AASHIRWAD BUNGLOWS & AVENUE
EMPIRE CORPORATION
AASHIRWAD BUNGLOWS & AVENUE, PATADIYA HANUMAN ROAD, B/H ZAIN SCHOOL, PADRA,VADODARA
Approved
9th Jul 2021
Completed
31st Mar 2023
Registration No.
PR/GJ/VADODARA/PADRA/Others/RAA08740/090721
Acknowledgement No.
PR/VADODARA/PADRA/VADODARA TPO/210326/010576
Project Type
Residential/Group Housing
Approving Authority
Others
District
Vadodara
Taluka
Padra
State
Gujarat
Project Details
| Project Name | AASHIRWAD BUNGLOWS & AVENUE |
| RERA Number | PR/GJ/VADODARA/PADRA/Others/RAA08740/090721 |
| Acknowledgement Number | PR/VADODARA/PADRA/VADODARA TPO/210326/010576 |
| Project Description | NEW RESIDENTIAL SCHEME WITH 19 UNITS |
| Project Type | Residential/Group Housing |
| Project Status | Completed |
| District | Vadodara |
| Taluka | Padra |
| Address | AASHIRWAD BUNGLOWS & AVENUE, PATADIYA HANUMAN ROAD, B/H ZAIN SCHOOL, PADRA,VADODARA |
| State | Gujarat |
| Approving Authority | Others |
| Approved On | 2021-07-09 |
| Start Date | 2017-09-28 |
| End Date | 2023-03-31 |
| Submission Date | 2021-03-01 |
| Months Delayed | 0 |
Area & Cost Details
| Total Land Area | 7088.0 |
| Total Land Area (Registered) | 3235.38 |
| Total Covered Area | 949.0 |
| Total Open Area | 2286.38 |
| Total Carpet Area | 1328.0 |
| Open Parking Area | 1435.91 |
| Covered Parking Area | 0.0 |
| Covered Parking Count | 0 |
| Parking for Sale Count | 6 |
| Cost of Land | 25835117 |
| Estimated Project Cost | 27926122 |
| Total Project Cost | 53761239 |
Promoter Details
| Promoter Name | EMPIRE CORPORATION |
| Promoter Type | PARTNERSHIP FIRM |
| emp********************@gmail.com | |
| Mobile | 97******** |
| Company Registration No. | NOT APPLICABLE |
| PAN | AAG******* |
| Experience (Years) | 0 |
| Area Constructed (sqm) | 3235 |
| Projects Completed | 0 |
| Ongoing Projects | 1 |
Promoter Partners
| Partner 1 | MR MUKHTARBHAI SHAFIBHAI DADI |
| Address | 101, AASHIYANA COMPLEX, TANDALJA,VADODARA |
| Partner 2 | MR. GULAMHUSSAIN SHAYIDAHMED DADI |
| Address | 401, HEMPTON SQUARE,, FATEHGUNJ, VADODARA |
| Partner 3 | MR. BIMAL YOGESH DESAI |
| Address | 22-B, KUNJ SOCIETY,, ALKAPURI, VADODARA |
| Partner 4 | MRS. YASMEEN GULAMHUSSAIN DADI |
| Address | 401,HEMPTON SQUARE,, FATEHGUNJ, VADODARA |
| Partner 5 | MR. HASHAM FARUQ SHIKARI |
| Address | SHIKARI MOHALLA,, GODHRA |
| Partner 6 | MRS. ZEBA MOHAMEDHANIF SHIKARI |
| Address | SHIKARI MOHALLA, GODHARA |
| Partner 7 | MR. MOHAMEDHANIF FAROOQ SHIKARI |
| Address | SHIKARI MOHALLA, GODHARA |
| Partner 8 | MRS. AFROZ NAJMUL HASAN |
| Address | 39, AARZOO BUNGLOWS, SUNPHARMA ROAD, TANDALJA, VADODARA |
| Partner 9 | MR. SIDDIQ SULEMAN DADI |
| Address | DADI MANTION, DHOBI TALAV, B/H METRO CINEMA, MUMBAI |
Building Blocks
| 1+2 - Start Date | 2017-09-28 |
| 1+2 - End Date | 2023-03-31 |
| 1+2 - Progress | 100.0% |
| 1+2 - Booked Units | 2 |
| 1+2 - Unbooked Units | 0 |
| 3+4 - Start Date | 2017-09-28 |
| 3+4 - End Date | 2023-03-31 |
| 3+4 - Progress | 0.0% |
| 3+4 - Booked Units | 0 |
| 3+4 - Unbooked Units | 2 |
| 5+6 - Start Date | 2017-09-28 |
| 5+6 - End Date | 2023-03-31 |
| 5+6 - Progress | 100.0% |
| 5+6 - Booked Units | 2 |
| 5+6 - Unbooked Units | 0 |
| 7+8 - Start Date | 2017-09-28 |
| 7+8 - End Date | 2023-03-31 |
| 7+8 - Progress | 100.0% |
| 7+8 - Booked Units | 2 |
| 7+8 - Unbooked Units | 0 |
| 9+10 - Start Date | 2017-09-28 |
| 9+10 - End Date | 2023-03-31 |
| 9+10 - Progress | 50.0% |
| 9+10 - Booked Units | 1 |
| 9+10 - Unbooked Units | 1 |
| 11 - Start Date | 2017-09-28 |
| 11 - End Date | 2023-03-31 |
| 11 - Progress | 100.0% |
| 11 - Booked Units | 1 |
| 11 - Unbooked Units | 0 |
| 12+13 - Start Date | 2017-09-28 |
| 12+13 - End Date | 2023-03-31 |
| 12+13 - Progress | 50.0% |
| 12+13 - Booked Units | 1 |
| 12+13 - Unbooked Units | 1 |
| 14+15 - Start Date | 2017-09-28 |
| 14+15 - End Date | 2023-03-31 |
| 14+15 - Progress | 50.0% |
| 14+15 - Booked Units | 1 |
| 14+15 - Unbooked Units | 1 |
| 16+17 - Start Date | 2017-09-28 |
| 16+17 - End Date | 2023-03-31 |
| 16+17 - Progress | 50.0% |
| 16+17 - Booked Units | 1 |
| 16+17 - Unbooked Units | 1 |
| 18+19 - Start Date | 2017-09-28 |
| 18+19 - End Date | 2023-03-31 |
| 18+19 - Progress | 100.0% |
| 18+19 - Booked Units | 2 |
| 18+19 - Unbooked Units | 0 |
Inventory Units
| RESIDENTIAL UNITS - Total Units | 19 |
| RESIDENTIAL UNITS - Carpet Area | 1328.0 |
| RESIDENTIAL UNITS - Exclusive Area | 91.98 |
| RESIDENTIAL UNITS - Open Terrace Area | 0.0 |
Quarterly Progress
| December 2021 | 64.39% |
| March 2022 | 66.06% |
| June 2022 | 83.77% |
| September 2022 | 83.88% |
| December 2022 | 93.14% |
| March 2023 | 97.0% |
| April 2023 | 97.0% |
Professionals
| Architect | NIRMAL SHAH |
| Licence No. | CA/2017/82643 |
| Engineer | ZARNA ASSOCIATES |
| Licence No. | VMC LIC NO. SEOR/01/64/19-24 OR VUDA LIC NO.01/21/18-23 |
The information provided on this page is collated from publicly available resources. PropTech Pulse does not guarantee the accuracy, completeness, or authority of this data and shall not be held liable for any discrepancies. For queries or further assistance, please contact us at pulse@aurumproptech.in