GAYATRI DEVELOPERS
OPP. SHYAMAL ENCLAVE, NR. SHREEM SHRUSHTI, 30 MT. SUN PHARMA ROAD
Approved
18th Sept 2018
Pending
30th Jun 2026
Registration No.
PR/GJ/VADODARA/VADODARA/Vadodara Municipal Corporation/MAA03439/A1M/190525/300626
Acknowledgement No.
PR/VADODARA/VADODARA/VADODARA TPO/180813/005932
Project Type
Mixed Development
Approving Authority
Vadodara Municipal Corporation
District
Vadodara
Taluka
Vadodara
State
Gujarat
| Project Name | AAMRAPALI RESI-COM |
| RERA Number | PR/GJ/VADODARA/VADODARA/Vadodara Municipal Corporation/MAA03439/A1M/190525/300626 |
| Acknowledgement Number | PR/VADODARA/VADODARA/VADODARA TPO/180813/005932 |
| Project Description | TOWER 1 WING A B C D TOWER 2 WING E F TOWER 3 WING G TOWER 4 WING H TOWER 5 WING I J TOWER 6 WING K L 51 TRIPLEX |
| Project Type | Mixed Development |
| Project Status | APPROVED |
| District | Vadodara |
| Taluka | Vadodara |
| Address | OPP. SHYAMAL ENCLAVE, NR. SHREEM SHRUSHTI, 30 MT. SUN PHARMA ROAD |
| Pincode | 390012 |
| State | Gujarat |
| Approving Authority | Vadodara Municipal Corporation |
| Approved On | 2018-09-18 |
| Start Date | 2018-07-15 |
| End Date | 2026-06-30 |
| Submission Date | 2018-08-13 |
| Months Delayed | 0 |
| Total Land Area (Registered) | 20849.0 |
| Total Covered Area | 7693.13 |
| Total Open Area | 13155.87 |
| Total Carpet Area | 31435.73 |
| Open Parking Area | 1712.82 |
| Covered Parking Area | 7050.33 |
| Covered Parking Count | 321 |
| Parking for Sale Count | 69 |
| Moje | Atladara |
| Revenue Survey No. | 186 to 189 , 191 to 193 |
| TP No. | 25 |
| TP Name | Atladara |
| Final Plot No. | 138 , 139 , 140 |
| Promoter Name | GAYATRI DEVELOPERS |
| Promoter Type | PARTNERSHIP FIRM |
| aamrapaliresicom@gmail.com | |
| Mobile | 8980025378 |
| Company Registration No. | GUJVA100819 |
| PAN | AARFG6793P |
| Date of Incorporation | 2017-09-14 |
| Experience (Years) | 1 |
| Area Constructed (sqm) | 7693 |
| Projects Completed | 0 |
| Ongoing Projects | 1 |
| Partner 1 | RACHIT VASUBHAI PATEL |
| PAN | BDOPP6008F |
| Address | 41, KUNJ SOCIETY, ALKAPURI |
| Partner 2 | JAYESHBHAI RATICHANDRA KHANDERIA |
| PAN | AKXPK4311R |
| Address | 10, SAMARPAN BUNGALOWS, INSIDE SAMARPAN SOCIETY, OPP. DMART, VASNA ROAD |
| Partner 3 | PRAVINKUMAR CHIMANBHAI PATEL |
| PAN | AVCPP0658G |
| Address | C-402, AAMRAPALI COMPLEX, WATER TANK ROAD, KARELIBAUG |
| Partner 4 | JAYENDRA BHAILALBHAI PATEL |
| PAN | AOJPP8950K |
| Address | 160, VIJAY SOCIETY-2,, R. V. DESAI ROAD, BAKRAWADI |
| Partner 5 | VASUBHAI CHUNIBHAI PATEL |
| PAN | AFWPP2155E |
| Address | 41, KUNJ SOCIETY, ALKAPURI |
| Partner 6 | YOGENDRA HASMUKHLAL SHAH |
| PAN | AFSPS8296M |
| Address | 108, ALKA SOCIETY, OPP. AKOTA ATITHI GRUH, AKOTA |
| Partner 7 | BHAVINBHAI BHARATBHAI PATEL |
| PAN | ASHPP3999A |
| Address | 6/A, SHANTI VILLA DUPLEX,, DEEP CHAMBER JUNCTION, MANJALPUR |
| Partner 8 | NEENABEN KANUBHAI PATEL |
| PAN | ATAPP4287H |
| Address | 6/A, SHANTI VILLA DUPLEX,, DEEP CHAMBER JUNCTION, MANJALPUR |
| Partner 9 | MIHIR CHANDRAMOHAN SHAH |
| PAN | AFSPS8295J |
| Address | 108, ALKA SOCIETY, OPP. AKOTA ATITHI GRUH, AKOTA |
| TOWER 1-WING A+B+C+D - Start Date | 2018-07-15 |
| TOWER 1-WING A+B+C+D - End Date | 2026-06-30 |
| TOWER 1-WING A+B+C+D - Height | 36.45 |
| TOWER 1-WING A+B+C+D - FSI | 11816.31 |
| TOWER 1-WING A+B+C+D - Built-up Area | 16258.41 |
| TOWER 1-WING A+B+C+D - Progress | 63.68% |
