GUJARAT HOUSING BOARD
Laxamipura road , Bh GEB sub station, opp. dasama temple , gorwa
Approved
10th May 2019
Completed
31st Oct 2023
Registration No.
PR/GJ/VADODARA/VADODARA/Others/MAA05414/EX1/200121
Acknowledgement No.
PR/VADODARA/VADODARA/VADODARA TPO/190408/006974
Project Type
Mixed Development
Approving Authority
Vadodara Municipal Corporation
District
Vadodara
Taluka
Vadodara
State
Gujarat
| Project Name | 49 shops + 1560 EWS - II at Gorwa, Phase 5 |
| RERA Number | PR/GJ/VADODARA/VADODARA/Others/MAA05414/EX1/200121 |
| Acknowledgement Number | PR/VADODARA/VADODARA/VADODARA TPO/190408/006974 |
| Project Description | 49 shops + 1560 EWS - II at Gorwa, Phase 5 at Vadodara |
| Project Type | Mixed Development |
| Project Status | APPROVED |
| District | Vadodara |
| Taluka | Vadodara |
| Address | Laxamipura road , Bh GEB sub station, opp. dasama temple , gorwa |
| Pincode | 390016 |
| State | Gujarat |
| Approving Authority | Vadodara Municipal Corporation |
| Approved On | 2019-05-10 |
| Start Date | 2019-01-17 |
| End Date | 2023-10-31 |
| Submission Date | 2019-03-27 |
| Months Delayed | 0 |
| Total Land Area | 32840.0 |
| Total Land Area (Registered) | 32840.0 |
| Total Covered Area | 30327.0 |
| Total Open Area | 4248.64 |
| Total Carpet Area | 57579.33 |
| Open Parking Area | 8676.13 |
| Covered Parking Area | 5801.01 |
| Covered Parking Count | 18 |
| Parking for Sale Count | 8 |
| Cost of Land | 369450000 |
| Estimated Project Cost | 1086757600 |
| Total Project Cost | 1014332583 |
| Moje | Gorva |
| Promoter Name | GUJARAT HOUSING BOARD |
| Promoter Type | COMPETENT AUTHORITY/ GOVERNMENT |
| ghb.phase6@gmail.com | |
| Mobile | 9099996558 |
| Company Registration No. | NOTAPPLICABLE |
| PAN | AAALG0206E |
| Date of Incorporation | 1962-04-23 |
| Experience (Years) | 50 |
| Area Constructed (sqm) | 50000 |
| Projects Completed | 90 |
| Ongoing Projects | 25 |
| Partner 1 | AMITBHAI DAHYABHAI MANGAR |
| PAN | AKCPM6887D |
| Address | GUJARAT HOUSING BOARD, Vadodara |
| EWS-2A - Start Date | 2019-01-17 |
| EWS-2A - End Date | 2023-10-31 |
| EWS-2A - Progress | 92.86% |
| EWS-2A - Booked Units | 104 |
| EWS-2A - Unbooked Units | 8 |
| EWS-2B - Start Date | 2019-01-17 |
| EWS-2B - End Date | 2023-10-31 |
| EWS-2B - Progress | 92.86% |
| EWS-2B - Booked Units | 104 |
| EWS-2B - Unbooked Units | 8 |
| EWS-2C - Start Date | 2019-01-17 |
| EWS-2C - End Date | 2023-10-31 |
| EWS-2C - Progress | 92.86% |
| EWS-2C - Booked Units | 104 |
| EWS-2C - Unbooked Units | 8 |
| EWS-2D - Start Date | 2019-01-17 |
| EWS-2D - End Date | 2023-10-31 |
| EWS-2D - Progress | 92.86% |
| EWS-2D - Booked Units | 104 |
| EWS-2D - Unbooked Units | 8 |
| EWS-2E - Start Date | 2019-01-17 |
| EWS-2E - End Date | 2023-10-31 |
| EWS-2E - Progress | 92.86% |
| EWS-2E - Booked Units | 104 |
| EWS-2E - Unbooked Units | 8 |
