JAY BHOLE ENTERPRISE
KAMAXI HEIGHTS BESIDE RAJESHWAR GREEN, NEAR MOTNATH MAHADEV HARNI
Approved
24th Feb 2021
Pending
31st Dec 2026
Registration No.
PR/GJ/VADODARA/VADODARA/Others/RAA08114/240221
Acknowledgement No.
PR/VADODARA/VADODARA/VADODARA TPO/210116/010241
Project Type
Residential/Group Housing
Approving Authority
Others
District
Vadodara
Taluka
Vadodara
State
Gujarat
| Project Name | KAMAXI HEIGHTS |
| RERA Number | PR/GJ/VADODARA/VADODARA/Others/RAA08114/240221 |
| Acknowledgement Number | PR/VADODARA/VADODARA/VADODARA TPO/210116/010241 |
| Project Description | construction of 4 Building total 84 Residential units, single Phase |
| Project Type | Residential/Group Housing |
| Project Status | APPROVED |
| District | Vadodara |
| Taluka | Vadodara |
| Address | KAMAXI HEIGHTS BESIDE RAJESHWAR GREEN, NEAR MOTNATH MAHADEV HARNI |
| State | Gujarat |
| Approving Authority | Others |
| Approved On | 2021-02-24 |
| Start Date | 2020-12-03 |
| End Date | 2026-12-31 |
| Submission Date | 2021-01-07 |
| Months Delayed | 0 |
| Total Land Area | 4465.0 |
| Total Land Area (Registered) | 4465.0 |
| Total Covered Area | 1899.04 |
| Total Open Area | 2565.96 |
| Total Carpet Area | 10267.25 |
| Open Parking Area | 2447.9 |
| Covered Parking Area | 0.0 |
| Covered Parking Count | 0 |
| Parking for Sale Count | 1 |
| Cost of Land | 92385835 |
| Estimated Project Cost | 287192030 |
| Total Project Cost | 379577865 |
| Promoter Name | JAY BHOLE ENTERPRISE |
| Promoter Type | PARTNERSHIP FIRM |
| kamaxiheight@gmail.com | |
| Mobile | 9824693888 |
| Company Registration No. | GUJVA102149 |
| PAN | AAQFJ2231E |
| Date of Incorporation | 2020-08-05 |
| Partner 1 | MANOJ KANJIBHAI BHIMANI |
| PAN | AFKPB2646G |
| Address | D 1 SURYA PARK SOCIETY OPP SHIVAM SOCIETY, ABHILASHA CHAR RASTA NEW SAMA ROAD |
| Partner 2 | MANISHA MANOJ BHIMANI |
| PAN | APNPB1818H |
| Address | D 1 SURYA PARK SOCIETY OPP SHIVAM SOCIETY, ABHILASHA CHAR RASTA NEW SAMA ROAD |
| TOWER A - Start Date | 2020-12-03 |
| TOWER A - End Date | 2026-12-31 |
| TOWER A - Progress | 100.0% |
| TOWER A - Booked Units | 14 |
| TOWER A - Unbooked Units | 0 |
| TOWER B - Start Date | 2020-12-03 |
| TOWER B - End Date | 2026-12-31 |
| TOWER B - Progress | 100.0% |
| TOWER B - Booked Units | 28 |
| TOWER B - Unbooked Units | 0 |
| TOWER C - Start Date | 2020-12-03 |
| TOWER C - End Date | 2026-12-31 |
| TOWER C - Progress | 100.0% |
| TOWER C - Booked Units | 28 |
| TOWER C - Unbooked Units | 0 |
| TOWER D - Start Date | 2020-12-03 |
| TOWER D - End Date | 2026-12-31 |
| TOWER D - Progress | 100.0% |
| TOWER D - Booked Units | 14 |
| TOWER D - Unbooked Units | 0 |
| RESIDENTIAL UNITS - Total Units | 84 |
| RESIDENTIAL UNITS - Carpet Area | 10267.25 |
| RESIDENTIAL UNITS - Exclusive Area | 1041.6 |
| RESIDENTIAL UNITS - Open Terrace Area | 0.0 |
| July 2021 | 21.31% |
| October 2021 | 23.18% |
| January 2022 | 32.21% |
| April 2022 | 43.18% |
| July 2022 | 49.46% |
| October 2022 | 63.11% |
| January 2023 | 67.72% |
| April 2023 | 69.05% |
| July 2023 | 70.24% |
| October 2023 | 77.6% |
| January 2024 | 78.01% |
| April 2024 | 78.01% |
| July 2024 | 80.04% |
| October 2024 | 80.63% |
| October 2025 | 99.93% |
| January 2026 | 99.93% |
| January 2027 | 100.0% |
| Architect | MATAI ASSOCIATES |
| Licence No. | CA/2013/60444 |
| Engineer | ASHOK SHAH & ASSOCIATES |
| Licence No. | SEOR-01/73/2019-2024 |