PARKPLUSH
EKDANT SPACES
PARKPLUSH, BESIDE KANHA GALAXY,, NEAR KHATAMBA, WAGHODIA ROAD,
Approved
20th Jul 2019
Pending
30th Jun 2027
Registration No.
PR/GJ/VADODARA/VADODARA/Others/RAA05760/200719
Acknowledgement No.
PR/VADODARA/VADODARA/VADODARA TPO/190709/007713
Project Type
Residential/Group Housing
Approving Authority
Vadodara Urban Development Authority
District
Vadodara
Taluka
Vadodara
State
Gujarat
Project Details
| Project Name | PARKPLUSH |
| RERA Number | PR/GJ/VADODARA/VADODARA/Others/RAA05760/200719 |
| Acknowledgement Number | PR/VADODARA/VADODARA/VADODARA TPO/190709/007713 |
| Project Description | 3 & 4 BHK BUNGLOWS |
| Project Type | Residential/Group Housing |
| Project Status | APPROVED |
| District | Vadodara |
| Taluka | Vadodara |
| Address | PARKPLUSH, BESIDE KANHA GALAXY,, NEAR KHATAMBA, WAGHODIA ROAD, |
| Pincode | 390019 |
| State | Gujarat |
| Approving Authority | Vadodara Urban Development Authority |
| Approved On | 2019-07-20 |
| Start Date | 2019-06-13 |
| End Date | 2027-06-30 |
| Submission Date | 2019-06-28 |
| Months Delayed | 0 |
Area & Cost Details
| Total Land Area | 21793.63 |
| Total Covered Area | 8040.25 |
| Total Open Area | 13753.38 |
| Open Parking Area | 0 |
| Covered Parking Area | 0.0 |
| Covered Parking Count | 0 |
| Parking for Sale Count | 0 |
| Cost of Land | 90100000 |
| Estimated Project Cost | 441435000 |
| Total Project Cost | 531535000 |
Land Details
| Moje | Khatmba |
Promoter Details
| Promoter Name | EKDANT SPACES |
| Promoter Type | PARTNERSHIP FIRM |
| ekd***********@gmail.com | |
| Mobile | 97******** |
| Company Registration No. | GUJVA101211 |
| PAN | AAH******* |
| Date of Incorporation | 2018-09-29 |
| Experience (Years) | 24 |
| Area Constructed (sqm) | 145000 |
| Projects Completed | 8 |
| Ongoing Projects | 4 |
Promoter Partners
| Partner 1 | DILIPKUMAR KISHANCHAND ADVANI |
| PAN | ABO******* |
| Address | 17, NAYNA SOCIETY,, MAKARPURA ROAD |
| Partner 2 | PRASHANT DILIPBHAI ADWANI |
| PAN | BXL******* |
| Address | 17, NAYNA SOCIETY,, MAKARPURA ROAD |
| Partner 3 | SANJIVKUMAR BHATT |
| PAN | AYC******* |
| Address | 452, Vaid Faliyu, Bill Vadodara |
| Partner 4 | PRAFULBHAI RAMESHWARBHAI BHATT |
| PAN | AMV******* |
| Address | Bhatt Faliyu Bill, Padra Vadodara |
| Partner 5 | HARDIKKUMAR ANILBHAI PANDYA |
| PAN | BMR******* |
| Address | Kundhela, Vadodara, vadodara |
Building Blocks
| B - Start Date | 2019-06-13 |
| B - End Date | 2027-06-30 |
| B - Progress | 75.71% |
| B - Booked Units | 106 |
| B - Unbooked Units | 34 |
| B1 - Start Date | 2019-06-13 |
| B1 - End Date | 2027-06-30 |
| B1 - Progress | 100.0% |
| B1 - Booked Units | 1 |
| B1 - Unbooked Units | 0 |
| B2 - Start Date | 2019-06-13 |
| B2 - End Date | 2027-06-30 |
| B2 - Progress | 100.0% |
| B2 - Booked Units | 1 |
| B2 - Unbooked Units | 0 |
| B3 - Start Date | 2019-06-13 |
| B3 - End Date | 2027-06-30 |