| EWS-2F - Start Date | 2019-01-17 |
| EWS-2F - End Date | 2023-10-31 |
| EWS-2F - Progress | 0.0% |
| EWS-2F - Booked Units | 0 |
| EWS-2F - Unbooked Units | 9 |
| EWS-2G - Start Date | 2019-01-17 |
| EWS-2G - End Date | 2023-10-31 |
| EWS-2G - Progress | 100.0% |
| EWS-2G - Booked Units | 104 |
| EWS-2G - Unbooked Units | 0 |
| EWS-2H - Start Date | 2019-01-17 |
| EWS-2H - End Date | 2023-10-31 |
| EWS-2H - Progress | 100.0% |
| EWS-2H - Booked Units | 104 |
| EWS-2H - Unbooked Units | 0 |
| EWS-2I - Start Date | 2019-01-17 |
| EWS-2I - End Date | 2023-10-31 |
| EWS-2I - Progress | 100.0% |
| EWS-2I - Booked Units | 104 |
| EWS-2I - Unbooked Units | 0 |
| EWS-2J - Start Date | 2019-01-17 |
| EWS-2J - End Date | 2023-10-31 |
| EWS-2J - Progress | 100.0% |
| EWS-2J - Booked Units | 104 |
| EWS-2J - Unbooked Units | 0 |
| EWS-2K - Start Date | 2019-01-17 |
| EWS-2K - End Date | 2023-10-31 |
| EWS-2K - Progress | 100.0% |
| EWS-2K - Booked Units | 104 |
| EWS-2K - Unbooked Units | 0 |
| EWS-2O - Start Date | 2019-01-17 |
| EWS-2O - End Date | 2023-10-31 |
| EWS-2O - Progress | 100.0% |
| EWS-2O - Booked Units | 104 |
| EWS-2O - Unbooked Units | 0 |
| EWS-2P - Start Date | 2019-01-17 |
| EWS-2P - End Date | 2023-10-31 |
| EWS-2P - Progress | 100.0% |
| EWS-2P - Booked Units | 104 |
| EWS-2P - Unbooked Units | 0 |
| EWS-2Q - Start Date | 2019-01-17 |
| EWS-2Q - End Date | 2023-10-31 |
| EWS-2Q - Progress | 100.0% |
| EWS-2Q - Booked Units | 104 |
| EWS-2Q - Unbooked Units | 0 |
| EWS-2R - Start Date | 2019-01-17 |
| EWS-2R - End Date | 2023-10-31 |
| EWS-2R - Progress | 100.0% |
| EWS-2R - Booked Units | 104 |
| EWS-2R - Unbooked Units | 0 |
| EWS-2S - Start Date | 2019-01-17 |
| EWS-2S - End Date | 2023-10-31 |
| EWS-2S - Progress | 100.0% |
| EWS-2S - Booked Units | 104 |
| EWS-2S - Unbooked Units | 0 |
| Shop - Total Units | 49 |
| Shop - Completed Units | 0 |
| Shop - Booked Units | 0 |
| Shop - Carpet Area | 935.73 |
| Shop - Exclusive Area | 0.0 |
| Shop - Open Terrace Area | 0.0 |
| Residential - Total Units | 1560 |
| Residential - Completed Units | 0 |
| Residential - Booked Units | 0 |
| Residential - Carpet Area | 56643.6 |
| Residential - Exclusive Area | 54147.6 |
| Residential - Open Terrace Area | 0.0 |
| October 2019 | 23.26% |
| January 2020 | 26.13% |
| April 2020 | 30.13% |
| October 2020 | 36.46% |
| January 2021 | 40.34% |
| April 2021 | 52.33% |
| July 2021 | 60.96% |
| October 2021 | 68.68% |
| January 2022 | 73.4% |
| April 2022 | 78.23% |
| July 2022 | 85.4% |
| October 2022 | 92.16% |
| January 2023 | 92.16% |
| April 2023 | 92.16% |
| July 2023 | 92.16% |
| October 2023 | 99.67% |
| November 2023 | 100.0% |
| Architect | ravi thakkar |
| Licence No. | CA/2013/62228 |
| Engineer | Madhusudan Patel |
| Licence No. | VMC License No:-SEOR-1/71 |
| Contractor | Cube Construction Engineering Ltd |