MARUTI INFRASTRUCTURE
Oppt. Satyam Exotica Duplex, Chhani-Dumad Road, VADODARA
Approved
16th Feb 2018
Pending
30th Jun 2026
Registration No.
PR/GJ/VADODARA/VADODARA/Others/RAA01641/160218
Acknowledgement No.
PR/VADODARA/VADODARA/VADODARA TPO/170919/002533
Project Type
Residential/Group Housing
Approving Authority
Vadodara Municipal Corporation
District
Vadodara
Taluka
Vadodara
State
Gujarat
| Project Name | MARUTI HEIGHTS |
| RERA Number | PR/GJ/VADODARA/VADODARA/Others/RAA01641/160218 |
| Acknowledgement Number | PR/VADODARA/VADODARA/VADODARA TPO/170919/002533 |
| Project Description | 14 RESIDENTIAL TOWERS |
| Project Type | Residential/Group Housing |
| Project Status | APPROVED |
| District | Vadodara |
| Taluka | Vadodara |
| Address | Oppt. Satyam Exotica Duplex, Chhani-Dumad Road, VADODARA |
| Pincode | 391740 |
| State | Gujarat |
| Approving Authority | Vadodara Municipal Corporation |
| Approved On | 2018-02-16 |
| Start Date | 2012-05-04 |
| End Date | 2026-06-30 |
| Submission Date | 2017-09-19 |
| Months Delayed | 0 |
| Total Land Area | 12410.0 |
| Total Covered Area | 3012.0 |
| Total Open Area | 5987.0 |
| Open Parking Area | 0 |
| Covered Parking Area | 3012.0 |
| Covered Parking Count | 280 |
| Parking for Sale Count | 0 |
| Cost of Land | 120214126 |
| Estimated Project Cost | 356400000 |
| Total Project Cost | 477867026 |
| Moje | Chhani |
| Plot No. | - |
| Promoter Name | MARUTI INFRASTRUCTURE |
| Promoter Type | PARTNERSHIP FIRM |
| marutiheights@gmail.com | |
| Mobile | 8733888422 |
| Company Registration No. | NOT APPLICABLE |
| PAN | AAUFM6755E |
| Experience (Years) | 10 |
| Area Constructed (sqm) | 12410 |
| Projects Completed | 0 |
| Ongoing Projects | 1 |
| Partner 1 | JAGDISH B MEGHANI |
| Address | B-14 AVANTI NAGAR, NEAR ABHILASHA CHAR RASTA, NEW SAMA ROAD, VADODARA |
| A - Start Date | 2012-05-04 |
| A - End Date | 2026-06-30 |
| A - Progress | 100.0% |
| A - Booked Units | 20 |
| A - Unbooked Units | 0 |
| B - Start Date | 2012-05-04 |
| B - End Date | 2026-06-30 |
| B - Progress | 90.0% |
| B - Booked Units | 18 |
| B - Unbooked Units | 2 |
| C - Start Date | 2012-05-04 |
| C - End Date | 2026-06-30 |
| C - Progress | 100.0% |
| C - Booked Units | 20 |
| C - Unbooked Units | 0 |
| D - Start Date | 2012-05-04 |
| D - End Date | 2026-06-30 |
| D - Progress | 80.0% |
| D - Booked Units | 16 |
| D - Unbooked Units | 4 |
| E - Start Date | 2012-05-04 |
| E - End Date | 2026-06-30 |
| E - Progress | 15.0% |
| E - Booked Units | 3 |
| E - Unbooked Units | 17 |
| F - Start Date | 2012-05-04 |
| F - End Date | 2026-06-30 |
| F - Progress | 90.0% |
| F - Booked Units | 18 |
| F - Unbooked Units | 2 |
| G - Start Date | 2012-05-04 |
| G - End Date | 2026-06-30 |
| G - Progress | 15.0% |
| G - Booked Units | 3 |
| G - Unbooked Units | 17 |
| H - Start Date | 2012-05-04 |
| H - End Date | 2026-06-30 |
| H - Progress | 5.0% |
| H - Booked Units | 1 |
| H - Unbooked Units | 19 |
| I - Start Date | 2012-05-04 |
| I - End Date | 2026-06-30 |
| I - Progress | 95.0% |
| I - Booked Units | 19 |
| I - Unbooked Units | 1 |
| J - Start Date | 2012-05-04 |
| J - End Date | 2026-06-30 |
| J - Progress | 100.0% |
| J - Booked Units | 20 |
| J - Unbooked Units | 0 |
| K - Start Date | 2012-05-04 |
| K - End Date | 2026-06-30 |
| K - Progress | 100.0% |
| K - Booked Units | 20 |
| K - Unbooked Units | 0 |
| L - Start Date | 2012-05-04 |
| L - End Date | 2026-06-30 |
| L - Progress | 100.0% |
| L - Booked Units | 20 |
| L - Unbooked Units | 0 |
| M - Start Date | 2012-05-04 |
| M - End Date | 2026-06-30 |
| M - Progress | 100.0% |
| M - Booked Units | 20 |
| M - Unbooked Units | 0 |
| N - Start Date | 2012-05-04 |
| N - End Date | 2026-06-30 |
| N - Progress | 100.0% |
| N - Booked Units | 20 |
| N - Unbooked Units | 0 |
| O - Start Date | 2012-05-04 |
| O - End Date | 2026-06-30 |
| O - Progress | 100.0% |
| O - Booked Units | 20 |
| O - Unbooked Units | 0 |
| P - Start Date | 2012-05-04 |
| P - End Date | 2026-06-30 |
| P - Progress | 100.0% |
| P - Booked Units | 20 |
| P - Unbooked Units | 0 |
| Q - Start Date | 2012-05-04 |
| Q - End Date | 2026-06-30 |
| Q - Progress | 95.0% |
| Q - Booked Units | 19 |
| Q - Unbooked Units | 1 |
| R - Start Date | 2012-05-04 |
| R - End Date | 2026-06-30 |
| R - Progress | 100.0% |
| R - Booked Units | 20 |
| R - Unbooked Units | 0 |
| S - Start Date | 2012-05-04 |
| S - End Date | 2026-06-30 |
| S - Progress | 100.0% |
| S - Booked Units | 20 |
| S - Unbooked Units | 0 |
| RESIDENTIAL - Total Units | 280 |
| RESIDENTIAL - Carpet Area | 12670.0 |
| RESIDENTIAL - Exclusive Area | 0.0 |
| RESIDENTIAL - Open Terrace Area | 0.0 |
| July 2018 | 75.89% |
| October 2018 | 73.3% |
| January 2019 | 74.23% |
| April 2019 | 75.55% |
| July 2019 | 81.52% |
| October 2019 | 82.58% |
| January 2020 | 84.06% |
| April 2020 | 84.85% |
| October 2020 | 85.76% |
| January 2021 | 89.71% |
| April 2021 | 91.6% |
| July 2021 | 92.86% |
| October 2021 | 94.78% |
| July 2026 | 100.0% |