| B3 - Progress | 100.0% |
| B3 - Booked Units | 1 |
| B3 - Unbooked Units | 0 |
| B4 - Start Date | 2019-06-13 |
| B4 - End Date | 2027-06-30 |
| B4 - Progress | 100.0% |
| B4 - Booked Units | 1 |
| B4 - Unbooked Units | 0 |
| B5 - Start Date | 2019-06-13 |
| B5 - End Date | 2027-06-30 |
| B5 - Progress | 100.0% |
| B5 - Booked Units | 1 |
| B5 - Unbooked Units | 0 |
| B6 - Start Date | 2019-06-13 |
| B6 - End Date | 2027-06-30 |
| B6 - Progress | 0.0% |
| B6 - Booked Units | 0 |
| B6 - Unbooked Units | 1 |
| B7 - Start Date | 2019-06-13 |
| B7 - End Date | 2027-06-30 |
| B7 - Progress | 100.0% |
| B7 - Booked Units | 1 |
| B7 - Unbooked Units | 0 |
| B8 - Start Date | 2019-06-13 |
| B8 - End Date | 2027-06-30 |
| B8 - Progress | 0.0% |
| B8 - Booked Units | 0 |
| B8 - Unbooked Units | 1 |
| B9 - Start Date | 2019-06-13 |
| B9 - End Date | 2027-06-30 |
| B9 - Progress | 66.67% |
| B9 - Booked Units | 2 |
| B9 - Unbooked Units | 1 |
| B10 - Start Date | 2019-06-13 |
| B10 - End Date | 2027-06-30 |
| B10 - Progress | 0.0% |
| B10 - Booked Units | 0 |
| B10 - Unbooked Units | 1 |
| B11 - Start Date | 2019-06-13 |
| B11 - End Date | 2027-06-30 |
| B11 - Progress | 100.0% |
| B11 - Booked Units | 1 |
| B11 - Unbooked Units | 0 |
| B12 - Start Date | 2019-06-13 |
| B12 - End Date | 2027-06-30 |
| B12 - Progress | 0.0% |
| B12 - Booked Units | 0 |
| B12 - Unbooked Units | 1 |
| B13 - Start Date | 2019-06-13 |
| B13 - End Date | 2027-06-30 |
| B13 - Progress | 0.0% |
| B13 - Booked Units | 0 |
| B13 - Unbooked Units | 1 |
| B14 - Start Date | 2019-06-13 |
| B14 - End Date | 2027-06-30 |
| B14 - Progress | 0.0% |
| B14 - Booked Units | 0 |
| B14 - Unbooked Units | 1 |
| B15 - Start Date | 2019-06-13 |
| B15 - End Date | 2027-06-30 |
| B15 - Progress | 100.0% |
| B15 - Booked Units | 1 |
| B15 - Unbooked Units | 0 |
| B16 - Start Date | 2019-06-13 |
| B16 - End Date | 2027-06-30 |
| B16 - Progress | 100.0% |
| B16 - Booked Units | 1 |
| B16 - Unbooked Units | 0 |
| B17 - Start Date | 2019-06-13 |
| B17 - End Date | 2027-06-30 |
| B17 - Progress | 0.0% |
| B17 - Booked Units | 0 |
| B17 - Unbooked Units | 1 |
| B18 - Start Date | 2019-06-13 |
| B18 - End Date | 2027-06-30 |
| B18 - Progress | 0.0% |
| B18 - Booked Units | 0 |
| B18 - Unbooked Units | 1 |
| B19 - Start Date | 2019-06-13 |
| B19 - End Date | 2027-06-30 |
| B19 - Progress | 100.0% |
| B19 - Booked Units | 1 |
| B19 - Unbooked Units | 0 |
| B20 - Start Date | 2019-06-13 |
| B20 - End Date | 2027-06-30 |
| B20 - Progress | 100.0% |
| B20 - Booked Units | 1 |
| B20 - Unbooked Units | 0 |
| B21 - Start Date | 2019-06-13 |
| B21 - End Date | 2027-06-30 |
| B21 - Progress | 100.0% |
| B21 - Booked Units | 1 |
| B21 - Unbooked Units | 0 |
| B22 - Start Date | 2019-06-13 |
| B22 - End Date | 2027-06-30 |
| B22 - Progress | 0.0% |
| B22 - Booked Units | 0 |
| B22 - Unbooked Units | 1 |
