Project Details

Project NameAL-AMEEN PARK
RERA NumberPR/GJ/VADODARA/VADODARA/Others/RAA02866/A1R/120319
Acknowledgement NumberPR/VADODARA/VADODARA/VADODARA TPO/170729/000518
Project DescriptionCONSTRUCTION OF 16 TENAMENT
Project TypeResidential/Group Housing
Project StatusAPPROVED
DistrictVadodara
TalukaVadodara
AddressOPP KALYAN PARTY PLOT, NEAR GOPAL BAUG, VASANA ROAD
Pincode390012
StateGujarat
Approving AuthorityVadodara Municipal Corporation
Approved On2018-06-08
Start Date2016-10-01
End Date2024-03-30
Submission Date2017-07-29
Months Delayed0

Area & Cost Details

Total Land Area6865.0
Total Covered Area6179.0
Total Open Area686.0
Open Parking Area378
Covered Parking Area418.0
Covered Parking Count1
Parking for Sale Count42
Cost of Land181157067
Estimated Project Cost138020000
Total Project Cost319177067

Land Details

MojeTandalja
TP No.23
TP NameTandalja

Promoter Details

Promoter NameAL KABEER DEVELOPERS
Promoter TypePARTNERSHIP FIRM
Emailinfo@al-kabeerdevelopers.com
Mobile9978692257
Company Registration No.GUJVA101360
PANABEFA9836B
Date of Incorporation2016-04-01
Experience (Years)10
Area Constructed (sqm)2500
Projects Completed0
Ongoing Projects1

Promoter Partners

Partner 1MUNAVVARKHAN PATHAN
PANACTPP2983J
AddressTAJ MANZIL NEAR TAJMALHAL SODA FACTORY, YAKUTPURA
Partner 2MUKESHKUMAR RAMNIKLAL PATEL
PANACMPP9011A
AddressAlaknanda Flat No.401,, Meghani Circle, Bhavnagar
Partner 3UDAYAN DHIRAJLAL VORA
PANABBPV0340C
AddressPlot No.1840,Aatabhai Road, Bhavnagar
Partner 4ABDUL KAYYUM KHAN ABDUL REHMAN KHAN PATHAN
PANACTPP2905J
AddressTaj Manjil, Nr.Tajmahal Soda Factory, Yakutpura, Vadodara
Partner 5DILIPBHAI CHAUHAN
PANABHPC0880E
AddressPlot No.2730lD Behind Patel Park, Nr.Airport,, Bhavnagar
Partner 6NILESH SHANKARBHAI NARSANGANI
PANABYPN7852Q
AddressPlot No.1284/A/3, Bhavnagar