| TOWER 1-WING A+B+C+D - Booked Units | 121 |
| TOWER 1-WING A+B+C+D - Unbooked Units | 69 |
| TOWER 2-WING E+F - Start Date | 2018-07-15 |
| TOWER 2-WING E+F - End Date | 2026-06-30 |
| TOWER 2-WING E+F - Height | 17.8 |
| TOWER 2-WING E+F - FSI | 3458.05 |
| TOWER 2-WING E+F - Built-up Area | 4517.6 |
| TOWER 2-WING E+F - Progress | 100.0% |
| TOWER 2-WING E+F - Booked Units | 40 |
| TOWER 2-WING E+F - Unbooked Units | 0 |
| TOWER 3-WING G - Start Date | 2018-07-15 |
| TOWER 3-WING G - End Date | 2026-06-30 |
| TOWER 3-WING G - Height | 17.8 |
| TOWER 3-WING G - FSI | 1731.0 |
| TOWER 3-WING G - Built-up Area | 2261.17 |
| TOWER 3-WING G - Progress | 100.0% |
| TOWER 3-WING G - Booked Units | 20 |
| TOWER 3-WING G - Unbooked Units | 0 |
| TOWER 4-WING H - Start Date | 2018-07-15 |
| TOWER 4-WING H - End Date | 2026-06-30 |
| TOWER 4-WING H - Height | 27 |
| TOWER 4-WING H - FSI | 2405.97 |
| TOWER 4-WING H - Built-up Area | 3085.97 |
| TOWER 4-WING H - Progress | 96.43% |
| TOWER 4-WING H - Booked Units | 27 |
| TOWER 4-WING H - Unbooked Units | 1 |
| TOWER 5-WING I+J - Start Date | 2018-07-15 |
| TOWER 5-WING I+J - End Date | 2026-06-30 |
| TOWER 5-WING I+J - Height | 27 |
| TOWER 5-WING I+J - FSI | 4779.18 |
| TOWER 5-WING I+J - Built-up Area | 8251.08 |
| TOWER 5-WING I+J - Progress | 98.21% |
| TOWER 5-WING I+J - Booked Units | 55 |
| TOWER 5-WING I+J - Unbooked Units | 1 |
| TOWER 6-WING K+L - Start Date | 2018-07-15 |
| TOWER 6-WING K+L - End Date | 2026-06-30 |
| TOWER 6-WING K+L - Height | 27 |
| TOWER 6-WING K+L - FSI | 4779.18 |
| TOWER 6-WING K+L - Built-up Area | 6132.7 |
| TOWER 6-WING K+L - Progress | 100.0% |
| TOWER 6-WING K+L - Booked Units | 56 |
| TOWER 6-WING K+L - Unbooked Units | 0 |
| TRIPLEX - Start Date | 2018-07-15 |
| TRIPLEX - End Date | 2026-06-30 |
| TRIPLEX - Height | 10.05 |
| TRIPLEX - FSI | 9038.32 |
| TRIPLEX - Built-up Area | 9038.32 |
| TRIPLEX - Progress | 100.0% |
| TRIPLEX - Booked Units | 51 |
| TRIPLEX - Unbooked Units | 0 |
| Office - Total Units | 25 |
| Office - Booked Units | 5 |
| Office - Carpet Area | 921.15 |
| Office - Exclusive Area | 0.0 |
| Office - Open Terrace Area | 0.0 |
| Flat - Total Units | 296 |
| Flat - Booked Units | 245 |
| Flat - Carpet Area | 21698.2 |
| Flat - Exclusive Area | 1749.96 |
| Flat - Open Terrace Area | 0.0 |
| Bungalow - Total Units | 51 |
| Bungalow - Booked Units | 49 |
| Bungalow - Carpet Area | 6883.28 |
| Bungalow - Exclusive Area | 536.93 |
| Bungalow - Open Terrace Area | 0.0 |
| Shop - Total Units | 69 |
| Shop - Booked Units | 32 |
| Shop - Carpet Area | 1933.1 |
| Shop - Exclusive Area | 0.0 |
| Shop - Open Terrace Area | 0.0 |
| February 2019 | 16.6% |
| May 2019 | 18.38% |
| August 2019 | 21.8% |
| November 2019 | 25.59% |
| February 2020 | 28.21% |
| August 2020 | 31.08% |
| November 2020 | 37.01% |
| February 2021 | 38.84% |
| May 2021 | 45.57% |
| August 2021 | 54.44% |
| November 2021 | 60.66% |
| February 2022 | 64.57% |
| May 2022 | 72.3% |
| August 2022 | 74.39% |
| November 2022 | 76.1% |
| February 2023 | 77.28% |
| May 2023 | 88.7% |
| August 2023 | 89.39% |
| November 2023 | 89.55% |
| January 2024 | 91.81% |
| April 2024 | 96.21% |
| July 2024 | 96.75% |
| October 2025 | 99.06% |
| July 2026 | 98.18% |
| Architect | SUDHIRKUMAR RAMANLAL SHAH |
| Licence No. | CA/85/9483 |
| Engineer | ALPESH RAJNIKANT CHAUHAN |
| Licence No. | EOR-315(LR) |