KRISHNA EMPIRE
AMAR OPULENT
T.P. 48 CHHANI MAIN ROAD BH. PRAKRUTI RESORT, OPP. RAMAKAKA DERI VADODARA 390024
Approved
3rd Jul 2018
Completed
31st Dec 2019
Registration No.
PR/GJ/VADODARA/VADODARA/Others/MAA03070/EX1/200219
Acknowledgement No.
PR/VADODARA/VADODARA/VADODARA TPO/170830/001820
Project Type
Mixed Development
Approving Authority
Vadodara Municipal Corporation
District
Vadodara
Taluka
Vadodara
State
Gujarat
Project Details
| Project Name | KRISHNA EMPIRE |
| RERA Number | PR/GJ/VADODARA/VADODARA/Others/MAA03070/EX1/200219 |
| Acknowledgement Number | PR/VADODARA/VADODARA/VADODARA TPO/170830/001820 |
| Project Description | 8 TOWER RESIDENTIAL AND COMMERCIAL |
| Project Type | Mixed Development |
| Project Status | Completed |
| District | Vadodara |
| Taluka | Vadodara |
| Address | T.P. 48 CHHANI MAIN ROAD BH. PRAKRUTI RESORT, OPP. RAMAKAKA DERI VADODARA 390024 |
| Pincode | 391740 |
| State | Gujarat |
| Approving Authority | Vadodara Municipal Corporation |
| Approved On | 2018-07-03 |
| Start Date | 2015-08-01 |
| End Date | 2019-12-31 |
| Submission Date | 2017-08-30 |
| Months Delayed | 0 |
Area & Cost Details
| Total Land Area | 4250.0 |
| Total Covered Area | 7589.0 |
| Total Open Area | 3102.0 |
| Open Parking Area | 478 |
| Covered Parking Area | 925.0 |
| Covered Parking Count | 0 |
| Parking for Sale Count | 0 |
| Cost of Land | 67776160 |
| Estimated Project Cost | 205000000 |
| Total Project Cost | 272776160 |
Land Details
| Moje | Chhani |
| TP No. | 48 |
| TP Name | Chhani |
Promoter Details
| Promoter Name | AMAR OPULENT |
| Promoter Type | PARTNERSHIP FIRM |
| raj***********@gmail.com | |
| Mobile | 74******** |
| Company Registration No. | not applicable |
| PAN | ABC******* |
| Experience (Years) | 15 |
| Area Constructed (sqm) | 28189 |
| Projects Completed | 10 |
| Ongoing Projects | 2 |
Promoter Partners
| Partner 1 | HITESH H. MOJIDRA |
| Address | E-5 RAGHUVIR NAGAR, NEW SAMA ROAD, Vadodara |
Building Blocks
| TOWER A - Start Date | 2015-08-01 |
| TOWER A - End Date | 2019-12-31 |
| TOWER A - Progress | 100.0% |
| TOWER A - Booked Units | 55 |
| TOWER A - Unbooked Units | 0 |
| TOWER B - Start Date | 2015-08-01 |
| TOWER B - End Date | 2019-12-31 |
| TOWER B - Progress | 100.0% |
| TOWER B - Booked Units | 17 |
| TOWER B - Unbooked Units | 0 |
| TOWER C - Start Date | 2015-08-01 |
| TOWER C - End Date | 2019-12-31 |
| TOWER C - Progress | 100.0% |
| TOWER C - Booked Units | 17 |
| TOWER C - Unbooked Units | 0 |
| TOWER D - Start Date | 2015-08-01 |
| TOWER D - End Date | 2019-12-31 |
| TOWER D - Progress | 100.0% |
| TOWER D - Booked Units | 13 |
| TOWER D - Unbooked Units | 0 |
| TOWER E - Start Date | 2015-08-01 |
| TOWER E - End Date | 2019-12-31 |
| TOWER E - Progress | 100.0% |
| TOWER E - Booked Units | 20 |
| TOWER E - Unbooked Units | 0 |
| TOWER F - Start Date | 2015-08-01 |
| TOWER F - End Date | 2019-12-31 |
| TOWER F - Progress | 100.0% |
| TOWER F - Booked Units | 20 |
| TOWER F - Unbooked Units | 0 |
| TOWER G - Start Date | 2015-08-01 |
| TOWER G - End Date | 2019-12-31 |
| TOWER G - Progress | 100.0% |
| TOWER G - Booked Units | 20 |
| TOWER G - Unbooked Units | 0 |
| TOWER H - Start Date | 2015-08-01 |
| TOWER H - End Date | 2019-12-31 |
| TOWER H - Progress | 100.0% |
| TOWER H - Booked Units | 30 |
| TOWER H - Unbooked Units | 0 |
Inventory Units
| RESIDENTIAL - Total Units | 154 |
| RESIDENTIAL - Carpet Area | 6797.0 |
| RESIDENTIAL - Exclusive Area | 0.0 |
| RESIDENTIAL - Open Terrace Area | 0.0 |
Quarterly Progress
| December 2018 | 100.0% |
| June 2019 | 100.0% |
| September 2019 | 100.0% |
| January 2020 | 100.0% |
The information provided on this page is collated from publicly available resources. PropTech Pulse does not guarantee the accuracy, completeness, or authority of this data and shall not be held liable for any discrepancies. For queries or further assistance, please contact us at pulse@aurumproptech.in