Building Blocks

1 - Start Date2016-10-01
1 - End Date2024-03-30
1 - Progress100.0%
1 - Booked Units1
1 - Unbooked Units0
2 - Start Date2016-10-01
2 - End Date2024-03-30
2 - Progress100.0%
2 - Booked Units1
2 - Unbooked Units0
3 - Start Date2016-10-01
3 - End Date2024-03-30
3 - Progress100.0%
3 - Booked Units1
3 - Unbooked Units0
4 - Start Date2016-10-01
4 - End Date2024-03-30
4 - Progress100.0%
4 - Booked Units1
4 - Unbooked Units0
5 - Start Date2016-10-01
5 - End Date2024-03-30
5 - Progress100.0%
5 - Booked Units1
5 - Unbooked Units0
6 - Start Date2016-10-01
6 - End Date2024-03-30
6 - Progress100.0%
6 - Booked Units1
6 - Unbooked Units0
7 - Start Date2016-10-01
7 - End Date2024-03-30
7 - Progress100.0%
7 - Booked Units1
7 - Unbooked Units0
8 - Start Date2016-10-01
8 - End Date2024-03-30
8 - Progress100.0%
8 - Booked Units1
8 - Unbooked Units0
9 - Start Date2016-10-01
9 - End Date2024-03-30
9 - Progress100.0%
9 - Booked Units1
9 - Unbooked Units0
10 - Start Date2016-10-01
10 - End Date2024-03-30
10 - Progress100.0%
10 - Booked Units1
10 - Unbooked Units0
15 - Start Date2016-10-01
15 - End Date2024-03-30
15 - Progress100.0%
15 - Booked Units1
15 - Unbooked Units0
16 - Start Date2016-10-01
16 - End Date2024-03-30
16 - Progress100.0%
16 - Booked Units1
16 - Unbooked Units0
17 - Start Date2016-10-01
17 - End Date2024-03-30
17 - Progress100.0%
17 - Booked Units1
17 - Unbooked Units0
18 - Start Date2016-10-01
18 - End Date2024-03-30
18 - Progress100.0%
18 - Booked Units1
18 - Unbooked Units0
19 - Start Date2016-10-01
19 - End Date2024-03-30
19 - Progress100.0%
19 - Booked Units1
19 - Unbooked Units0
20 - Start Date2016-10-01
20 - End Date2024-03-30
20 - Progress100.0%
20 - Booked Units1
20 - Unbooked Units0
11 - Start Date2016-10-01
11 - End Date2024-03-30
11 - Progress100.0%
11 - Booked Units1
11 - Unbooked Units0
12 - Start Date2016-10-01
12 - End Date2024-03-30
12 - Progress100.0%
12 - Booked Units1
12 - Unbooked Units0
13 - Start Date2016-10-01
13 - End Date2024-03-30
13 - Progress100.0%
13 - Booked Units1
13 - Unbooked Units0
14 - Start Date2016-10-01
14 - End Date2024-03-30
14 - Progress100.0%
14 - Booked Units1
14 - Unbooked Units0
21 - Start Date2016-10-01
21 - End Date2024-03-30
21 - Progress100.0%
21 - Booked Units1
21 - Unbooked Units0
22 - Start Date2016-10-01
22 - End Date2024-03-30
22 - Progress100.0%
22 - Booked Units1
22 - Unbooked Units0
23 - Start Date2016-10-01
23 - End Date2024-03-30
23 - Progress100.0%
23 - Booked Units1
23 - Unbooked Units0
24 - Start Date2016-10-01
24 - End Date2024-03-30
24 - Progress100.0%
24 - Booked Units1
24 - Unbooked Units0
25 - Start Date2016-10-01
25 - End Date2024-03-30
25 - Progress100.0%
25 - Booked Units1
25 - Unbooked Units0
26 - Start Date2016-10-01
26 - End Date2024-03-30
26 - Progress100.0%
26 - Booked Units1
26 - Unbooked Units0
27 - Start Date2016-10-01
27 - End Date2024-03-30
27 - Progress100.0%
27 - Booked Units1
27 - Unbooked Units0
28 - Start Date2016-10-01
28 - End Date2024-03-30
28 - Progress100.0%
28 - Booked Units1
28 - Unbooked Units0
29 - Start Date2016-10-01
29 - End Date2024-03-30
29 - Progress100.0%
29 - Booked Units1
29 - Unbooked Units0
30 - Start Date2016-10-01
30 - End Date2024-03-30
30 - Progress100.0%
30 - Booked Units1
30 - Unbooked Units0
31 - Start Date2016-10-01
31 - End Date2024-03-30
31 - Progress100.0%
31 - Booked Units1
31 - Unbooked Units0
32 - Start Date2016-10-01
32 - End Date2024-03-30
32 - Progress100.0%
32 - Booked Units1
32 - Unbooked Units0
33 - Start Date2016-10-01
33 - End Date2024-03-30
33 - Progress100.0%
33 - Booked Units1
33 - Unbooked Units0
34 - Start Date2016-10-01
34 - End Date2024-03-30
34 - Progress100.0%
34 - Booked Units1
34 - Unbooked Units0
35 - Start Date2016-10-01
35 - End Date2024-03-30
35 - Progress100.0%
35 - Booked Units1
35 - Unbooked Units0
36 - Start Date2016-10-01
36 - End Date2024-03-30
36 - Progress100.0%
36 - Booked Units1
36 - Unbooked Units0
37 - Start Date2016-10-01
37 - End Date2024-03-30
37 - Progress100.0%
37 - Booked Units1
37 - Unbooked Units0
38 - Start Date2016-10-01
38 - End Date2024-03-30
38 - Progress100.0%
38 - Booked Units1
38 - Unbooked Units0
39 - Start Date2016-10-01
39 - End Date2024-03-30
39 - Progress100.0%
39 - Booked Units1
39 - Unbooked Units0
40 - Start Date2016-10-01
40 - End Date2024-03-30
40 - Progress100.0%
40 - Booked Units1
40 - Unbooked Units0
41 - Start Date2016-10-01
41 - End Date2024-03-30
41 - Progress100.0%
41 - Booked Units1
41 - Unbooked Units0
42 - Start Date2016-10-01
42 - End Date2024-03-30
42 - Progress100.0%
42 - Booked Units1
42 - Unbooked Units0
TOWER A - Start Date2016-10-01
TOWER A - End Date2024-03-30
TOWER A - Progress90.0%
TOWER A - Booked Units18
TOWER A - Unbooked Units2

Inventory Units

Residential - Total Units62
Residential - Completed Units0
Residential - Booked Units37
Residential - Carpet Area6821.36
Residential - Exclusive Area0.0
Residential - Open Terrace Area0.0

Quarterly Progress

November 201865.06%
February 201972.58%
May 201962.94%
August 201969.46%
November 201974.48%
February 202076.69%
August 202076.9%
November 202079.88%
February 202179.88%
May 202182.37%
August 202183.63%
November 202188.35%
February 202288.42%
May 202289.52%
August 202290.35%
April 202499.94%

Professionals

ArchitectARYA ASSOCIATES
Licence No.ER/37/16-18
EngineerZARANA ASSOCIATES
Licence No.SH64/16-19

Top Properties in Rajkot

Pexo Icon

Ask Pulse Ai anything about real estate

Unlock the Latest in Real Estate

News, Infographics, Blogs & More! Delivered to your inbox.

Proptech Pulse Logo

Data that drives action.
Insight that inspires action.
Technology that empowers action.“

Made with Love

Statue

© PropTech Pulse 2026, All rights reserved.

Terms of Use and Privacy Policy