LIG SCHEME TP 1 FP 145
VADODARA MUNICIPAL CORPORATION
TP 1 FP 145 HARNI VADODARA, VADODARA
Approved
7th Sept 2018
Completed
30th Dec 2019
Registration No.
PR/GJ/VADODARA/VADODARA/Others/MAA03381/070918
Acknowledgement No.
PR/VADODARA/VADODARA/VADODARA TPO/170930/003480
Project Type
Mixed Development
Approving Authority
Vadodara Municipal Corporation
District
Vadodara
Taluka
Vadodara
State
Gujarat
Project Details
| Project Name | LIG SCHEME TP 1 FP 145 |
| RERA Number | PR/GJ/VADODARA/VADODARA/Others/MAA03381/070918 |
| Acknowledgement Number | PR/VADODARA/VADODARA/VADODARA TPO/170930/003480 |
| Project Description | PLANING DESIGNING & CONSTRUCTION OF FLAT TYPE HIGH RISE BUILDING CUM COMMERCIAL AT TP 1 FP 145 HARNI VADODARA |
| Project Type | Mixed Development |
| Project Status | Completed |
| District | Vadodara |
| Taluka | Vadodara |
| Address | TP 1 FP 145 HARNI VADODARA, VADODARA |
| Pincode | 390022 |
| State | Gujarat |
| Approving Authority | Vadodara Municipal Corporation |
| Approved On | 2018-09-07 |
| Start Date | 2016-04-01 |
| End Date | 2019-12-30 |
| Submission Date | 2017-09-30 |
| Months Delayed | 0 |
Area & Cost Details
| Total Land Area | 11097.13 |
| Total Covered Area | 5013.0 |
| Total Open Area | 6073.0 |
| Open Parking Area | 472 |
| Covered Parking Area | 3900.0 |
| Covered Parking Count | 12 |
| Parking for Sale Count | 1 |
| Cost of Land | 0 |
| Estimated Project Cost | 489216000 |
| Total Project Cost | 529356800 |
Land Details
| Moje | Harni |
| TP No. | 1 |
| TP Name | Harni |
Promoter Details
| Promoter Name | VADODARA MUNICIPAL CORPORATION |
| Promoter Type | COMPETENT AUTHORITY/ GOVERNMENT |
| rer*******@gmail.com | |
| Mobile | 94******** |
| Company Registration No. | N.A. |
| PAN | AAA******* |
| Date of Incorporation | 1966-01-04 |
| Experience (Years) | 75 |
| Area Constructed (sqm) | 20000 |
| Projects Completed | 18 |
| Ongoing Projects | 8 |
Promoter Partners
| Partner 1 | NILESH KANUBHAI PARMAR |
| PAN | AHB******* |
| Address | OFFICE OF EXECUTIVE ENGINEER, AFFORDABLE HOUSING DEPT, RAOPURA KANYASHALA NO.03, RAOPURA, VADODARA, VMC |
Building Blocks
| A - Start Date | 2016-04-01 |
| A - End Date | 2019-12-30 |
| A - Progress | 89.36% |
| A - Booked Units | 42 |
| A - Unbooked Units | 5 |
| B - Start Date | 2016-04-01 |
| B - End Date | 2019-12-30 |
| B - Progress | 89.36% |
| B - Booked Units | 42 |
| B - Unbooked Units | 5 |
| C - Start Date | 2016-04-01 |
| C - End Date | 2019-12-30 |
| C - Progress | 89.36% |
| C - Booked Units | 42 |
| C - Unbooked Units | 5 |
| D - Start Date | 2016-04-01 |
| D - End Date | 2019-12-30 |
| D - Progress | 87.5% |
| D - Booked Units | 42 |
| D - Unbooked Units | 6 |
| E - Start Date | 2016-04-01 |
| E - End Date | 2019-12-30 |
| E - Progress | 100.0% |
| E - Booked Units | 14 |
| E - Unbooked Units | 0 |
| F - Start Date | 2016-04-01 |
| F - End Date | 2019-12-30 |
| F - Progress | 100.0% |
| F - Booked Units | 42 |
| F - Unbooked Units | 0 |
| G - Start Date | 2016-04-01 |
| G - End Date | 2019-12-30 |
| G - Progress | 100.0% |
| G - Booked Units | 42 |
| G - Unbooked Units | 0 |
| H - Start Date | 2016-04-01 |
| H - End Date | 2019-12-30 |
| H - Progress | 100.0% |
| H - Booked Units | 28 |
| H - Unbooked Units | 0 |
| I - Start Date | 2016-04-01 |
| I - End Date | 2019-12-30 |
| I - Progress | 100.0% |
| I - Booked Units | 42 |
| I - Unbooked Units | 0 |
| J - Start Date | 2016-04-01 |
| J - End Date | 2019-12-30 |
| J - Progress | 100.0% |
| J - Booked Units | 42 |
| J - Unbooked Units | 0 |
| K - Start Date | 2016-04-01 |
| K - End Date | 2019-12-30 |
| K - Progress | 89.36% |
| K - Booked Units | 42 |
| K - Unbooked Units | 5 |
| L - Start Date | 2016-04-01 |
| L - End Date | 2019-12-30 |
| L - Progress | 89.36% |
| L - Booked Units | 42 |
| L - Unbooked Units | 5 |
Inventory Units
| LIG HOUSING UNIT - Total Units | 462 |
| LIG HOUSING UNIT - Carpet Area | 23742.0 |
| LIG HOUSING UNIT - Exclusive Area | 0.0 |
| LIG HOUSING UNIT - Open Terrace Area | 0.0 |
Quarterly Progress
| August 2019 | 100.0% |
| January 2020 | 100.0% |
Professionals
| Architect | ANAND TATU |
| Licence No. | CA 86 2014 18 |
| Engineer | JIGAR G SHAH |
| Licence No. | SH 106 2014 2017 |
| Contractor | RAJKAML BUILDERS INFRASTRUCTURE PVT LTD |
The information provided on this page is collated from publicly available resources. PropTech Pulse does not guarantee the accuracy, completeness, or authority of this data and shall not be held liable for any discrepancies. For queries or further assistance, please contact us at pulse@aurumproptech.in
Top Properties in Vadodara


Ask Pulse Ai anything about real estate