Progress | 28.57% |
| F - Booked Units | 4 |
| F - Unbooked Units | 10 |
| G - Start Date | 2013-07-15 |
| G - End Date | 2023-12-01 |
| G - Progress | 66.67% |
| G - Booked Units | 2 |
| G - Unbooked Units | 1 |
| H - Start Date | 2013-07-15 |
| H - End Date | 2023-12-01 |
| H - Progress | 66.67% |
| H - Booked Units | 2 |
| H - Unbooked Units | 1 |
| I - Start Date | 2013-07-15 |
| I - End Date | 2023-12-01 |
| I - Progress | 57.14% |
| I - Booked Units | 4 |
| I - Unbooked Units | 3 |
| J - Start Date | 2013-07-15 |
| J - End Date | 2023-12-01 |
| J - Progress | 50.0% |
| J - Booked Units | 4 |
| J - Unbooked Units | 4 |
| K - Start Date | 2013-07-15 |
| K - End Date | 2023-12-01 |
| K - Progress | 100.0% |
| K - Booked Units | 4 |
| K - Unbooked Units | 0 |
| L - Start Date | 2013-07-15 |
| L - End Date | 2023-12-01 |
| L - Progress | 82.61% |
| L - Booked Units | 19 |
| L - Unbooked Units | 4 |
| M - Start Date | 2013-07-15 |
| M - End Date | 2023-12-01 |
| M - Progress | 63.16% |
| M - Booked Units | 12 |
| M - Unbooked Units | 7 |
| N - Start Date | 2013-07-15 |
| N - End Date | 2023-12-01 |
| N - Progress | 100.0% |
| N - Booked Units | 1 |
| N - Unbooked Units | 0 |
| O - Start Date | 2013-07-15 |
| O - End Date | 2023-12-01 |
| O - Progress | 66.67% |
| O - Booked Units | 2 |
| O - Unbooked Units | 1 |
| Residential - Total Units | 361 |
| Residential - Completed Units | 0 |
| Residential - Booked Units | 0 |
| Residential - Carpet Area | 25906.07 |
| Residential - Exclusive Area | 0.0 |
| Residential - Open Terrace Area | 0.0 |
| March 2019 | 100.0% |
| June 2019 | 100.0% |
| September 2019 | 100.0% |
| December 2019 | 100.0% |
| March 2020 | 100.0% |
| June 2020 | 100.0% |
| September 2020 | 100.0% |
| January 2024 | 100.0% |
| Architect | ARQUITECTOS |
| Licence No. | PII/CHNDL/2900004/0153747 |
| Engineer | Jignesh I Patel |
| Licence No. | SUDA-L-STR-190 |