440 LIG-II + 208 MIG-I + 208 MIG-II + 20 SHOPS AT PHASE-3, PACKAGE NO. 21, SAMTA , VADODARA
GUJARAT HOUSING BOARD
NEAR SAMTA POLICE STATION, SAMTA ROAD
Approved
5th Sept 2018
Completed
31st Mar 2019
Registration No.
PR/GJ/VADODARA/VADODARA/Others/MAA03375/050918
Acknowledgement No.
PR/VADODARA/VADODARA/VADODARA TPO/171030/003868
Project Type
Mixed Development
Approving Authority
Vadodara Municipal Corporation
District
Vadodara
Taluka
Vadodara
State
Gujarat
Project Details
| Project Name | 440 LIG-II + 208 MIG-I + 208 MIG-II + 20 SHOPS AT PHASE-3, PACKAGE NO. 21, SAMTA , VADODARA |
| RERA Number | PR/GJ/VADODARA/VADODARA/Others/MAA03375/050918 |
| Acknowledgement Number | PR/VADODARA/VADODARA/VADODARA TPO/171030/003868 |
| Project Description | 440 LIG-II + 208 MIG-I + 208 MIG-II + 20 SHOPS AT PHASE-3, PACKAGE NO. 21, SAMTA , VADODARA |
| Project Type | Mixed Development |
| Project Status | Completed |
| District | Vadodara |
| Taluka | Vadodara |
| Address | NEAR SAMTA POLICE STATION, SAMTA ROAD |
| Pincode | 390023 |
| State | Gujarat |
| Approving Authority | Vadodara Municipal Corporation |
| Approved On | 2018-09-05 |
| Start Date | 2015-05-18 |
| End Date | 2019-03-31 |
| Submission Date | 2017-10-30 |
| Months Delayed | 0 |
Area & Cost Details
| Total Land Area | 34859.0 |
| Total Covered Area | 20420.0 |
| Total Open Area | 0.0 |
| Open Parking Area | 8600 |
| Covered Parking Area | 0.0 |
| Covered Parking Count | 0 |
| Parking for Sale Count | 1 |
| Cost of Land | 2844494 |
| Estimated Project Cost | 1414800000 |
| Total Project Cost | 1417644494 |
Land Details
| Moje | Gorwa |
Promoter Details
| Promoter Name | GUJARAT HOUSING BOARD |
| Promoter Type | COMPETENT AUTHORITY/ GOVERNMENT |
| ghb*******@gmail.com | |
| Mobile | 90******** |
| Company Registration No. | NOTAPPLICABLE |
| PAN | AAA******* |
| Date of Incorporation | 1962-04-23 |
| Experience (Years) | 50 |
| Area Constructed (sqm) | 50000 |
| Projects Completed | 90 |
| Ongoing Projects | 25 |
Promoter Partners
| Partner 1 | AMITBHAI DAHYABHAI MANGAR |
| PAN | AKC******* |
| Address | GUJARAT HOUSING BOARD, Vadodara |
Building Blocks
| MIG 2 A - Start Date | 2015-05-18 |
| MIG 2 A - End Date | 2019-03-31 |
| MIG 2 A - Progress | 88.46% |
| MIG 2 A - Booked Units | 46 |
| MIG 2 A - Unbooked Units | 6 |
| MIG 2 B - Start Date | 2015-05-18 |
| MIG 2 B - End Date | 2019-03-31 |
| MIG 2 B - Progress | 88.46% |
| MIG 2 B - Booked Units | 46 |
| MIG 2 B - Unbooked Units | 6 |
| MIG 2 C - Start Date | 2015-05-18 |
| MIG 2 C - End Date | 2019-03-31 |
| MIG 2 C - Progress | 73.08% |
| MIG 2 C - Booked Units | 38 |
| MIG 2 C - Unbooked Units | 14 |
| MIG 2 D - Start Date | 2015-05-18 |
| MIG 2 D - End Date | 2019-03-31 |
| MIG 2 D - Progress | 78.85% |
| MIG 2 D - Booked Units | 41 |
| MIG 2 D - Unbooked Units | 11 |
| MIG 1 E - Start Date | 2015-05-18 |
| MIG 1 E - End Date | 2019-03-31 |
| MIG 1 E - Progress | 83.65% |
| MIG 1 E - Booked Units | 87 |
| MIG 1 E - Unbooked Units | 17 |
| MIG 1 F - Start Date | 2015-05-18 |
| MIG 1 F - End Date | 2019-03-31 |
| MIG 1 F - Progress | 87.5% |
| MIG 1 F - Booked Units | 91 |
| MIG 1 F - Unbooked Units | 13 |
| LIG 2 H - Start Date | 2015-05-18 |
| LIG 2 H - End Date | 2019-03-31 |
| LIG 2 H - Progress | 80.87% |
| LIG 2 H - Booked Units | 93 |
| LIG 2 H - Unbooked Units | 22 |
| LIG 2 I - Start Date | 2015-05-18 |
| LIG 2 I - End Date | 2019-03-31 |
| LIG 2 I - Progress | 80.87% |
| LIG 2 I - Booked Units | 93 |
| LIG 2 I - Unbooked Units | 22 |
| LIG 2 J - Start Date | 2015-05-18 |
| LIG 2 J - End Date | 2019-03-31 |
| LIG 2 J - Progress | 85.22% |
| LIG 2 J - Booked Units | 98 |
| LIG 2 J - Unbooked Units | 17 |
| LIG 2 K - Start Date | 2015-05-18 |
| LIG 2 K - End Date | 2019-03-31 |
| LIG 2 K - Progress | 84.35% |
| LIG 2 K - Booked Units | 97 |
| LIG 2 K - Unbooked Units | 18 |
Inventory Units
| LIG-II FLATS - Total Units | 440 |
| LIG-II FLATS - Carpet Area | 45.0 |
| LIG-II FLATS - Exclusive Area | 38.0 |
| LIG-II FLATS - Open Terrace Area | 0.0 |
| MIG-I FLATS - Total Units | 208 |
| MIG-I FLATS - Carpet Area | 65.0 |
| MIG-I FLATS - Exclusive Area | 55.0 |
| MIG-I FLATS - Open Terrace Area | 0.0 |
| MIG-II FLATS - Total Units | 208 |
| MIG-II FLATS - Carpet Area | 80.0 |
| MIG-II FLATS - Exclusive Area | 68.0 |
| MIG-II FLATS - Open Terrace Area | 0.0 |
Quarterly Progress
| February 2019 | 64.09% |
| April 2019 | 100.0% |
Professionals
| Architect | M.M.SHAH |
| Licence No. | ER/-200/13-16 |
| Engineer | M.M.SHAH |
| Licence No. | ER/-200/13-16 |
| Contractor | CUBE CONSTRUCTION ENGINEERING LTD. |
The information provided on this page is collated from publicly available resources. PropTech Pulse does not guarantee the accuracy, completeness, or authority of this data and shall not be held liable for any discrepancies. For queries or further assistance, please contact us at pulse@aurumproptech.in