| B23 - Start Date | 2019-06-13 |
| B23 - End Date | 2027-06-30 |
| B23 - Progress | 100.0% |
| B23 - Booked Units | 1 |
| B23 - Unbooked Units | 0 |
| B24 - Start Date | 2019-06-13 |
| B24 - End Date | 2027-06-30 |
| B24 - Progress | 100.0% |
| B24 - Booked Units | 1 |
| B24 - Unbooked Units | 0 |
| C - Start Date | 2019-06-13 |
| C - End Date | 2027-06-30 |
| C - Progress | 66.67% |
| C - Booked Units | 4 |
| C - Unbooked Units | 2 |
| C1 - Start Date | 2019-06-13 |
| C1 - End Date | 2027-06-30 |
| C1 - Progress | 100.0% |
| C1 - Booked Units | 3 |
| C1 - Unbooked Units | 0 |
| D1 - Start Date | 2019-06-13 |
| D1 - End Date | 2027-06-30 |
| D1 - Progress | 100.0% |
| D1 - Booked Units | 1 |
| D1 - Unbooked Units | 0 |
| D2 - Start Date | 2019-06-13 |
| D2 - End Date | 2027-06-30 |
| D2 - Progress | 0.0% |
| D2 - Booked Units | 0 |
| D2 - Unbooked Units | 1 |
| E1 - Start Date | 2019-06-13 |
| E1 - End Date | 2027-06-30 |
| E1 - Progress | 100.0% |
| E1 - Booked Units | 1 |
| E1 - Unbooked Units | 0 |
| E2 - Start Date | 2019-06-13 |
| E2 - End Date | 2027-06-30 |
| E2 - Progress | 0.0% |
| E2 - Booked Units | 0 |
| E2 - Unbooked Units | 1 |
| E3 - Start Date | 2019-06-13 |
| E3 - End Date | 2027-06-30 |
| E3 - Progress | 100.0% |
| E3 - Booked Units | 3 |
| E3 - Unbooked Units | 0 |
| E4 - Start Date | 2019-06-13 |
| E4 - End Date | 2027-06-30 |
| E4 - Progress | 100.0% |
| E4 - Booked Units | 1 |
| E4 - Unbooked Units | 0 |
| E5 - Start Date | 2019-06-13 |
| E5 - End Date | 2027-06-30 |
| E5 - Progress | 100.0% |
| E5 - Booked Units | 1 |
| E5 - Unbooked Units | 0 |
| F - Start Date | 2019-06-13 |
| F - End Date | 2027-06-30 |
| F - Progress | 0.0% |
| F - Booked Units | 0 |
| F - Unbooked Units | 1 |
Inventory Units
| 3 & 4 BHK BUNGLOWS - Total Units | 185 |
| 3 & 4 BHK BUNGLOWS - Carpet Area | 18300.01 |
| 3 & 4 BHK BUNGLOWS - Exclusive Area | 222.0 |
| 3 & 4 BHK BUNGLOWS - Open Terrace Area | 0.0 |
Quarterly Progress
| December 2019 | 17.15% |
| March 2020 | 18.03% |
| September 2020 | 19.61% |
| December 2020 | 22.84% |
| March 2021 | 23.15% |
| June 2021 | 25.26% |
| September 2021 | 27.58% |
| December 2021 | 29.58% |
| March 2022 | 31.86% |
| June 2022 | 31.87% |
| September 2022 | 31.88% |
| December 2022 | 37.77% |
| March 2023 | 39.59% |
| June 2023 | 40.32% |
| September 2023 | 41.95% |
| December 2023 | 42.59% |
| April 2024 | 34.79% |
| July 2024 | 40.43% |
| October 2024 | 41.3% |
| October 2025 | 46.14% |
| January 2026 | 67.6% |
| April 2026 | 68.38% |
Professionals
| Engineer | TARANG K GALANI |
| Licence No. | EOR-01-200 |
The information provided on this page is collated from publicly available resources. PropTech Pulse does not guarantee the accuracy, completeness, or authority of this data and shall not be held liable for any discrepancies. For queries or further assistance, please contact us at pulse@aurumproptech.in