AIM REALTY
3, Asopalav Coutry Side near Planet Green,, Talsat Vadodara
Approved
25th Oct 2018
Pending
30th Jun 2026
Registration No.
PR/GJ/VADODARA/VADODARA/Others/RAA03823/251018
Acknowledgement No.
PR/VADODARA/VADODARA/GANDHINAGAR TPO/180804/005882
Project Type
Residential/Group Housing
Approving Authority
Vadodara Urban Development Authority
District
Vadodara
Taluka
Vadodara
State
Gujarat
| Project Name | Asopalav Presidential Villa |
| RERA Number | PR/GJ/VADODARA/VADODARA/Others/RAA03823/251018 |
| Acknowledgement Number | PR/VADODARA/VADODARA/GANDHINAGAR TPO/180804/005882 |
| Project Description | 4BHK Ultra Luxurious Villa |
| Project Type | Residential/Group Housing |
| Project Status | APPROVED |
| District | Vadodara |
| Taluka | Vadodara |
| Address | 3, Asopalav Coutry Side near Planet Green,, Talsat Vadodara |
| Pincode | 391410 |
| State | Gujarat |
| Approving Authority | Vadodara Urban Development Authority |
| Approved On | 2018-10-25 |
| Start Date | 2017-10-12 |
| End Date | 2026-06-30 |
| Submission Date | 2018-08-04 |
| Months Delayed | 0 |
| Total Land Area | 10032.8 |
| Total Covered Area | 1586.0 |
| Total Open Area | 3276.0 |
| Open Parking Area | 0 |
| Covered Parking Area | 198.0 |
| Covered Parking Count | 30 |
| Parking for Sale Count | 0 |
| Cost of Land | 27003770 |
| Estimated Project Cost | 52169525 |
| Total Project Cost | 52169525 |
| Moje | Vadodara |
| Plot No. | Chaapad |
| Sub Plot No. | - |
| Promoter Name | AIM REALTY |
| Promoter Type | PARTNERSHIP FIRM |
| asopalavchapad@gmail.com | |
| Mobile | 9825801936 |
| Company Registration No. | GUJVA104034 |
| PAN | ABCFA7539D |
| Date of Incorporation | 2015-04-01 |
| Experience (Years) | 0 |
| Area Constructed (sqm) | 1364 |
| Projects Completed | 0 |
| Ongoing Projects | 1 |
| Partner 1 | SUBODH DHIRAJLAL SHAH |
| PAN | AFKPS2294B |
| Address | 7 Sunrise park,Opp. Kalyan Party Plot, Vasna Road,Vadodara |
| Partner 2 | SANJAY PRAVINCHANDRA PARIKH |
| PAN | AAAPP8605Q |
| Address | 41, UMANGBUILDINGKASHIBAINAVRANGE, MUMBAI |
| Partner 3 | MANTHAN SUBODH SHAH |
| PAN | BGFPS3402N |
| Address | A7, SunrisePark, VasanaRoad |
| 6 - Start Date | 2017-10-12 |
| 6 - End Date | 2026-06-30 |
| 6 - Progress | 100.0% |
| 6 - Booked Units | 1 |
| 6 - Unbooked Units | 0 |
| 7 - Start Date | 2017-10-12 |
| 7 - End Date | 2026-06-30 |
| 7 - Progress | 100.0% |
| 7 - Booked Units | 1 |
| 7 - Unbooked Units | 0 |
| 8 - Start Date | 2017-10-12 |
| 8 - End Date | 2026-06-30 |
| 8 - Progress | 100.0% |
| 8 - Booked Units | 1 |
| 8 - Unbooked Units | 0 |
| 9 - Start Date | 2017-10-12 |
| 9 - End Date | 2026-06-30 |
| 9 - Progress | 100.0% |
| 9 - Booked Units | 1 |
| 9 - Unbooked Units | 0 |
| 10 - Start Date | 2017-10-12 |
| 10 - End Date | 2026-06-30 |
| 10 - Progress | 100.0% |
| 10 - Booked Units | 1 |
| 10 - Unbooked Units | 0 |
| 11 - Start Date | 2017-10-12 |
| 11 - End Date | 2026-06-30 |
| 11 - Progress | 100.0% |
| 11 - Booked Units | 1 |
| 11 - Unbooked Units | 0 |
| 12 - Start Date | 2017-10-12 |
| 12 - End Date | 2026-06-30 |
| 12 - Progress | 100.0% |
| 12 - Booked Units | 1 |
| 12 - Unbooked Units | 0 |
| 13 - Start Date | 2017-10-12 |
| 13 - End Date | 2026-06-30 |
| 13 - Progress | 100.0% |
| 13 - Booked Units | 1 |
| 13 - Unbooked Units | 0 |
| 14 - Start Date | 2017-10-12 |
| 14 - End Date | 2026-06-30 |
| 14 - Progress | 100.0% |
| 14 - Booked Units | 1 |
| 14 - Unbooked Units | 0 |
| 15 - Start Date | 2017-10-12 |
| 15 - End Date | 2026-06-30 |
| 15 - Progress | 0.0% |
| 15 - Booked Units | 0 |
| 15 - Unbooked Units | 1 |
| 16 - Start Date | 2017-10-12 |
| 16 - End Date | 2026-06-30 |
| 16 - Progress | 0.0% |
| 16 - Booked Units | 0 |
| 16 - Unbooked Units | 1 |
| 17 - Start Date | 2017-10-12 |
| 17 - End Date | 2026-06-30 |
| 17 - Progress | 100.0% |
| 17 - Booked Units | 1 |
| 17 - Unbooked Units | 0 |
| 18 - Start Date | 2017-10-12 |
| 18 - End Date | 2026-06-30 |
| 18 - Progress | 100.0% |
| 18 - Booked Units | 1 |
| 18 - Unbooked Units | 0 |
| 19 - Start Date | 2017-10-12 |
| 19 - End Date | 2026-06-30 |
| 19 - Progress | 100.0% |
| 19 - Booked Units | 1 |
| 19 - Unbooked Units | 0 |
| 20 - Start Date | 2017-10-12 |
| 20 - End Date | 2026-06-30 |
| 20 - Progress | 100.0% |
| 20 - Booked Units | 1 |
| 20 - Unbooked Units | 0 |
| Residential - Total Units | 12 |
| Residential - Carpet Area | 1623.0 |
| Residential - Exclusive Area | 289.0 |
| Residential - Open Terrace Area | 1583.0 |
| March 2019 | 23.19% |
| June 2019 | 30.56% |
| September 2019 | 31.78% |
| December 2019 | 33.94% |
| March 2020 | 36.39% |
| September 2020 | 40.56% |
| December 2020 | 40.62% |
| March 2021 | 41.17% |
| June 2021 | 40.12% |
| September 2021 | 40.12% |
| December 2021 | 40.13% |
| March 2022 | 40.32% |
| June 2022 | 51.42% |
| September 2022 | 53.24% |
| December 2022 | 55.83% |
| March 2023 | 55.85% |
| June 2023 | 61.75% |
| September 2023 | 61.56% |
| December 2023 | 62.59% |
| April 2024 | 62.67% |
| July 2024 | 62.36% |
| October 2024 | 62.43% |
| Architect | Nirmal S. Shah |
| Licence No. | CA/2017/82643 |
| Engineer | Dr. M.K. Marulya |
| Licence No. | VUDA LIC.NO.S-94(ER/SH) |
| Contractor | Prakash solanki |